OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 1
Table of Contents
1. INTRODUCTION......................................................................................................... 4
1.1 Purpose............................................................................................................................ 4
1.1.1 OPM SDLC Policy ......................................................................................................... 4
1.1.2 Key Concepts and Principles ........................................................................................ 4
1.2 Scope and Applicability ................................................................................................. 5
1.3 Compliance, Enforcement and Exceptions .................................................................. 6
2. ROLES, RESPONSIBILITIES, AND GOVERNANCE ........................................... 7
3. PROJECT INITIATION............................................................................................ 16
3.1 Need Identified ............................................................................................................. 16
3.2 Executive Sponsor, Business Program Manager, Business Project Manager adopts
the need ......................................................................................................................... 16
3.3 Executive Sponsorship Approval ............................................................................... 17
3.4 Initiate the OPM SDLC ............................................................................................... 17
3.5 Critical Prerequisites to Investment Success ............................................................. 17
4. OPM SYSTEM DEVELOPMENT LIFE CYCLE (SDLC) .................................... 19
4.1 Introduction .................................................................................................................. 19
4.2 SDLC Phases ................................................................................................................. 20
4.2.1 Overview .......................................................................................................................... 20
4.2.2 Determine System Needs Phase....................................................................................... 20
4.2.3 Define System Requirements Phase ................................................................................ 21
4.2.4 Design System Components Phase .................................................................................. 22
4.2.5 Build System Components Phase .................................................................................... 23
4.2.6 Evaluate System Readiness Phase ................................................................................... 24
4.2.7 Deploy the System Phase ................................................................................................. 25
4.2.8 Decommission the System Phase..................................................................................... 26
5. METHODOLOGIES .................................................................................................. 26
5.1 Waterfall ....................................................................................................................... 27
5.1.1 Overview .......................................................................................................................... 27
5.1.2 Strengths .......................................................................................................................... 27
5.1.3 Weaknesses ...................................................................................................................... 27
5.2 Incremental ................................................................................................................... 27
5.2.1 Overview .......................................................................................................................... 27
5.2.2 Strengths .......................................................................................................................... 28
5.2.3 Weaknesses ...................................................................................................................... 28
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 2
5.3 Agile (Scrum) ............................................................................................................... 28
5.3.1 Overview ......................................................................................................................... 28
5.3.2 Strengths: ........................................................................................................................ 31
5.3.3 Weaknesses: .................................................................................................................... 31
6. PROJECT MANAGEMENT FRAMEWORK ........................................................ 31
7. CONFIGURATION MANAGEMENT FRAMEWORK ........................................ 34
8. QUALITY ASSURANCE FRAMEWORK .............................................................. 36
9. RECORDS MANAGEMENT FRAMEWORK ....................................................... 37
APPENDIX A: ACRONYMS ................................................................................................... 43
APPENDIX B: GLOSSARY ..................................................................................................... 46
APPENDIX C: REFERENCES ................................................................................................ 55
APPENDIX D : OPM SDLC PHASE ACTIVITIES ............................................................... 57
Appendix D.1: Determine System Needs Phase Activities ....................................................... 57
Appendix D.2 : Define System Requirements Phase Activities ................................................ 67
Appendix D.3: Design System Components Phase Activities ................................................... 79
Appendix D.4: Build System Components Phase Activities ..................................................... 87
Appendix D.5: Evaluate System Readiness Phase Activities .................................................... 98
Appendix D.6 : Deploy the System Phase Activities .............................................................. 106
Appendix D.7: Decommission the System Phase ................................................................... 113
APPENDIX E: PROJECT CATEGORIES AND PROJECT DOCUMENTATION LEVEL ....... 115
Appendix E.2.1: Project Documentation Level 1 .................................................................... 118
Appendix E.2.2: Project Documentation Level 2 .................................................................... 118
Appendix E.2.3: Project Documentation Level 3 .................................................................... 119
Appendix E.2.4: Project Documentation Level 4 .................................................................... 121
Appendix E.2.5: Project Documentation Level 5 .................................................................... 122
APPENDIX F: SCRUM PROCESS DETAILS .................................................................... 124
Appendix F.1 Determine Systems Needs / Idea Proposed ...................................................... 125
Appendix F.2 Develop and Prioritize Product Backlog.......................................................... 125
Appendix F.3 Sprint Planning Meeting Process ..................................................................... 126
Appendix F.4 Daily Scrum Process ........................................................................................ 126
Appendix F.5 Sprint Functionality Review Process ................................................................ 126
Appendix F.6 Monthly Business-related Performance Metric Reviews ................................ 127
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 3
Revision History
Version Number
Version Date
Revision Summary
1.0
June 2012
Official first OPM version of this document
1.1
April 2013
Address OPM’s Office of Inspector General
audit recommendations especially the one
regarding We recommend that the OCIO
establish an SDLC review process in which the
OCIO must review and formally approve
SDLC work at various milestones for all OPM
system implementation projects. as well as
others.
Executive Summary
The Office of Management and Budget (OMB), the Federal Chief Information Officer and the
Congress have set ever higher standards for the management and performance of information
technology investments within the Federal government. Those standards require IT programs and
projects to achieve consistently successful outcomes that maximize alignment with business
objectives and meet key cost, schedule and performance objectives.
A key to successful IT management is a solid program and project management methodology
that incorporates best government and commercial practices through a consistent and repeatable
process, and provides a standard structure for planning, managing and overseeing IT programs
and projects over their entire life cycle. Industry and government experience demonstrates that
the quality of IT investments is directly proportional to the quality of the management processes
used to acquire and operate the IT products those investments produce. This document is the
U.S. Office of Personnel Management (OPM) System Development Life Cycle (SDLC) policy
and standards guidance.
The OPM SDLC applies to all OPM and contractor personnel who are developing systems,
acquiring systems, managing new systems, and making modifications or enhancement of
existing systems. System developers, users, and all level of OPM management across all
functional areas must adhere to the OPM SDLC or equivalent SDLC processes. The OPM
SDLC is crucial to delivering cost effective information systems for OPM.
The version of this document that is posted to the Web is the official, authoritative version
and supersedes the Information Technology Systems Manager (ITSM) SDLC policy and
standards found in THEO.
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 4
1. INTRODUCTION
This document is provided as a resource for the management and development of OPM
information technology (IT). This document serves as the mechanism to assure that systems
under development are engineered to satisfy the user's requirements, within determined cost,
schedule and quality guidelines. It provides a structured approach to managing information
systems programs and projects beginning with establishing the need for a systems development
or maintenance effort, through development and deployment, and concluding with
decommissioning of the system.
1.1 Purpose
The OPM System Development Life Cycle (SDLC) Policy and Standards document provides
Business Program Managers, Business Project Managers, Technical Project Managers and other
program and project stakeholders guidance and implementation standards for system
development. It is a collection of resources designed to support the approval, planning and life
cycle development of OPM information systems. To deliver cost effective information, it is
crucial that system developers, customers, and all levels of OPM management across functional
areas adhere to the OPM SDLC.
1.1.1 OPM SDLC Policy
OPM IT programs and projects must use an SDLC according to standards outlined in this
document. An SDLC is a consistent and repeatable process which applies to planning,
managing, and overseeing IT programs and projects over their entire life cycle. The OPM
approved SDLC methodologies include Waterfall, Incremental, and Agile. In some cases,
deviating from one of the approved SDLC methodologies could be more advantageous to OPM.
In order to deviate from an approved SDLC methodology, the Technical Project Manager must
present to the SDLC Program Manager and Chief Information Officer (CIO) how the alternative
methodology meets all seven of the SDLC phases as discussed in section 1.2.
1.1.2 Key Concepts and Principles
OPM’s SDLC Policy is based on the following key concepts and principles:
1. Baseline Management. The careful development, monitoring, maintenance and
management of plans, including cost, schedule and business-related performance as
required by the OPM Baseline Management policy is fundamental to the success of all IT
programs and projects. All SDLC options addressed by this document require the use of
effective baseline management methods. For more information, see OPM’s IT Baseline
Management Policy at which can be found in an internal OPM link at Appendix C.1.1.
2. “Line of Sight”. The reporting of actual cost, schedule and performance of an IT
program or project must be easily traced to the original plans. Any reports generated
shall be simple and easy to understand. Major investments requiring Earned Value
Management reports should reference the OPM Baseline Management policy.
3. Accountability. The ClingerCohen Act provides that the OPM IT organization be
operated as an efficient and profitable entity. To meet that goal, the law requires the
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 5
OPM Director to establish clear accountability for IT management activities by
appointing a CIO with the visibility and management responsibilities necessary to carry
out the specific provisions of the Clinger-Cohen Act.
4. Cost and Schedule. Cost estimation for IT programs and projects must be performed
according to Federal standards. All SDLC options addressed by this document require the
use of the Government Accountability Office (GAO) Cost Estimating and Assessment
Guide which can be found in an external link at Appendix C.1.1. Since actual costs will
be reported on www.USASpending.gov and available for public review, it is imperative
that cost estimates be valid. This will also require that each program and project must
establish Service Level Agreements (SLA) or Operating Level Agreements (OLA) within
the cost estimates, if appropriate.
