Project BIM Execution Plan
[Project Name]
Revision [Revision Number]
Submitted Date: [Submission Date]
Author Name: [Name]
Author Company: [Name]
Author E-mail: [Name]
BIM Execution Plan Overview
The intent of this project BIM Execution Plan is to provide a framework that will let the owner, architect,
engineers, and construction manager to deploy building information modeling (BIM) technology and
best practices on this project faster and more cost-effectively. This plan delineates roles and
responsibilities of each party, the detail and scope of information to be shared, relevant business processes
and supporting software. The BEP will be revisited and updated at each design phase and at the onset of
construction. All text that is RED is for illustrative and guidance purposes by UCSD only and should not
be construed as a formalized response to this execution plan. Items in red are for reference only and
should be deleted or replaced with relevant project information.
Section 1: Project Information
Section 1.1 General Project Information
Project Name [Project Name]
UCSD Project Number Click or tap here to enter text.
Project Location/Address
Click or tap here to enter text.
Contract Type/Delivery
Method
Choose an item.
Project Size (GSF) Click or tap here to enter text. GSF
Number of Floors Click or tap here to enter text.
General Project Description
Click or tap here to enter text.
Section 1.2 Project Contacts
Below are the primary contacts from each stakeholder for BIM-related topics. These contacts should be
used to obtain information and answer any questions related to their organizations models or
downstream needs relevant to BIM and BIM deliverables.
University Contacts
Role Organization Contact Name Location E-Mail Phone
UCSD Project
Manager
UCSD
UCSD BIM Lead
UCSD
UCSD – [Other]
UCSD
UCSD – [Other]
UCSD
Design Contacts
Role Organization Contact Name Location E-Mail Phone
Architectural
BIM Manager
Structural
Engineer BIM-
responsible
Mechanical
Engineer BIM-
responsible
Plumbing
Engineer BIM-
responsible
Electrical
Engineer BIM-
responsible
Civil Engineer
BIM-responsible
Lighting
Consultant BIM-
responsible
Landscape
Architect BIM-
responsible
[Other] Design
Consultant BIM-
Responsible
[Other] Design
Consultant BIM-
Responsible
Construction Contacts
Role Organization Contact Name Location E-Mail Phone
CM/GC BIM
Manager
Steel
Subcontractor
BIM-responsible
Concrete
Subcontractor
BIM-responsible
Mechanical Sub
BIM-responsible
Plumbing Sub
BIM-responsible
Electrical Sub
BIM-responsible
Utilities Sub
BIM-responsible
Fire Protection
Sub BIM-
responsible
[Other] Sub
BIM-responsible
[Other] Sub
BIM-Responsible
[Other] Sub
BIM-Responsible
Section 1.3 Project Schedule
The table below identifies all stakeholders involved in completing the project phase milestones. Start and
end dates correspond with the approved project schedule. The intent is to list broad time ranges for when
the project team will be developing the design authoring models, construction models, and as-built and/or
record models throughout the project. Stakeholders involved should be the contributing parties assigned
to those tasks within the phases for the project. For discipline and system-specific model element LOD
definitions and authors, the project team should complete a project BIM LOD Matrix (Appendix C of the
University BIM Guide). Minimum University requirements for element LODs are denoted in the
template BIM LOD Matrix.
Project Stage / Milestone
Estimated Start
Date
Estimated
Completion Date
Project Stakeholders
Involved
Design Phase
Design
Model
Programming/Concept
Design
LOD 0-100
Click or tap to
enter a date.
Click or tap to
enter a date.
Click or tap to enter
stakeholders.
Schematic Design
LOD 100-200
Click or tap to
enter a date.
Click or tap to
enter a date.
Click or tap to enter
stakeholders.
Design Development
LOD 200-300
Click or tap to
enter a date.
Click or tap to
enter a date.
Click or tap to enter
stakeholders.
Construction Documents
LOD 200-300 Complete
Click or tap to
enter a date.
Click or tap to
enter a date.
Click or tap to enter
stakeholders.