1.2 Scope and Applicability
This policy document applies to all OPM programs with an information technology component
regardless of funding type and funding amounts. There may be an OPM information technology
program and project that is not part of any internal OPM mission or program such as an
interagency or Government-wide effort, this policy document would still apply to those
initiatives. The document applies to both government and contractor efforts.
The use of the OPM SDLC Policy and Standards document applies to all OPM and contractor
personnel who are developing, acquiring or managing new systems or making modifications or
enhancements to existing systems. The use of the document includes the acquisition of all
commercial off-the-shelf (COTS) solutions and Cloud solutions by OPM.
When an analysis of alternatives indicates an IT solution is required to satisfy the identified
requirement, a Cloud solution strategy must be the primary focus for Business Program
Managers, Business Project Managers and Technical Project Managers as required by Vivek
Kundra's "25 POINT IMPLEMENTATION PLAN TO REFORM FEDERAL INFORMATION
TECHNOLOGY MANAGEMENT" document (see Appendix C). If Cloud solutions are found
to not meet OPM requirements, COTS or new systems development may be pursued.
OPM staffs are responsible for ensuring that the systems development and management approach
described in the document is practiced on a day-to-day basis. Because there may be external
Federal agencies (i.e., Government Accountability Office, Office of Management and Budget,
etc.) who may request investment information at a moment’s notice, the OPM staff must be
prepared to provide SDLC documentation or deliverables. This can only be achieved by
following the best practice of utilizing an SDLC and documenting the SDLC deliverables.
If the Technical Project Manager wishes to use an alternative SDLC then it must be equivalent in
all areas of the OPM SDLC as stated in Section 4 of this document. The Technical Project
Manager must provide a presentation to the SDLC Program Manager, other appropriate CIO
staff, and the Business Program Manager or Business Project Manager showing how the
equivalence is achieved for all seven SDLC phases:
Determine System Need (Section 4.2.2)
Define System Requirements (Section 4.2.3)
Design System Components (Section 4.2.4)
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 6
Build System Components (Section 4.2.5)
Evaluate System Readiness (Section 4.2.6)
Deploy the System (Section 4.2.7)
Decommission the System (Section 4.2.8)
The presentation must include a portfolio of documentation deliverables which can be expected.
This document applies to the work of the individuals and groups filling the roles described in
section 2, Roles, Responsibilities, and Governance”.
1.3 Compliance, Enforcement and Exceptions
The CIO will enforce the OPM SDLC process to ensure compliance through periodic reviews of
randomly selected OPM programs with IT components and OPM IT projects. The reviews may
be conducted by the SDLC Program Manager or a designated SDLC subject matter expert
(SME) on behalf of the CIO.
The CIO or an authorized designee is the official approver of submitted deviations and waivers
to the OPM SDLC Policy and Standards.
All OPM SDLC templates or process documents can be utilized in the Agile methodology. If the
Technical Project Manager wishes to use an alternative SDLC then it must be equivalent in all
areas of the OPM SDLC as stated in Section 4 of this document. It is recognized that there will
be alternative Agile documentation that Project Teams will wish to utilize. Waiver and deviation
requests from the OPM SDLC standard are not required when alternative Agile documentation
methods convey the OPM SDLC standards’ requirements.
OPM IT programs or projects currently utilizing the previous SDLC standard, Information
Technology Systems Manager (ITSM), are grandfathered in using the ITSM standards to
complete their implementation. All other OPM IT programs or projects which have just entered
into the initial planning stage are subject to the OPM SDLC policy and standards in this
document.
1.4 Authority
This document is issued under the following authorities:
Clinger Cohen Act of 1996 which requires “the head of each executive agency [to] design
and implement a process for maximizing the value and assessing and managing the
risks of the information technology acquisitions of the executive agency” (Clinger-Cohen
Act of 1996, Section 5122(a))
Office of Management and Budget (OMB) Circular A-130, Management of Federal
Information Resources, which requires the Chief Information Officer to monitor and
evaluate the performance of information technology investments
Paperwork Reduction Act (PRA)
OMB Memorandum, M-11-29, CIO Authorities
Berry, J. (OPM Director) (11/7/2011) “Chief Information Officer Authorities”,
Memorandum for Associate Directors and Heads of Offices. Office of Personnel
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 7
Management
2. ROLES, RESPONSIBILITIES, AND GOVERNANCE
The roles detailed in the following sections are required for new development as well as
maintenance and enhancement programs or projects. An individual can be responsible for
multiple roles especially for the small maintenance and enhancement program or project. For
example, an individual can be both the system developer and the system quality assurance team
of a project. The Business Program Manager or Business Project Manager in collaboration with
the Technical Project Manager must ensure that the roles are addressed within the constraints of
the assigned members to the program or project.
2.1 The Chief Information Officer (CIO)
The CIO has responsibilities in the following areas:
Assigning the Technical Project Manager to the IT project;
Jointly responsible with the OPM Associate Directors, Heads of Offices and Senior
Executives for selecting, assessing and managing information technologies;
Reviewing and approving all information technology-related procurement plans and
strategies before any other OPM governance approvals (e.g., Capital Investment
Committee, etc.);
Approving all IT-related procurements;
Advising the OPM Director on the selection, management and use of information
technology, and on risks related to the management of IT;
Advising the agency head on budgetary implications of information technology decisions
as the Chair of the Investment Review Board (IRB);
Advising the agency head on whether to continue, modify or terminate an IT investment
as one of the TechStat Co-Chairs;
Approving of new and revised baselines for an IT investment;
Authorizing the waiving or deviating from the policy and standards of this document;
Designating CIO staff to be on the Integrated Project Team for the program or project;
Designate CIO staff to be dedicated technical advisors on IT projects if funded by the
program office or by the project;
Chairing the OPM IRB.
2.2 OPM Associate Directors, Heads of Offices and Senior Executives
The OPM Associate Directors, Heads of Offices and Senior Executives have responsibilities in
the following areas:
Selection of the Business Program Manager or Business Project Manager;
Jointly responsible with the CIO for selecting, assessing and managing information
technology;
Ensuring that all IT-related procurement plans and strategies are approved in advance by
the CIO;
Serving as Authorizing Official (for more information, see Authorizing Official below in
Section 2.10.);
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 8
Ensuring compliance with the requirements of this document.
2.3 Chief Financial Officer (CFO)
The CFO obtains the CIO’s concurrence on any budgeting decisions that affect OPM funding for
IT programs or projects.
2.4 Business Program Manager
The Business Program Manager manages one or more major multi-year IT initiatives of such
magnitude they must be carried out through multiple related IT projects and is accountable for
the overall success of the program. Responsibilities include:
Report to the CIO within a matrix organization framework for the life of the program;
Creating and leading an Integrated Project Team;
Leading, coordinating, communicating, integrating program activities;
Ensuring alignment with critical agency priorities;
Ensuring the work efforts achieve the outcome specified within the agency’s business
strategy, including appropriate strategic, life cycle management and capital IT investment
plans;
Managing the project selection, prioritization, evaluation and monitoring, cost schedule
management, risk management, quality management and resource allocations;
Representing the program office and the customers during the life of the IT projects
within the investment;
Preparing cost, schedule and business-related performance metric baselines for their
investments in accordance with the OPM Baseline Management Policy;
Monitoring cost, schedule and performance baselines for the investment;
Responsible for ensuring that IT projects meet budgetary constraints;
Updating the Federal IT Dashboard with current status for major IT investments;
Responding to CIO questions about the investment, including questions related to in-
depth reviews of the investment;
Coordinating the business needs with the Technical Project Manager;
Create and monitor the approved investment baseline and accepting the work products
produced as outlined in the OPM Baseline Management Policy;
Based on the Risk Matrix of the program or project, periodically assess the entire
Program’s or Project’s return on investment (ROI) and successful completion of the
program within baseline milestones.
For the Agile (Scrum) methodology, the Business Program Manager can serve as the
Product Owner. The Product Owner will ensure that the scrum process is supported as
detailed in Appendix F “Scrum Process Details”.
2.5 Business Project Manager
The Business Project Manager manages one IT project and is accountable for the overall success
of the IT project. Responsibilities include:
Report to the CIO within a matrix organization framework for the life of the project;
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 9
Creating and leading an Integrated Project Team;
Leading, coordinating, communicating, integrating and being accountable for the overall
success of the project;
Ensuring alignment with critical agency priorities;
Ensuring the work efforts achieve the outcome specified within the agency’s business
strategy, including appropriate strategic, life cycle management and capital IT investment
plans;
Managing the project selection, prioritization, evaluation and monitoring, cost schedule
management, risk management, quality management and resource allocations;
Representing the program office and the customers during the life of the IT project;
Preparing cost, schedule and business-related performance metric baselines for their
project in accordance with the OPM Baseline Management Policy;
Monitoring cost, schedule and performance baselines for the project;
Responsible for ensuring that the IT project meet budgetary constraints;
Updating the Federal IT Dashboard with current status for the major IT investments;
Responding to CIO questions about the project, including questions related to in-depth
reviews of the investment;
Coordinating the business needs with the Technical Project Manager;
Create and monitor the approved investment baseline and accepting the work products
produced as outlined in the OPM Baseline Management Policy;
Based on the Risk Matrix of the program or project, periodically assess the entire
Program’s or Project’s return on investment (ROI) and successful completion of the
program within baseline milestones.