Construction Phase
Construction
Model
Construction
Modeling/Coordination
LOD 350-400 Complete
Click or tap to
enter a date.
Click or tap to
enter a date.
Click or tap to enter
stakeholders.
Project close-out phase
As-Built/Record Model LOD
Complete
Click or tap to
enter a date.
Click or tap to
enter a date.
Click or tap to enter
stakeholders.
Section 1.4 UCSD Standards
The project team acknowledges receipt of and has developed this BIM Execution plan and all other
project deliverables referencing the following UCSD Standards:
Considered Standard Name
University BIM Guide
File Naming Convention
Space Naming Convention
University Facility Data Specification
(FDS)
Asset Inventory Form (AIF) Requirements
University CAD Standards
Sheet and View Naming Convention
Section 2: Project Goals
Section 2.1 Project goals leveraging BIM
The projects goals are described in the table below as well as the metric being used to measure their
success. The team members have considered the BIM maturity of every stakeholder required to
accomplish each goal and confirm that all goals listed are achievable.
The team members acknowledge the success of each goal can only be attained through a combined team
effort by all required project participants as listed in the tables in this section.
Priority
/
Measur
ement
Goal /
Achieved if
Primary Responsibility
P
riority
High
Goal:
Turn over BIMs for each
design discipline that
represents the final design
intent for use by UCSD to
manage facility operations.
Owner / Operator
Request and approve disciplines and systems requiring
record models with architect and GC. Ensure these
requirements are included as part of the project LOD
matrix.
Architect Develop and execute process to reincorporate any design-
intent changes into record model at end of project.
Partake in all meetings necessary to define facility data
requirements, BIM element needs at turnover, define and
assign model responsibility for record and/or as-built
models to ensure responsibility for each BIM scope is
assigned to correct team member.
Builder / Contractor
Buy-out project from design-build subs with record
model requirements, ensure each sub has a process to
reincorporate design intent changes and update record
models at the end of the project.
Subcontractors
For design-build subs, re-incorporate any design-intent
changes into record model at the end of the project.
Ensure facility data relates back to record model. Ensure
process in place to validate final design intent is reflected
in model.
Measureme
nt
Achieved if:
Builder / Contractor
Field verify during walkthrough using field BIM tools
reviewing record model with each subcontractor having
record model requirements 100% of as-managed assets.
Record models obtained
from project team with:
100% as-managed
components verified in
model (components
specified in FDS) with
accurate locations verified
in field +/- 6 inches.
Architect
Field verify record models for 100% as-managed arch
components in field, +/-6” with GC present.
Subcontractors
Updated record models provided with 100% of as-
managed components located +/- 6 inches from field
locations. Sign-off sheets with list of components
verified, observed in field with representative of CM
present.
Section 3: BIM Uses Summary
The preferred authoring platform for UCSD is Autodesk Revit. For convenience, the BIM Uses matrix
below denotes the UCSD priority for each BIM use as it relates to design and construction
. Priority level
1 BIM uses are required for every design-construction project team using BIM
on University projects.
See the University BIM Guide for more information.
Section 3.1: BIM Uses Matrix
Project Phase
BIM Uses
UCSD
Priority
Applied
to
Project?
Software Applications Used Team Member(s)
Planning Programming 3
Enter other application including
version/year
Organization Name
Site Analysis 3
Enter other application including
version/year
Organization Name
Existing Conditions
Modeling
2
Revit 20XX Other Enter other
application including version/year
Organization Name
Cost Estimation 3
Enter other application including
version/year
Organization Name
Design Design Authoring -
Architecture
1
Revit 20XX Other Enter other
application including version/year
Organization Name
Design Authoring -
MEP
1
Revit 20XX Other Enter other
application including version/year
Organization Name
Design Authoring -
Structure
1
Revit 20XX Other Enter other
application including version/year
Organization Name
Design Authoring -
Civil
1
Civil 3D 20XX Other Enter other
application including version/year
Organization Name
Design Authoring -
Landscape
1
Revit 20XX Other Enter other
application including version/year
Organization Name
Design
Review/Visualization
/Rendering
1
Enter other application including
version/year
Organization Name
3D Coordination 1
Navisworks Manage 20XX Other Enter
other application including version/year
Organization Name
Structural Analysis 3
Enter other application including
version/year
Organization Name
Mechanical/
Energy Analysis
3
Enter other application including
version/year
Organization Name
Other Engineering
Analysis
3
Enter other application including
version/year
Organization Name
Lighting Analysis 3
Enter other application including
version/year
Organization Name
Sustainability (LEED)
Evaluation
3
Enter other application including
version/year
Organization Name
Phase Planning (4D
Modeling)
3
Enter other application including
version/year
Organization Name
Cost Estimation 3
Enter other application including
version/year
Organization Name
Code Validation 3
Enter other application including
version/year
Organization Name
Existing Conditions
Modeling
2
Revit 20XX Other Enter other
application including version/year
Organization Name
Construction Construction
Modeling
1
Revit 20XX Other Enter other
application including version/year
Organization Name
Digital Fabrication 3
Revit 20XX Other Enter other
application including version/year
Organization Name
3D Coordination 1
Navisworks Manage 20XX Other Enter
other application including version/year
Organization Name
Site Utilization
Planning (Logistics)
3
Enter other application including
version/year
Organization Name
Construction System
Design
3
Enter other application including
version/year
Organization Name
3D Control and
Planning
2
Enter other application including
version/year
Organization Name
Record Modeling 1
Revit 20XX Other Enter other
application including version/year
Organization Name
4D Modeling 3
Enter other application including
version/year
Organization Name
Cost Estimation 3
Enter other application including
version/year
Organization Name
Safety 3
Enter other application including
version/year
Organization Name
Commissioning Data 2
Enter other application including
version/year
Organization Name
As-Built Modeling 1
Revit 20XX Other Enter other
application including version/year
Organization Name
Other BIM Use
Enter other application including
version/year
Organization Name
Other BIM Use
Enter other application including
version/year
Organization Name
Other BIM Use
Enter other application including
version/year
Organization Name
Section 3.2 Other Tools
List other supporting tools (computational design, model checking/validation, field data collection, etc.)
that will be used on the project, what they will be used to accomplish, and who will be the primary users:
Other
Tools
Software Applications Used Mobile App? Purpose/Use Team Member(s)
Application name and version.
Purpose or use of application. Organization Name
Application name and
version.
Purpose or use of application.
Organization Name
Application name and version.
Purpose or use of application.
Organization Name
Application name and version.
Purpose or use of application. Organization Name
Application name and version.
Purpose or use of application. Organization Name
Application name and version.
Purpose or use of application.
Organization Name
Application name and version.
Purpose or use of
application.
Organization Name
Application name and version.
Purpose or use of application. Organization Name
Application name and version.
Purpose or use of application. Organization Name
Application name and version.
Purpose or use of application. Organization Name
Application name and version.
Purpose or use of application. Organization Name
Application name and version.
Purpose or use of application.
Organization Name
Section 3.3 BIM Application Version Transition Plan
Describe the project teams plan for revisiting and managing software version upgrades throughout the
project. This is especially important for multi-year projects:
Click or tap here to enter text.
Section 3.4 Training Plan
Certain uses of BIM require multiple team members to access and use applications and tools administered
by one lead team member who may have the most experience with the BIM tool in question. This section
should describe any tools training offered by lead team members to align other contributing team
members on best practices for these tools. List the tool or platform, team member who is offering the
training, the team members who are recommended to receive the training.
Enter description of training program here.
Section 4: Collaboration
Section 4.1 Collaboration Strategy
Describe strategies for collaboration amongst the project team or between the project team and University
stakeholders. These include approaches to alternative methods for setting up the project team offices,
new structures for how meetings are conducted, and supporting tools and technologies for exchanging
information and communicating.
Document Management System:
E.g. BIM 360 Docs, Sharepoint, Box, etc.
Model Collaboration/Exchange Platform or Common Data Environment (CDE) (if different from
DMS):
E.g. BIM 360 Glue, Trimble Connect, Projectwise, Sharepoint, etc. Note if this changes from
design into construction.