For the Agile (Scrum) methodology, the Business Project Manager can serve as the
Product Owner. The Product Owner will ensure that the scrum process is supported as
detailed in Appendix F “Scrum Process Details”.
2.6 Technical Project Manager (Technical PM) (Scrum Master)
The Technical Project Manager (Technical PM) has responsibilities in the following areas:
Meeting the objectives of a IT project;
Creating and leading a technical Integrated Project Team;
Coordinating with Business Program Manager or Business Project Manager from the
program office on the development of the IT project;
Selecting a system life cycle methodology, the methods and tools to be used, and the
required controls and deliverables;
Provide overview of the technical approach of the project to the Business Program
Manager or Business Project Manager;
Providing the leadership and management of the SLDC implementation effort and the IT
project team;
Reporting to the Executive Steering Committee on the performance of the IT project.
For the Agile (Scrum) methodology, the Technical Project Manager will serve as the
Scrum Master. The Scrum Master will ensure that the scrum process is managed as
detailed in Appendix F “Scrum Process Details”.
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 10
2.7 Program Management Offices (PMO)
Program Management Offices are responsible for the following:
Planning for and managing implementation of the requirements of the OPM SDLC;
Developing the following program or project requirements:
o The investment’s Work Breakdown Structure
o The investment’s Organizational Breakdown Structure
o The investment’s Responsibility Assignment Matrix
o Summary Earned Value or operational analysis reports
o The investment’s cost, schedule and performance baselines;
Monitoring the investment’s cost, schedule and performance baselines;
Performing operational analysis for the investment;
Providing analytical support to the Business Program Manager or Business Project
Manager in response to CIO’s questions about the investment.
2.8 OPM Contracting Officers
OPM Contracting Officers must consult with the CIO on the development of contract clauses for
investments covered by this document to ensure that the clauses reflect the requirements of this
document. They must work with the CIO in requesting appropriate documentation from
contractors related to validating compliance with this document.
2.9 Configuration Control Board (CCB)
The Configuration Control Board reviews, approves/rejects, and prioritizes change requests
which deals with IT System changes. A CCB must exist for each IT program or project.
2.10 Authorizing Official (AO) (Associate Directors, Heads of Offices and Senior
Executives)
The following role definition for Authorizing Official is from the Information Security and Privacy
Policy which can found by following the link in Appendix C.
The Authorizing Official is an executive with the authority to formally assume responsibility for
operating an information system at an acceptable level of risk to organizational operations and assets,
individuals, other organizations, and the Nation. The role of an AO has inherent U.S. Government
authority and is assigned to Government personnel only. Only an executive can accept risk. Risk
justification must be supported with a compelling business case. With the increasing complexity of
missions/business processes, partnership arrangements, and the use of external/shared services, it is
possible that a particular information system may involve multiple AOs. The AO shall:
Have budgetary oversight for an information system or be responsible for the mission and/or
business operations supported by the system;
Be accountable for the security risks associated with information system operations;
Review Security Assessment and Authorization documentation and discuss concerns with the
Chief Information Security Officer (CISO) as necessary;
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 11
Deny authorization to operate an information system or if the system is operational, halt
operations, if unacceptable risks exist;
Coordinate their activities with the CISO, System Owner (SO), Information System Security
Officers (ISSO), Security Control Assessors, and other interested parties during the security
authorization process;
Establish agreements among AOs, if multiple AOs, and document in the SSP; and
Be responsible for ensuring all activities and functions delegated to an Authorizing Official
Designated Representatives are carried out. The AO is responsible for determining that the
system meets appropriate security requirements and formally approves the system for
operation.
2.11 Executive Sponsor
The Executive Sponsor is a senior business executive who provides approval, guidance and
support for new information system initiatives.
2.12 Chief Architect
The OPM Chief Architect functions as the chief IT architect for all IT initiatives in OPM. The
Chief Architect guides the evolution of the OPM enterprise architecture. The Chief Architect
maintains the architecture vision, technical standards and implementation plan. The Chief
Architect reviews a project’s IT architecture to ensure it aligns with the OPM enterprise
architecture.
2.13 Customer (User)
The customer is a designated user representative from the investment or program office who
supports the Business Program Manager, Business Project Manager and Technical Project
Manager to help define requirements, resolve issues, and test IT user requirements for the
Technical Project team. There can be many customers who support the system development,
enhancement or maintenance process.
For the OPM SDLC, a reference to “user” is synonymous with customer.
2.14 Configuration Management (CM) Team
The CM Team is responsible for adhering to any CIO CM standards or establishing new CM
processes (if none exist). The CM Team maintains the integrity of configuration items
throughout a system’s life cycle. The CM Team can exist at the system, project or program
office level within OPM.
2.15 Configuration Management (CM) Practitioner
The CM Practitioner participates in a CM Team and performs the work required to control
versions of deliverables such as releases (e.g., system, hardware, etc.), documentation, program
artifacts and project artifacts.
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 12
2.16 Operations Team/Network Management Team
The Operations Team/Network Management Team is responsible for operations and
performance of all network systems (internal and external) related to program or project
operations. However, there are certain systems which are outside of Network Management’s
control and authority.
2.17 Integrated Project Team (IPT)
OMB Circular A-11 states: An Integrated Project Team is a multidisciplinary team led by the
program manager to manage the acquisition process. Team members may change somewhat for
different phases of the project, but members must represent those who have a major interest in
the project. Members should be full time or dedicated to the program when needed. Members
should include qualified people able to advise the program manager about technical, business,
project, schedule, procurement, finance, and other issues, and identify users’ concerns about the
acquisition.”
2.18 Requirements Management Team (Requirements Practitioner)
The Requirements Management Team is responsible for the requirements derivation, traceability,
and ensuring that business needs are covered completely throughout the system’s life cycle.
2.19 Quality Assurance (QA) Team
QA Team reports to the Business Program Manager or Business Project Manager. QA Team is
responsible for the formal monitoring of the various work products of the program or project to
ensure standards, policies and procedures are being met in addition to monitoring for compliance
and effectiveness of the processes being used.
2.20 Software Quality Assurance (SQA) Team
SQA Team reports to the Technical Project Manager. SQA Team is responsible for the formal
monitoring of the software products of the program or project to ensure standards, policies and
procedures are being met in addition to monitoring for compliance and effectiveness of the
processes being used. This team is involved in the technical system development level.
2.21 Technical Advisor (Subject Matter Expert (SME))
Technical Advisor is an IT Specialist engaged to provide technical consultation and support in
various IT technical areas of the project to the Business Program Manager or Business Project
Manager. If the Program Office provides sufficient funds to the CIO, the CIO can designate
dedicated technical advisors to support their specific IT project.
2.22 Security and Privacy Team
The Security and Privacy Team provides the program or project with expertise in computer
security, communications security, emissions security, and/or network security and designates a
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 13
security officer to ensure security requirements are satisfied. The Security and Privacy Team is
an integral part of the development and operational management of any system in order to ensure
compliance with Federal Information Security Management Act (FISMA) and National Institute
of Standards and Technology (NIST) guidance. Refer to the Information Security and Privacy
Policy webpages for the contact information. A link to the webpages is located in Appendix C.
2.23 Designated Security Officers (DSOs)
The following role definition for DSOs is from the Information Security and Privacy Policy
which can found by following the link in Appendix C.
The Designated Security Officer (DSO) is appointed by an OPM Program Office or Department
to represent the interests of the program office or department in carrying out the security
functions of the organization. The DSO shall:
Work closely with the CISO, ISSO, and appropriate staff in the program offices to protect
information resources from misuse, whether intentional or unintentional. This effort will
involve reviewing, evaluating, and recommending appropriate information security and
privacy measures along with safeguards;
Conduct periodic security reviews of system facilities to ensure safeguards are
commensurate with the system information being stored, processed, or transmitted;
Update system security documentation and work with the SO and ISSO to assess the
security impact of any information system changes;
Coordinate with the Software Development Managers and ensure security requirements
and issues are addressed consistent with this policy;
Assist the CISO, Information Systems Security Manager, and ISSO in the identification,
implementation, and assessment of common security controls;
Ensure the implementation of any modifications necessary and correct security control
deficiencies found during security assessment testing;
Advise users of the security features and procedures to be used for information systems;
Establish access control criteria and administrative procedures consistent with OPM
policy;
Review and approve new user accounts for system and network access after obtaining
supervisor or management approval;
Ensure the development and timely completion of reports to security and privacy
including those related to POA&Ms, system inventory, security controls testing and
monitoring, contingency plan testing etc.;
Ensure all actual and suspected security incidents and breaches of PII are reported to the
OPM Situation Room (SitRoom);
Assist in the investigation of actual or suspected security incidents and breaches of PII as
appropriate;
Participate in internal/external reviews, inspections, and audits to ensure compliance with
federal laws and OPM policy;
Coordinate with the CISO to advise contracting officers developing or administering
contracts on behalf of OPM regarding the content and implementation of contract clauses
related to OPM’s information security and privacy policy;
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 14
Review acquisition documentation to ensure the inclusion of appropriate information
security-related clauses, consistent with this policy and the Policy on IT Procurement;
Develop and maintain (with the assistance of the CISO) an annually verified list of
systems requiring security authorization;
Coordinate the Security Assessment and Authorization process for program office
systems (See OPM’s Security Assessment and Authorization Procedure for more
information.); and
Attend monthly ITSWG meetings and participate in ITSWG activities.