Collaboration methods:
Will a Big Room approach be used? Will Lean methodologies be used and in
between which project team members? Will video conferencing or other remote meeting tools be used?
How does the team expect these methods to improve project outcomes?
Section 4.2 Coordinate System and Units
All models will be coordinated around one control point, determined at the beginning of the project.
UCSD will provide survey information to the team.
The composite model must contain a 3D target element that is a visual reference point to assist in aligning
the Revit models. The 3D target also contains the reference data found in the site survey from the project
(e.g. elevation above sea level, compass orientation, etc.)
Replace the example 3D target below with the project specific target.
Section 4.3 Meeting Procedures
The following is a summary list of meetings that the project team will conduct to facilitate progress in the
development and definition of design and planning and execution of construction works facilitated by
BIM. The below list is a starting point and the team should add all meetings related to successfully
executing BIM uses for the specific project in this table.
Meeting Type Project Stage Frequency Participants Location
BIM requirements
design kick-off
Programming Once
BIM Execution Plan
Review - Design
Programming As-needed
FDS Planning - Design SD Once
Design
Coordination/QC
SD/DD/Bidding Once per Stage
Design
Coordination/QC
CD Monthly
BIM Requirements CM
Kick-off
CM Award Once
BIM Execution Plan
Review
Post-Award As-needed
FDS Planning
Construction
Post-Award CM Once
Constructability
Coordination/QC
Construction Monthly
FDS and Model
Deliverable Checks
Design/Construction Each Data
Milestone
Final Punch list Construction Once
Lifecycle BIM Planning Construction As-needed
Any other BIM
meetings that occurs
with multiple parties
Section 4.4 Information Exchanges
See the Information Exchanges worksheet in the companion Excel file. The Information Exchanges
worksheet is intended to communicate all required model delivery and exports required between project
team members to facilitate coordination and follow-on uses of BIM across the project.
Section 4.4 Information Exchanges
The successful use of BIM requires the exchange of models between team members at specified intervals to support collaboration. The table below should capture all
exchanges between team members and include the file type provided to the receipient if the model is a file conversion from the BIM authoring tool used.
Architect
Civil Engineer
Structural Engineer
Mechanical Engineer
Electrical Engineer
Fire Protection
Structural Fabricator
Mechanical Sub
Electrical Sub
Fire Protection Sub
CM/GC (Lead Coordinator)
Architect
IFC 2x3
Revit 2019
Revit 2019
Revit 2019
DWG 2018
IFC 2x3
DWG 2018
DWG 2018
DWG 2018
NWC 2018
Civil Engineer
DWG 2018
DWG 2018
DWG 2018
DWG 2018
DWG 2018
N/A
N/A
N/A
N/A
NWC 2018
Structural Engineer
Revit 2019
IFC 2x3
Revit 2019
Revit 2019
DWG 2018
CIS/2
N/A
N/A
N/A
NWC 2018
Mechanical Engineer
Revit 2019
IFC 2x3
Revit 2019
Revit 2019
DWG 2018
N/A
IFC 2x3
N/A
N/A
NWC 2018
Electrical Engineer
Revit 2019
IFC 2x3
Revit 2019
Revit 2019
DWG 2018
N/A
N/A
IFC 2x3
N/A
NWC 2018
Fire Protection
DWG 2018
DWG 2018
DWG 2018
DWG 2018
DWG 2018
N/A
N/A
N/A
DWG 2018
NWC 2018
Structural Fabricator
Via. Stru. Eng.
N/A
IFC 2x3
N/A
N/A
N/A
IFC 2x3
IFC 2x3
IFC 2x3
IFC 2x3
Mechanical Sub
IFC 2x3
N/A
N/A
IFC 2x3
N/A
N/A
DWG 2018
DWG 2018
DWG 2018
NWC 2018
Electrical Sub
IFC 2x3
N/A
N/A
N/A
IFC 2x3
N/A
DWG 2018
DWG 2018
DWG 2018
NWC 2018
Fire Protection Sub
DWG 2018
N/A
N/A
N/A
N/A
DWG 2018
DWG 2018
DWG 2018
DWG 2018
NWC 2018
Notes:
From
: Data will be delivered
from the party in the format
listed.