2.24 System Development Team (Scrum Team)
The System Development Team is responsible for the development or configuration of the
technical design of the system and is the author of the work products (e.g., the program code,
specification, document, module, screen, component, etc.) actually produced by the program or
project in compliance with the system requirements fulfilling the customer needs.
For the Agile (Scrum) methodology, the System Development Team will serve as the Scrum
Team. The Scrum Team will ensure that the system development process is followed as detailed
in Appendix F “Scrum Process Details”.
2.25 System Development Team Lead
The System Development Team Lead is responsible for leading the system development team
assigned to perform the specific task of the project.
2.26 Testing Team
The Testing Team is responsible for testing and verifying that the system functions and performs
as expected, as defined by the system requirements and design documentation.
2.27 System Owner (Certifying Official)
The OPM Associate Directors, Heads of Offices and Senior Executives for the program offices
serves as the System Owners. In addition, the following role definition for System Owner is from the
Information Security and Privacy Policy which can found by following the link in Appendix C.
The System Owner is the official responsible for the overall security, procurement, development,
integration, modification, or operation and maintenance of an information system. The SO shall:
Categorize the information system according to the potential impact to OPM of a breach of
confidentiality, integrity, or availability;
Ensure the implementation of the security controls appropriate to the risk rating established
through the categorization process for the system;
Identify and evaluate security risks and vulnerabilities and establish risk mitigation plans;
Approve System Security Plans (SSPs), and review Memorandums of Agreement or
Understanding (MOA/U), and Plans of Action and Milestones (POA&Ms) and determine whether
significant changes in the information systems or environments of operation require reauthorization;
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 15
Ensure the Information Security and Privacy Policy (ISPP) is followed by all users accessing
the information system;
Ensure the management, operational and technical information security controls are
implemented and operating as intended for all of their information systems;
Ensure system users and support personnel receive the requisite security and privacy training;
Ensure that DSOs are identified and provide security-related support;
Ensure that program office senior management is aware of the resources required to assess
and authorize information systems allowing appropriate work plans and budgets to be developed;
Ensure appropriate staff (system administrators, technical developers, and other staff) are
assigned to coordinate with the DSO in developing Security Assessment and Authorization
documentation (See OPM’s Security Assessment and Authorization Procedure for more
information);
Provide necessary system-related documentation to the CISO;
Take appropriate steps to reduce or eliminate system vulnerabilities identified in the Security
Assessment and Authorization process;
Ensure a Privacy Threshold Analysis (PTA) and if applicable, a Privacy Impact Assessment
are conducted on all systems before implementation or enhancement, in accordance with OPM’s
Privacy Impact Assessment Guide;
Review acquisition documentation to ensure adequate and cost-effective security measures
and safeguards are included; and
Ensure all contracts for IT services, both software and hardware, include clauses
incorporating OPM’s System Security Plan (SSP) and related references.
2.28 Training Team
The Training Team is responsible for training the users and develops all related training
materials as necessary.
2.29 IT Executive Governance Groups
The following are the IT executive governance groups who oversee OPM’s use of information
technology.
Investment Review Board (IRB) - For more detail on the roles and responsibilities of the
IRB, see the IRB charter located at http://theo.opm.gov/References/IT/IRB/charter.asp
Executive Steering Committee (ESC) - Responsible for providing direct oversight of
information technology investments.
2.30 Business Analyst
The Business Analyst provides functional support to the Business Program Manager or Business
Project Manager in the area of Business Process Re-engineering (BPR). The business processes
must be assessed, evaluated, revised, implemented and verified appropriately in order for the
investment to take advantage of the technology solution in an efficient and effective manner.
2.31 Customer Service/Help Desk
The Customer Service/Help Desk (CS/HD) provides support services for both business and
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 16
technical issues of an IT project. Issues can range from technical issues such as password resets
to business issues such as locating documentation for a software enhancement. The program and
project teams must ensure coordination by working with CS/HD to capture specific requirements
and touch points regarding the necessary CS/HD involvement for the program and projects.
2.32 Transition Team
A Transition Team may be required if a new IT project is replacing an older IT system. The
Transition Team will coordinate the necessary business and technical actions required to ensure
that a new IT project is implemented with the least disruption to all customers and capable of
being sustained throughout the life cycle.
3. PROJECT INITIATION
This section describes how the program or project’s initiation before entering the system
development life cycle. Before new system development, maintenance or enhancement begins,
the following steps must occur.
3.1 Need Identified
A program or project begins when a need for technology or a solution to a problem is identified.
This need can arise from the Business/Functional staff or from the Technical staff. This need
may require the development of a new application with new functionality or the
purchase/integration of Commercial Off-the-Shelf (COTS) software or Cloud solution; or the
need may be satisfied by maintenance/enhancement to an existing system.
3.1.1 New Development or Implementation
When the need is for development of a new application/system, implementation of new COTS
product or implementation of a Cloud solution, it must be submitted to the Executive Sponsor,
Business Program Manager or Business Project Manager via a recognized communication
channel such as email, memorandum or issue tracking software. When a need is new to OPM
and there is no assigned Business Program Manager or Business Project Manager, the Executive
Sponsor must initially assess the need and determine if it warrants assigning someone the
responsibility of being the Business Program Manager or Business Project Manager. The
assigned Business Program Manager or Business Project Manager would proceed to Section 3.2
below.
3.1.2 Maintenance or Enhancement
When the need is for maintenance or enhancement requirements to existing systems or Cloud
solutions, it must be documented as a Change Request (CR) which is routed to the Business
Program Manager or Business Project Manager. The Executive Sponsor had previously
authorized the system so review by the Executive Sponsor is not required.
3.2 Executive Sponsor, Business Program Manager, Business Project Manager adopts
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 17
the need
The user discusses the need and the rationale for the need with the Executive Sponsor, Business
Program Manager or Business Project Manager (in some instances the Business Program
Manager or Business Project Manager or user can be the same person).
3.2.1 New Development or Implementation
If the Business Program Manager or Business Project Manager decides the need for the new
system development or implementation is worthy of further development, he/she gathers
information in preparation for Executive Sponsorship approval.
3.2.2 Maintenance or Enhancement
If the Business Program Manager or Business Project Manager decides the need for the
maintenance or enhancement is worthy of further development, he/she gathers information in
preparation for Configuration Control Board (CCB) assessment and determination. If the CCB
approves the need based on the technical functions requested, the Business Program Manager or
Business Project Manager will proceed to Section 3.4 below.
3.3 Executive Sponsorship Approval
The Business Program Manager or Business Project Manager briefs his/her senior management
regarding the need. The executive sponsor then approves or disapproves the project for further
development and ensures that funding is provided to the Business Program Manager or Business
Project Manager.
3.4 Initiate the OPM SDLC
Once the need receives approval for further development, the Business Program Manager or
Business Project Manager begins the activities in the OPM SDLC Determine System Need
phase. The Business Program Manager or Business Project Manager will determine the Project
Documentation Level by selecting the appropriate project categories (i.e., Duration, Risks (High,
Medium, Low), etc.). Appendix E outlines the process to determine the Project Documentation
Level.
3.5 Critical Prerequisites to Investment Success
Four factors are critical to successful communication and development within OPM IT system
development programs and projects. The Business Program Manager or Business Project
Manager for the investment must ensure these factors are satisfied before initiating the OPM
SDLC. They include:
3.5.1 Integrated Project Teams (IPTs )
The Business Program Manager or Business Project Manager must ensure that an Integrated
Project Team (IPT) is formed and engaged throughout the system development phases. The IPT
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 18
facilitates communication and collaboration among all subject matter experts necessary to the
success of the investment. At a minimum, the IPT must have representation from the following
applicable IT functional areas in the CIO organization:
IT Security and Privacy
Accessibility (Section 508)
Records Management
Network Management
Capital Planning and Investment Control.
SDLC
Performance Management (i.e., Earned Value Management, etc.)
3.5.2 Central Document Repository
In order to support the OPM SDLC, the Business Program Manager or Business Project Manager
must set up a central repository for all documentation, reports and artifacts created for the
investment. This central repository must be used as the basis of meeting Configuration
Management program or project requirements.
3.5.3 Secured Funding
The Business Program Manager or Business Project Manager must ensure that funding is
secured before any technical system development is initiated. This may require that the
investment must obtain Capital Investment Committee (CIC) approval for acquisitions over
$250,000.
3.5.4 Familiarization with IT Standards and Federal Laws
There are IT Standards and Federal Laws which the Business Program Manager or Business
Project Manager must follow and ensure that their teams adhere to. These IT Standards and
Federal Laws include:
Reporting Standards.
o Performance reporting is described in the IT Baseline Management Policy. For
additional detail information, please contact the EVM PMO Program Manager
in the CIO IT Investment Management team. OPM’s IT Baseline Management
Policy can be found in the OPM reference at Appendix C.1.1.