To
: Data will be delivered to the party in the format listed.
Design Authoring
Fabrication Installation
Design Authoring
Fabrication
Installation
Section 4.5 Facility Data
Develop and document a plan for collecting facility data from various project team members including
procedures for delivery and storage of data such that data can be accumulated and carried forward from
design to construction and closeout.
Determine if model data will be stored as BIM element attributes or in a separate set of files or database
with a method to relate between the facility dataset and models (e.g. BIMlink, Assemble Systems,
Ecodomus, VueOps, etc.). Define the tool set used to accomplish delivery of the facility data set. If
alternative methods are used, then document how the data will be transferred to the LCM systems and the
steps to accomplish that.
For CM/GC, describe how FDS requirements will be incorporated for each trade contractor into contract
documents/exhibits.
For assets not being modeled but having a facility data requirement, describe the approach that will be
taken to collect and provide to UCSD facility data for these sets of assets.
Section 4.6 File Naming Structure
The model file names below will be used for this project. Refer to BIM Guide Attachment 1 – File
Naming Convention for University file naming requirements. Request the facility ID and project number
from the University PM if uncertain.
File Names for Models Should Be Formatted as:
Facility ID-Project #-Discipline-Style of File-Scope Designation-Scope Modifer-Floor-Zone-File Extension
(example: MCH-9421-A-M-CS-0-0000.rvt)
Design Authoring BIM File Naming
Architectural Model
Architectural Interiors Model
Civil Sitework Model
Civil Utilities Model
Landscape Model
Mechanical Model
Electrical Model
Plumbing Model
Fire Protection
Food Service Model
Structural Model
Telecommunications Model
Audio Visual Model
Lighting Consultant Model
Energy Model
Constructability Model
Estimating Model
Coordination Model
Construction Models BIM File Naming
Drywall and Framing
Masonry
Concrete
Mechanical Model
Electrical Model
Plumbing Model
Fire Protection Model
Mechanical Pipe Model
Process Piping/Med Gas Model
Security Model
Structural Steel Model
Utilities Models
Telecommunications Model
Construction Models
Coordination Models
Section 5: Deliverables Matrix
Section 5.1 Major Model and Data Delivery Schedule
Document the deliverable schedule for models and model-related data that will occur on the project
where the University is involved. The intent of the table below is to provide a
high-level summary of all
of the model-related deliverables across the project. Extend the table for additional project-specific
deliverables if needed. Detailed information exchanges between project team members should be defined
in the Information Exchanges worksheet and Section 7 BIM Use-specific section of this Plan.
Use the Excel version of the table below when filling out this table for a project-specific BIM Execution
Plan.
BIM Submittal Item
File
Sender/
Author
File
Received/
Location
Distributed
or
Available
Stage
Frequency
of Delivery
File Type
Notes
Complete BEP
Development
Schedule
BEP (Design)
Schematic Design
Phase Models for
Review
Facility Data
Deliverables
Schedule
Design
Development
Models for Review
Design
Coordination
Reports (DD)
Construction
Document Models
for Review
Space Management
Floorplans (CD)
Design
Coordination
Reports (CD)
Facility Data
Deliverables
(Design)
Construction
Documents Model
for Bidding
Project-Specific FDS
BEP (Construction)
Construction
Models (for
Coordination)
Submittal and Shop
Drawings
Facility Data
Deliverables
(Construction)
Space Management
Floorplans
(Closeout)
Change Orders
Record Models
As-Built Models
Section 6: Model Quality
Section 6.1 Model and Data Quality Overview
Describe the major strategies in place to ensure model and data quality at each deliverable and
information exchange on the project.
Section 6.2 Model Quality Tools
List tools used in performing or automating model quality and data checks. Confirm these are consistent
with the tools listed in section 3.
Section 6.2 Model Quality Checklists
The lists below are a starting point for best-practices when it comes to model health and maintenance
tasks in Revit. Model data quality checklists are also listed in the tables below. The project team should
use these checklists as a starting point and extend them according to their own firm-specific practices and
needs at the project level between project team members.
Revit
Model Quality Checklist
General and Settings
Does the model authoring firm perform a model audit in Revit week
ly?
Are user-models recreated on a weekly basis?
Are old/un-used views purged on a weekly basis?
Are warnings reviewed and resolved on a weekly basis?
Have the use of design options been limited and used sparingly?
When a design option is accepte
d, has the model been archived and other desi
gn optio
ns removed
that are no longer relevant?
At final turnover, have all design options been removed?
Have all unnecessary raster images been removed in the model?
Revit Model Quality Checklist – Elements
Has the use of Generic Model
category
elements been minimized? Only special circumstances
should elicit the use of a generic model family.
Have all unnecessary Groups in the model and linked model been removed?
Do family and type names describe the element adequately? Avoid any vague naming that does
not give at least a general description of the element.
Has manufacturer/vend
or or project
-
specific wording in the family and type name been avoided?
Revit Model Quality Checklist – Views
Have views not on sheets been limited to working views only? Review views not on sheet and
remove unneeded views on a periodic basis.
Have the use of hidden lines been limited? Use visibility settings and overrides to control category
and element visibility.
Revit Model Qualit
y Checklist
Worksharing
Have linked files/models been placed on unique worksets? Worksets should be tur
ned off when
content is not needed to improve model performance.
Revit Model Quality Checklist – Rooms/Spaces
Have room schedules been reviewed to identify and resolve any unbounded rooms?
Have rooms been reviewed to eliminate any overlapping r
oom or space elements?
Do room number and levels correspond to the intended numbering convention and base level?
Revit Model Quality Checklist
Data
(for elements required in FDS)
Has the FDS Products and Attributes worksheets been completed prior to the start of modeling?
Have all models with FDS requirements added a Shared Parameters file and using approved
names of parameters per the “Master-ATTRIBUTES” worksheet?
Have model elements that require facility data been checked in the parameter “Sc
ope”?
Are all OmniClass Names and Codes parameters populated for in
-
scope elements?
Has the Asset Class parameter been populated per the approved UCSD list?
Has the System name been populated?
Have space (room) names and numbers been populated for the element?
Has the building name been populated in the correct parameter for each element?
Has a general
des
cription been populated in the cor
rect parameter for each element?
Has a tag number been populated for elements requiring a tag? Only assets that need to be
uniquely identified require a tag.
Are UCSD-approved tag abbreviations being used?
Section 7: BIM Use Specific Instructions
This section should be used to document the BIM use-specific information related to each required and
optional BIM use that the project team will employ. The section headings below are recommended;
however, the project team should expand or modify these sections as required by the particular BIM use
in question.
Section 7.1 BIM Use Overview and Expected Benefits
Give a general overview of the BIM use and why it is being applied to the project and expected benefits.
Section 7.2 Team Members Involved
List the team members involved in developing models or other information required for this BIM use.
Section 7.3 BIM Use Deliverables and Project Timing
List the deliverables that will be provided out of the BIM Use both between project team members and to
the University. Ensure these deliverables align with those listed in Section 5. Indicate the frequency and
timing of these deliverables.
Section 7.4 BIM Use Process Information
Use this section to describe any processes related to the BIM use. For example, a coordination/clash
detection BIM use would describe the specific clash tests being used, how the models will be tested and
exports required (e.g. by level, by zone) out of authoring tools to perform clash tests, any meetings
required to review the results, frequency of review, who should attend, where meetings will be held, etc.
Section 7.5 BIM Use Procedural Guides
Use this section to document or attach any best practices or procedural guides that the project team will
use related to the specific BIM use.
Section 8: Record Modeling
The items below should be specifically addressed in the Record Modeling-specific BIM Use section
in
addition to
the general requirements for the BIM use sections described in Section 7.