Section 508.
o IT components (hardware, software and services) must be accessible to the
disabled community. The OPM Section 508 Policy can be found at:
http://theo.opm.gov/policies/IT_policy-accessibility_0104.pdf
Data Standards.
o The OPM Enterprise Human Resources Integration (EHRI) and OPM Human
Resources Line of Business (HR LOB) investment initiatives have developed
data standards for system interfaces which must be used by those IT systems
dealing with HR data. The EHRI data standards are located at:
http://www.opm.gov/feddata/guidance.asp. HR LOB data standards are located
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 19
at: http://www.opm.gov/egov/documents/architecture/HRLOB_DM.pdf
o In the event that there are additional data standard issues which need to be
brought to the attention of EHRI and HR LOB, there is a Data Governance
Board which is co-chaired by CIO Records Management and EHRI senior
management. Contact the EHRI Program Manager on how to engage the Data
Governance Board.
System Integration.
o The Business Program Manager and Business Project Manager must ensure that
integration occurs when systems are designed. All hardware and software that
are part of the IT solution must work as a cohesive function in meeting the user
requirements in accordance with the OPM Enterprise Architecture. Any external
system interfaces with other Federal agencies must be managed through a
Memorandum of Understanding or Memorandum of Agreement.
IT Procurement.
o Procurement of IT hardware and software must be initiated in the CIO on-line
system named IT Procurement Authorization (ITPA). Approved OPM hardware
and software that meet OPM Enterprise Architecture standards are stored within
ITPA. For hardware and software that are not approved in ITPA, a Business Case
Exception request must be submitted to the OPM Helpdesk. The ITPA is
accessed by submitting a request to the OPM Helpdesk for sign-in capability to
http://sbm.opm.gov/.
o Procurement of IT services must be coordinated with the Office of the CIO
through the contract vehicles (e.g., IT Support Services Blanket Purchase
Agreements, etc.) that the CIO has implemented with the OPM Contracting
Office.
IT Security
o Information security must be integrated into the SDLC at all phases to ensure
appropriate protection for the information that the system will transmit, process, and
store in compliance with the OPM Information Security and Privacy Policy.
Compliance with OPM Information Security and Privacy Policy must be ensured in
coordination with the OCIO IT Security Team.
4. OPM SYSTEM DEVELOPMENT LIFE CYCLE (SDLC)
4.1 Introduction
An important objective of the OPM SDLC is to support various types of development within
OPM. The OPM SDLC provides the framework needed to accomplish work encompassing new
IT system development, implementation of COTS and Cloud solutions, maintenance, and
enhancement. The OPM SDLC describes all the phases of system development, process steps in
each phase, procedures, product templates and checklists needed to support the system
development life cycle. All templates and process documents referenced in this document can be
found in the OPM SDLC WebPages (currently in THEO).
After completing the four steps in the previous “Section 3: Project Initiation”, the Business
Program Manager or Business Project Manager must initiate the SDLC by documenting the
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 20
business need and requirements. The business need documentation will be used by the Technical
Project Manager in developing and implementing the IT system.
4.2 SDLC Phases
4.2.1 Overview
The OPM SDLC consists of the following seven phases:
Determine System Need (Section 4.2.2)
Define System Requirements (Section 4.2.3)
Design System Components (Section 4.2.4)
Build System Components (Section 4.2.5)
Evaluate System Readiness (Section 4.2.6)
Deploy the System (Section 4.2.7)
Decommission the System (Section 4.2.8)
Using the Capability Maturity Model Integration (CMMI) for Development process model as
outlined by the Software Engineering Institute (SEI), each phase includes entry and exit criteria,
and process steps particular to each phase, and identifies the roles, document templates,
procedures, checklists and forms needed for each phase. These phases, combined with the
development methodology, define how the project to manage the system development will be
structured. The processes and resources within the OPM SDLC should be used for all
information systems, systems development, and system maintenance. These phases are
applicable across all information technology environments (e.g., enterprise server, distributed,
web) and apply to contractually developed and in-house developed applications.
4.2.2 Determine System Needs Phase
4.2.2.1 Purpose
The Determine System Need phase is the period in which an information system need is
identified and the decision is made whether to commit the necessary resources to solve the
deficiency.
4.2.2.2 Description
The activities of the Determine System Need Phase begin with the identification of an idea or a
need. A user or system sponsor may identify the need or it may be the result of a strategic
information architecture analysis. For a system which does not currently exist, the need is
documented in a Needs Statement (NS) document. For an existing system, the need is
documented in a Change Request (CR) document. These documents describe the need and
justify the exploration of alternative solutions.
Large-scale development and major system enhancements are described in the Needs Statement
by the project sponsoring organization and approved by the Investment Review Board. Smaller
development efforts, minor enhancements, or maintenance efforts are described in a CR and
approved at the group or division level Configuration Control Board (CCB). After the idea/need
has been documented, alternatives for solving the need are identified as necessary. Decisions are
made on whether or not to continue development of the need.
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 21
Entry Process
After the Customer or Executive Sponsor has identified a need OR a CR has been submitted,
there are tasks associated with the approval of the need and the documentation of the
requirements to meet the needs.
Tasks
The activities are outlined in Appendix D.1
Exit Criteria
A CR package has been approved for an existing system
The Information Technology Investment Analysis Package has been submitted and approved
Needs Statement and User Requirements Document have been approved and baselined for
both new and existing systems
Approval by the appropriate approvers to proceed to next phase when artifacts support the
methodology selected and approvals/directions have been given per the Project Plan and as
outlined in Appendix D.1. Approvers must include the Executive Sponsor, CIO, Technical
Advisor, Business Program Manager or Business Project Manager as appropriate.
4.2.3 Define System Requirements Phase
4.2.3.1 Purpose
The Define System Requirements Phase is the period in which the User Requirements are broken
down into more detailed requirements which can be used during designing and coding.
4.2.3.2 Description
This phase begins formal planning and requirements definition for new projects. The activities of
the Define System Requirements Phase include initial project planning activities. System and
software requirements are formally defined and delineated in terms of data, system performance,
security, and maintainability. All requirements are defined to a level of detail sufficient for
systems design to proceed. For applications requiring electronic signatures see the OPM Policy
on Electronic Signatures in the OPM THEO webpage as linked in Appendix C. Initial
documentation of the Test Plan (Unit & Integration) and the Training Plan begins in this phase
and are updated in subsequent phases.
Entry Criteria:
The program or project has been approved and funded
Needs Statement and User Requirements Document have been approved and baselined for
the new or existing system
Approval by appropriate approvers to exit the previous phase has been granted
Tasks
The activities are outlined in Appendix D.2
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 22
Exit Criteria
The Project Plan, Quality Assurance Plan, Configuration Management Plan, Security Impact
Analysis and Test Plan (Unit & Integration) have been documented and placed under
configuration control
The System Architecture, Software Requirements Specification, Data Specification, FIPS-
199, Privacy Threshold Analysis/Privacy Impact Assessment, Requirements Traceability
Matrix and Training Plan have been approved and baselined
The baselined requirements have been approved as meeting the acceptance criteria for this
cycle
Approval by appropriate approvers to proceed to next phase when artifacts support the
methodology selected and approvals/directions have been given per the Project Plan and as
outlined in Appendix D.2. Approvers must include the Technical Project Manager, Chief
Architect, Business Program Manager or Business Project Manager as appropriate.
A requirements management software tool may be used in the place of a manual matrix. In this
case, the tool would need to be updated in place of the manual matrix.
4.2.4 Design System Components Phase
4.2.4.1 Purpose
The objective of the Design System Components Phase is to transform the detailed, defined
requirements into complete, detailed specifications for the system to guide the work of the
Development Phase. The decisions made in this phase address in detail how the system will
meet the defined functional, physical, interface, and data requirements. Design Phase activities
may be conducted in an iterative fashion, producing first a general system design that
emphasizes the functional features of the system, then a more detailed system design that
expands the general design by providing all the technical detail.
4.2.4.2 Description
This procedure defines the steps required to develop the system design. It gives the user details
on what activities and steps should occur during this phase, which include developing the
Software Design Description, the Database Design Description, Information Systems Security
Plan, User Manual, and training materials. It describes the steps required to document and
baseline system design.
Entry Criteria:
The Project Plan, Quality Assurance Plan, Configuration Management Plan, and Test Plan
(Unit & Integration) have been documented and placed under Configuration Management
(CM) control
The System Architecture, Software Requirements Specification, Data Specification,
Requirements Traceability Matrix, IT Security Planning, and the Training Plan have been
approved and baselined
The baselined requirements have been approved as meeting the acceptance criteria for this
cycle
Approvals by appropriate approvers to exit the previous phase has been granted
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 23
Tasks
The activities are outlined in Appendix D.3.
Exit Criteria:
The Software Design Description document, Database Design Description document,
Information Systems Security Plan, User Manual, Requirements Traceability Matrix, and
Training Materials have been approved and baselined
The Project Plan, Test Plan (Unit & Integration) and Training Plan have been updated. (as
required)
The baselined designs have been approved as meeting the acceptance criteria for this cycle.
Approvals by appropriate approvers to proceed to next phase when artifacts support the
methodology selected and approvals/directions have been given per the Project Plan and as
outlined in Appendix D.3. Approvers must include the Technical Project Manager, Business
Program Manager or Business Project Manager as appropriate.
A testing support tool may be used in the place of Test Plans (Unit & Integration). In this case,
the tool would need to be updated in place of the Test Plans.
4.2.5 Build System Components Phase
4.2.5.1 Purpose
The objective of the Build Phase is to transform the detailed, system design into complete coded
software units and eventually, into an integrated product for release. Each software unit and
subsequent integrated units are tested thoroughly. System documents that support installation
and operations are also developed in this phase.
4.2.5.2 Description
The Version Description Document, Operations Manual, Verification Validation & Test Plan,
and the Installation and Conversion Plan are created as a result of this phase. As software source
objects and system configuration items are completed, they are placed under configuration
control.
Entry Criteria:
The Software Design Description document, Database Design Description document,
Information Systems Security Plan, User Manual, Requirements Traceability Matrix, and
Training Materials have been approved and baselined
The Project Plan, Test Plan (Unit & Integration) and Training Plan have been updated. (as
required)
The baselined designs have been approved as meeting the acceptance criteria for this cycle
Approvals by appropriate approvers to exit the previous phase has been granted
Tasks:
Follow the activities as detailed in Appendix D.4
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 24
Exit Criteria:
Unit and integration testing has been conducted and results meet the acceptance criteria
The Version Description Document, Verification Validation & Testing Plan, Installation &
Conversion Plan, Requirements Traceability Matrix
and Operations Manual have been
approved and baselined
The Project Plan, Test Plan (Unit & Integration), Training Plan and Training Materials have
been updated (as required)
Approvals by appropriate approvers to proceed to next phase when artifacts support the
methodology selected and approvals/directions have been given per the Project Plan and as
outlined in Appendix D.4. Approvers must include the Technical Project Manager, Business
Program Manager or Business Project Manager as appropriate.
4.2.6 Evaluate System Readiness Phase
4.2.6.1 Purpose
This objective of the Evaluate Phase is to ensure that the system as designed and built satisfies
the requirements of the user. Whenever possible, independent testers measure the system's
ability to perform the functions that are required by the customer and ensure an acceptable level
of quality and performance. Once the phase is complete, it will be evident whether or not the
system is ready for operation. This function shall be the responsibility of the system testers and
will be heavily supported by the user participants.
4.2.6.2 Description
The Verification, Validation & Testing Plan, Test Results & Evaluation Report, Installation &
Conversion Plan, User Manual, and Training Materials are updated, tested (if applicable), and
finalized in this phase. The Systems Assessment and Authorization package is created in this
phase. As work products are created they are placed under configuration control.
Entry Criteria:
Unit and integration (including regression) testing has been conducted and results meet the
acceptance criteria
The Verification, Validation, & Testing Plan, Installation & Conversion Plan, Requirements
Traceability Matrix,
and Operations Manual have been approved and baselined
The Project Plan, Test Plan (Unit & Integration), Training Plan, and Training Materials have
been updated. (as required)
Technical Project Manager approval with Business Program Manager or Business Project
Manager concurrent approval to exit the previous phase has been granted
Tasks:
Follow the activities as detailed in Appendix D.5
Exit Criteria:
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 25
The System Assessment and Authorization has been approved by the Authorizing Official
The Customer, Business Program Manager or Business Project Manager and IT Project
Manager has approved the baselined testing results as meeting the acceptance criteria for this
cycle
Business Program Manager or Business Project Manager, IT Project Manager, Software
Quality Assurance and the Customer have approved the Test Results and Evaluation Report,
Version Description Document, Installation & Conversion Plan, User Manual, updated
Requirements Traceability Matrix, and the applicable Training Materials
The Project Plan has been updated to reflect activities of this phase and has been placed
under CM control
The Phase Exit Review meeting has occurred and Technical Project Manager approval along
with IPT members, Business Program Manager or Business Project Manager concurrent
approval to proceed to the next phase has been granted as outlined in Appendix D.5.
4.2.7 Deploy the System Phase
4.2.7.1 Purpose
Deploy the System Phase is the final phase of the development life cycle, when the system is
released initially to a pilot site and then into the production environment. All necessary training
for using the system is accomplished.
4.2.7.2 Description
This phase is to install the system in a production environment for use by the intended user. The
production environment is prepared for system installation, which includes the physical
environment as well as hardware and software components. Once the system is installed, a
thorough test of the system installation is conducted. User training is also conducted to prepare
the user for new system functionality or system changes. The Business Program Manager or
Business Project Manager and Technical Project Manager verify that the installed system meets
all requirements, all specifications and all deliverables have been received.
Entry Criteria:
Test Results & Evaluation Report, and Requirements Traceability Matrix have been
approved and baselined
System Assessment and Authorization have been approved and baselined
The Project Plan, Test Plan (Unit & Integration), Training Plan, Training Materials, User
Manual, Installation & Conversion Plan, Operations Manual, Version Description Document
have been updated (as required)
Established Service Level Agreements (SLA) or Operating Level Agreements (OLA) for the
project have been signed by all parties and ready for implementation
Technical Project Manager approval along with IPT members, Business Program Manager or
Business Project Manager concurrent approval to exit the previous phase and deploy the
system has been granted.
Tasks:
Follow the activities as detailed in Appendix D.6
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 26
Exit Criteria:
System has been installed and is operational
System Sign-off Package has been approved by Technical Project Manager approval along
with Business Program Manager or Business Project Manager concurrent approval
Project Plan has been updated. (as required)
4.2.8 Decommission the System Phase
4.2.8.1 Purpose
The Decommissioning a System phase is the period in which a system is completely taken off
line, or a portion of a system’s functionality (due to duplication in another system) is removed.
This phase is conducted to retire a system.
4.2.8.2 Description
Once the decision to decommission a system has been made, the activities of the
Decommissioning a System Phase begin with the completion of the decommission form. This
form documents the information and coordination necessary to end the target systems life cycle.
The system is decommissioned following the steps in the Decommissioning procedure. Systems
that have interfaces to the targeted system are checked to verify the decommissioning does not
adversely affect them. As a result of the system being decommissioned, affected business
processes and policies are updated. Once the system has been decommissioned, a formal system
close out meeting is conducted.
Entry Criteria:
User/Executive Sponsor has identified a need OR a CR has been submitted
Business Program Manager or Business Project Manager approval as well as CIO approval to
decommission a system
Tasks:
Follow the activities as detailed in Appendix D.7
Exit Criteria:
A system, or part of a system, is decommissioned.
System components and artifacts have been archived or disposed of.
Completed Decommission Form with input and approval from the IT Security Team and
approved by CIO and Business Program Manager or Business Project Manager.
Affected/interfacing systems continue to operate.
Meeting Minutes which document that all parties are aware of decommission requirements.
5. METHODOLOGIES
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 27
A process model covers the whole life cycle and defines each phase as described in Section 4
above. It also defines the tasks and activities to be performed within that phase. There are
several systems development life cycle methodologies. This section provides an overview of the
methodologies that are commonly used within OPM. The Technical Project Manager should
select a system life cycle methodology based on the nature of the program and application, the
methods and tools to be used, and the required controls and deliverables. The Technical Project
Manager integrates the selected life cycle methodology with the phases of the OPM SDLC in
developing the project's schedule.
5.1 Waterfall
5.1.1 Overview
The waterfall (or "grand design") model is a program strategy which is a "once-through, do-
each-step once" strategy. In waterfall, each process as described in Section 4.2 above is
performed in sequence, and each process is completed before proceeding to the next process in
the sequence. For example, requirements are not documented until the need is approved.
Likewise, software build (construction) does not begin until the analysis and design are
complete.
5.1.2 Strengths
Waterfall provides a structured, disciplined method for system development, and can be
useful for maintenance projects, and small, new projects with clearly defined and understood
requirements.
Waterfall methodology is well-suited to systems of record where the current process (or lack
thereof) can proceed until delivery without negative impact to the organization.
5.1.3 Weaknesses
Waterfall can prove to be a risky and inflexible strategy. With only a single pass through the
process, integration problems often surface too late in development, and a completed product
is not available until the very end of the process.
The long period between project start and product delivery can discourage customer
involvement and lead to a system which does not meet changing customer requirements.
5.2 Incremental
5.2.1 Overview
The incremental model of systems development performs the waterfall approach in overlapping
phases attempting to compensate for the length of waterfall model projects by producing usable
functionality earlier. For those projects whose expertise lies with the waterfall model and may
not be able to secure the services of certified Scrum Masters, the incremental methodology is an
acceptable solution in lieu of the Agile (Scrum) methodology.
The incremental model of systems development involves sets of requirements that are
implemented in a series of small subprojects which follow the seven SDLC phases. A project
using the incremental model may start with general objectives. Then some portion of these
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 28
objectives is defined as requirements and is implemented as a subproject, followed by the next
portion of the objectives until all objectives are implemented within all subprojects.
Incremental model follows the same phases as the OPM SDLC within each small subproject
using the entry, activities and exit criteria.