Section 8.1 Record Modeling Strategy
Define the process of how design or construction models will be updated to represent the final design
intent in the record models. Include the frequency for incorporating RFI responses and change orders
that affect design intent into the design authoring models. Demonstrate how team members will know
definitively if an RFI response affects design intent and a process for how to track and follow through on
these required updates into the design authoring models.
Record models should remove all unused views and design options and purge all unused content to
optimize file size and performance as much as possible.
Section 8.2 Facility Data Strategy
Use this section to describe how facility data will be provided so that it satisfies the requirement to have a
relationship back to the record model deliverables. The most common way to satisfy this requirement is
to store facility data in element parameters, however, some teams may use external tools such as
spreadsheets, cloud-based databases, or local databases, to store facility data and a Revit add-in to connect
the data back to Revit. If external tools outside Revit or add-in’s are to be used, describe how the
University should maintain the use of data and record models after project completion (e.g. can cloud-
based data be pushed to Excel files with a certain element parameter used as a lookup/key for connectivity
back to the model?).
If record models are the final model deliverable in Revit and as-built models for the same system will be
provided in CAD-based formats, describe how facility data provided in as-built models and/or through
other means by CM/GC/subcontractors will be merged and conformed with designer provided facility
data or if they will be conveyed through an external data deliverable. Identify the project team member(s)
who will be responsible for this process.
Section 8.3 Record Modeling Responsibility
Ensure the project BIM LOD Matrix (University BIM Guidelines Appendix C) is complete and has a
designated project team member in the model element author (MEA) column for record modeling when
there is a record model required for a particular system or scope. Ensure the MEA is aware of their record
modeling requirement and document in this section the timing and acceptance criteria for the record
model submission.
Section 9: As-Built Modeling
The items below should be specifically addressed in the As-Built Modeling-specific BIM Use section
in
addition to
the general requirements for the BIM use sections described in Section 7.
Section 8.1 Record Modeling Strategy
Define the process of construction models will be updated to represent the field conditions in the as-built
models. Include the timing for when as-built models will be expected from each trade partner. As-built
models should be provided in native model formats with Revit being the performed modeling platform.
If CAD-based models are to be provided, freeze all annotations, linework, and points.
If as-built models in Revit are provided, they will supersede any Record models. Describe how facility
data from record models and earlier data drops will be merged and conformed into the as-built models or
if they will be conveyed through an external data deliverable.
[Project Name]
FDS Schedule
[Date Created]
[Schedule Author]
Milestone Information Required
Deliverable and Specification/Exhibit
Reference(s)
Responsibility
1 – Design (no later than 100%DD)
Incorporate required UCSD facility
data attribute fields (no values) into
model elements, Spatial Elements
defined (Floor, Area, Space, Room,
etc.)
Design documents and design-intent models.
Design team member according to BEP and LOD
Matrix provides.
Design Team
2 – Design (no later than 50% CD –
varies by discipline)
Models with scope aligned to FDS
(Asset Class defined), full scope of
managed assets listed. Asset ID
should exist at this stage.
Design documents and design-intent models.
Design team member according to BEP and LOD
Matrix provides.
Design Team
3 – Design (no later than 100% CD)
Full scope of managed assets
modeled with Asset Class, Omniclass
Name and Number, Space Name and
Number, Level, Building, Unit Tag,
and all other design team specified
data.
Design documents and design-intent models Design Team
4x* - Procurement
Procurement Facility Data (Common
and Extended Attributes). Update to
any facility data from milestone 1-3 if
they require updates.
Vendor and/or installing subcontractor provides
facility data through procurement facility data
submittals. Incremental and cumulative as
procurement progresses.
Installing Contractor or Vendor
through CM/GC
5x* - Installation
As-Installed Facility Data (ex. Serial
number, Warranty Start Date,
Installation Date)
Installing subcontractors provides facility data and
as-installed facility data submittal. Incremental and
cumulative as construction progresses.
Installing Contractor or Vendor
through CM/GC
*The “x” in the table above denotes deliverables that may be broken down into smaller, partial deliverables and cumulative over the course of the project.