5.2.2 Strengths
Orderliness appeals to management
Facilitates allocation of resources
Early functionality
Does not require a complete set of requirements at the onset
Can size the increments based on available resources
Well-suited to systems of record where the current process (or lack thereof) no longer meets
the organization's needs and must be replaced more rapidly than a big-bang delivery would
allow
5.2.3 Weaknesses
Beginning with less defined general objectives may be uncomfortable for project team
members
Requires clean interfaces between modules
Tendency for difficult problems to be pushed to the future so that the initial promise of the
first increment is not met by subsequent products
5.3 Agile (Scrum)
5.3.1 Overview
Agile system development for OPM must adhere to the Manifesto for Agile Development (Beck,
2001) which is characterized by the following in the publication:
Direct involvement of the customer in product development
Use of multiple development iterations to learn about and evolve the product
Customer willingness to share in the responsibility for decisions and risk
Agile system development methodologies meet the above by the implementation of a number of
phases that are repeated in cycles, with a feedback loop after each cycle is completed. The
project team learns from the preceding cycles and plans the next cycle in an attempt to converge
on an acceptable solution. At the discretion of the customer, the project team may release a
partial solution. The characteristics of Agile development include:
Iterative structure - structured around iterations that are designed to find and complete the
solution
Justintime planning - highest priority features are planned first and executed upon.
Planning is finely detailed for immediate features, coarsely detailed for features to be
developed later.
Critical mission projects - Certain projects are considered high risk because of the
complexity and uncertainty associated with the project. With that high risk comes high
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 29
business value. They are undertaken because their successful completion is critical to the
enterprise.
Thrives on change through learning and discovery - The learning and discovery can come
about only with the customer being heavily involved in the project.
Some of the best practices within the Agile methodology are:
Teams should be co-located, long-lasting, and persistent
Do not transition knowledge support of a product to another team
Start staffing project teams with a focus on resource versatility so that the starting core
can do multiple tasks while experts are on-board
Scrum is one of the current popular Agile system development methodologies. The Scrum
software development team is selfdirected, operates in successive iterations (typically 2 to 3
weeks as indicated by best practices), holds daily team standup meetings of no longer than 15
minutes, continuously offers the customer demos of the current solution, and adapts its
development plan at the end of each iteration.
It is the Product Owner who defines the functions and features that the team prioritizes into
phases and builds a phase at a time in iterative cycles. The process allows the customer to change
functions and features as more of the solution depth is uncovered through the previous iterations.
A diagram of the Scrum life cycle (Figure 1) is presented below:
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 30
Figure 1: The Scrum Lifecycle
The Scrum Lifecycle diagram illustrates a general overview of the Scrum process. Scrum uses
the sprint as the basic unit of development. Each specific function or task is defined within the
sprint and can take no longer than six weeks for development as well as are "timeboxed" (i.e.
restricted to a specific duration). Each sprint is preceded by planning meetings, where the tasks
for the sprints are identified and an estimated commitment for the sprint goal is made. Scrum
reviews are conducted where the progress is reviewed and lessons for the next sprint are
identified. During each sprint, the team creates finished portions of a task or product. These
finished portions must be formally accepted and approved by the Product Owner and Scrum
Master using the appropriate SDLC Phase Exit Review procedures and documentation (defined
in Section 4.2 “SDLC Phases” above) before additional sprints are initiated or planned. The
functionality or tasks that go into a sprint is pulled from a product backlog, which is a prioritized
list of requirements, and is determined by sprint planning meetings.
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 31
For a more detailed overview of Scrum, the Scrum Process Details can be found in Appendix F
of this document.
5.3.2 Strengths:
Avoids all management issues in processing scope change requests
Does not waste time planning uncertainty
Provides maximum business value within the given time and cost constraints
Delivers finished, tested, usable code with each iteration
Provides flexibility and quick feedback which is used to plan the next iteration
Well-suited to systems of differentiation and innovation so that stakeholders can see a
resolving picture of unfamiliar technology/processes
Utilizes the Rolling Wave planning method which embraces the Lean ideal of making
decisions at the last responsible moment, when the possible information is available, and
maximizes flexibility and planning accuracy
Uses empirical methods to monitor progress and direct change, rather than use of definitive
methods (i.e. Waterfall) to try to predict progress and stop change
Assists in:
o Strategic Planning (Strategic Product line goals)
o Product Planning (Strategic product goals)
o Lean/Six Sigma (Specific problems to solve)
o Release Planning (Large functional goals)
o Sprint Planning (Small, well-defined work items)
o Daily Scrum (Tactical organization & execution)
5.3.3 Weaknesses:
High reliance on meaningful daily customer involvement leads to higher levels of risk
Cannot identify precisely what will be delivered at the end of the project since requirements
may change
Changes in scope results in rework through multiple iterations which can increase cost
6. PROJECT MANAGEMENT FRAMEWORK
Project management is the application of knowledge, skills, and techniques to project activities
in order to meet or exceed stakeholder needs and expectations from a project. Meeting or
exceeding stakeholder needs and expectations invariably involves balancing competing demands
among:
Scope, time, cost and quality
Stakeholders with differing needs and expectations
Identified requirements (needs) and unidentified requirements (expectations)
The Business Program Manager, Business Project Manager, Technical Project Manager and the
Project Teams must follow project management best practices during the SDLC implementation.
The Project Management Institute (PMI) is a world-wide organization which has been
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 32
recognized as the expert in project management standards. PMI has defined the standards in
their publication called the Project Management Book of Knowledge (PMBOK). The PMBOK
uses the following 5 process areas with the appropriate procedures:
1. Project Initiation
a. Collect historical information
b. Determine Project objectives
c. Determine high-level deliverables, estimates
d. Determine high-level constraints and assumptions
e. Determine business need
f. Develop product description
g. Define Project Manager responsibilities
h. Determine high-level resource requirements
i. Finalize Project Charter
2. Project Planning
a. Create scope statement
b. Determine Integrated Project Team (IPT)
c. Create Work Breakdown Structure (WBS)
d. Finalize the IPT
e. Create WBS Dictionary
f. Create network diagram
g. Estimate time and cost
h. Determine critical path
i. Create risk management plan
j. Develop schedule
k. Develop budget
l. Determine communication requirements
m. Determine quality standards
n. Risk identification, qualification, quantification and response planning
o. Iterations go back
p. Create other management plans
i. Scope
ii. Schedule
iii. Cost
iv. Quality
v. Staffing
vi. Communications
vii. Acquisition
q. Create project control system
r. Final project plan development
s. Gain formal project plan approval
t. Conduct Project Kickoff meeting
3. Project Execution
a. Execute project plan
b. Manage project progress
c. Complete Work Packages
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 33
d. Distribute information
e. Quality Assurance
f. Team Development
g. Progress Meetings
h. Identify Changes
i. Work Authorization
j. Manage by Exception to Project Plan
4. Project Control
a. Integrated change control
b. Project performance measurement
c. Performance reporting
d. Scope change control
e. Quality control
f. Risk monitoring and control
g. Schedule control
h. Cost control
i. Scope verification
j. Compliance with all plans
k. Project Plan updates
l. Corrective Action
5. Project Closing
a. Acquisition audits
b. Product verification
c. Financial closure
d. Lesson learned
e. Project performance reporting closure
f. Formal acceptance
g. Project archive (includes contract close-outs)
For more detail information in regards to the above processes and procedures, the IT project
team should consult or procure a copy of the PMBOK from the PMI.
In addition to the PMI, the Federal Acquisition Institute (FAI) has developed a Program
Management and Project Management certification program for Federal Program and Project
Managers. FAI established the necessary competencies, training, and experience requirements
for program and project managers in civilian agencies to become certified to manage the
acquisition-related aspects of projects. Information about the certification program can be
viewed on the FAI website at http://www.fai.gov/certification/management.asp.
6.1 OPM SDLC and Project Management
The OPM SDLC and Project Management best practices are interwoven within the IT solution
implementation. One cannot exist without the other when IT projects are planned, developed,
tested and implemented. For each of the SDLC phases, the Business Program Manager and
Business Project Manager must ensure that the appropriate Project Management process is
adhered to as follows:
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 34
Project Initiation process must be part of the Determine System Need phase;
Project Planning process must be part of the Determine System Need, Define System
Requirements and Design System Components phases;
Project Execution must be part of the Design System Requirements and Build System
Components phases;
Project Control must be part of the Evaluate System Readiness phase;
Project Closing must be part of the Deploy the System and Decommission the System phase.
7. CONFIGURATION MANAGEMENT FRAMEWORK
Configuration Management is the discipline of identifying the configuration of a system at
discrete points in time for the purpose of systematically controlling changes to the configuration
throughout the system life cycle. The components of configuration management are:
Section 7.1: Software Configuration Identification
Section 7.2: Configuration Control
Section 7.3: Baseline Management
Section 7.4: Configuration Status Accounting
Section 7.5: Configuration Auditing
7.1 Software Configuration Identification
Configuration identification involves the effective management of the development of the system
by careful definition of its baseline components. Changes to these components are also defined
since these changes, together with the baselines, specify the system evolution. Configuration
identification also involves identifying what information has been approved for concurrent use in
the project, who owns the information, how the information was approved for CM control, and
the latest approved release. At a minimum, the following shall be selected as Configuration Items
(CIs):
The system itself, defined as the top-level CI.
All Commercial Off-the-Shelf (COTS) software and hardware needed for the system (or
application) to function or required for procurement.
Application software components already designated as CIs.
Project support software essential for system maintenance, including debuggers, test
scripts, and configuration checkers.
7.2 Configuration Control
Configuration control involves the process and procedures for designating the level of control
through which each work product must pass; identifying the persons or groups with authority to
authorize changes and to make changes at each level; and the steps to be followed to obtain
required authorization for changes, to process change requests, to track changes, to distribute
changes, and to maintain past versions. Configuration control is initiated after the Functional
Baseline (FBL) is established and extends to include the Allocated Baseline (ABL) and Product
Baseline (PBL). Change control provides the mechanism to build software systems for tests that
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 35
have a known configuration and can be exactly reproduced.
7.3 Baseline Management
Once a baseline (made up of baselined documentation) has been established, it should not be
changed without a formal action. The typical baselines used for information systems are the
FBL, ABL, and PBL. Baselines are normally established successively with each one adding
more detail about the final system. Each project Configuration Management Plan (CMP) must
list all required contents of each baseline.
Functional Baseline - The FBL is the approved documentation that describes the system
(or product) functional characteristics. After approval of the User Requirements
Document during the Define System Needs phase, the FBL is established. This baseline
should be maintained throughout the life cycle of the project.
Allocated Baseline - The ABL is the approved documentation that describes the design of
the functional and interface characteristics that are allocated from a higher level CI. All
fielded systems shall have an ABL to support test, training, and maintenance. This
baseline shall be maintained throughout the life cycle of the project, usually by the
organization responsible for maintaining the functional products.
Product Baseline - The PBL consists of completed and accepted system components and
the corresponding documentation that identifies these products. This baseline supports
the ability to accurately duplicate software, purchase COTS, and modify COTS. The PBL
includes source code on electronic media, COTS (hardware and software), maintenance
and user manuals, vendor-supplied COTS manuals, purchase specifications for modified
COTS, system and hardware drawings, Version Description Documents, and code
listings. This baseline should be maintained throughout the life cycle of the project.
7.4 Configuration Status Accounting
Configuration Status Accounting (CSA) records, stores, maintains, correlates, and reports the
status of an evolving CI throughout the system life cycle. CSA requires that all software and
related documentation be carefully tracked from initial development, through the approval or
disapproval of changes, to the implementation of changes. CSA records and monitors all changes
to baselines. As a result of this effort, CSA will maintain traceability of the hierarchy of
requirements from the stated user need at the top, through the functional and allocated baseline
documentation, and down to the lowest level of the product baseline. The information required
for comprehensive CSA includes:
Baseline name, version, and designation
Date and time at which the baseline was established
Date and time when each CI and change was included in the baseline
Description of each CI
Status of each change request
Description of each change.
7.5 Configuration Auditing
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 36
Configuration Auditing is a formal review of a project for the purpose of assessing compliance
with the CM plan. The purpose of Configuration Audits is to ensure that the functional
requirements have been met by the delivered CI and to ensure that all physical attributes listed in
the design requirements have been met by the CI to be delivered. Configuration audits shall be
performed for application software, COTS products, and customized products that satisfy a
functional requirement. The configuration audit is the responsibility of the system tester and the
project configuration manager.
All project and contractor personnel who are developing, acquiring, disposing, operating, or
maintaining project systems should use documented configuration management methodology to
ensure that system requirements are clearly defined and controlled throughout the life of the
system and that the operational system satisfies the needs of the project. To accomplish these
tasks, the following should be accomplished:
A project CMP must be developed as required in the Define System Requirements Phase
(Section 4.2.3.2) using the OPM CMP framework if available.
Configuration baselines must be established, documented and controlled using a formal
change control processes.
Fielded systems must be documented and software releases and system upgrades
documented and controlled using a formal process.
8. QUALITY ASSURANCE FRAMEWORK
Project Quality Assurance Management includes the processes required to ensure that the
project will satisfy the needs for which it was undertaken. It includes all activities of the overall
management function that determine the quality policy, objectives, and responsibilities and
implements them by means such as quality planning, quality control, quality assurance, and
quality improvement, within the quality system.
To be unbiased, quality assurance needs to have organizational freedom and authority from
persons directly responsible for developing the software product or executing the process in the
project. A quality product or service, by definition, meets or exceeds the need to which the
product or service is applied. This process consists of four activities:
Section 8.1: Process Implementation
Section 8.2: Product Assurance
Section 8.3: Process Assurance
Section 8.4: Assurance of Quality Systems
8.1 Process Implementation
The quality assurance process should be responsible for conducting ongoing evaluations of
software acquisition/initiation, design, development, evaluate, deploy, and supporting process
activities and the resulting software products to assure that each process, activity, and task
required or described in plans is being performed in accordance with those plans. It also assures
that each software product required by a relevant process exists and has undergone software
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 37
product evaluations, testing, and problem resolution, as required. A plan for conducting the
quality assurance process activities and tasks is developed, documented, implemented, and
maintained for the life of the project.
8.2 Product Assurance
Product assurance ensures that all the plans required are documented, comply with requirements,
are mutually consistent, and are being executed as required. All software products and related
documentation should adhere to the plans. Software products that have fully satisfied contractual
requirements may be assumed to be acceptable to the user. The quality assurance process is
performed to assure that all products exist, have undergone evaluations in accordance with the
plans for conducting quality assurance activities and tasks, and satisfy the acceptance criteria.
The results of verification, validation, and other processes to satisfy product assurance tasks may
be used.
8.3 Process Assurance
Process assurance ensures that those software life cycle processes (requirements, design, build,
evaluate, deploy, and supporting processes, including quality assurance) employed for the project
adheres to the plans. Internal software engineering practices, development environment, test
environment and libraries must comply with the requirements. The user needs the required
support and cooperation to carry out these processes. This means that the staff assigned to the
project has the skill and knowledge needed to meet the requirements and receive any necessary
training.
8.4 Assurance of Quality Systems
A quality product or service, by definition, meets or exceeds the need to which the product or
service is applied. With this as a framework, a few significant characteristics of a quality product
or service are:
Meets the user's need
Meets the user's requirements
Meets the user's expectations
Allows the user to accomplish a task to which the product or service applies
Is available to the user when the task to which the produce or services applies is
accomplished
For a continuing product or service, uniformly and consistently meeting the user's need,
requirement, and/or expectation allows the user to "trust" the continued use of the product
or service
Meets the user's affordability or other constraints
In summary, a quality product or service meets expectations and is useful, available, consistent,
and affordable when applied to a task.
9. RECORDS MANAGEMENT FRAMEWORK
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 38
The Records Management Profile recommends that agencies embed records management
requirements in the earliest stages of their SDLC. The Profile can be found by referring to
Federal Enterprise Records Management Profile, Sections 4.1.1 through 4.1.6;
http://www.archives.gov/records-mgmt/policy/rm-profile.html.
The document on the following page is a checklist to assist OPM program and project managers
integrate records management requirements into their IT system SDLC process. The checklist
identifies where in the SDLC process the records management review and approval should take
place to ensure that sound records management practices are incorporated into the development
of the proposed IT system.
The checklist provides two to six basic questions about records management and recordkeeping
for each phase of the OPM SDLC life cycle process. The checklist questions are intended to
begin a more detailed discussion with agency records managers, IT and Capital Planning and
Investment Control (CPIC) staff, and program managers and staffs that will help identify
recordkeeping requirements in each phase, with a great emphasis on identifying records
management requirements at the earliest stages of project planning, initiation and requirements
gathering.
The checklist is intended to become a part of the IT system documentation and will be used
throughout the system life cycle. Please use the comments field for any additional information.
Records Management Checklist
IT System: (Name of IT System)
OPM DIVISION: (Name of Division)
IT System Owner: (Name of IT System Owner)
All electronic records should be managed following the National Archives regulations, NARA
Records Management Guidance and Regulations, subchapter B, Record Management, Part 1234
at http://www.archives.gov/about/regulations/part-1234.html.
Phase 1: Determine System Need
Requirement
Met?
Indicate
FM = Fully
Met
PM = Partially
Met
NM = Not
Met)
CIO Records
Management
Approval
1) Is the OPM Records Officer
included from the beginning in the
system design process?
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 39
2) Are records identified that support
the business process?
3) a. Do current record schedules
apply to the new system?
b. Is a new record schedule
required because of changes in the
records?
4) Have you notified your division
Records Coordinator and the OPM
Records Officer, that this system
should be included as an update to the
division file plan?
5) Has the appropriate contract
language been inserted into all active
contracts and reviewed by the Records
Officer? (see
http://www.archives.gov/records-
mgmt/handbook/records-mgmt-
language.html)
Phase 2: Define System Requirements
Requirement
Met?
Indicate
FM = Fully
Met
PM = Partially
Met
NM = Not
Met)
CIO Records
Management
Approval
6) Are all records-related
requirements identified and
incorporated into the final CONOPS
Report or Business Requirements
Document?
7) Are new records schedules being
drafted, if needed?
8) Has the agency Records Officer
reviewed the requirements document?
Phase 3: Design System Components
Requirement
Met?
Indicate
FM = Fully
Met
PM = Partially
Met
NM = Not
Met)
CIO Records
Management
Approval
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 40
9) Are all records management
requirements incorporated into the
system design document?
10) Has the Records Officer reviewed
the system design document?
Phase 4: Build System Components
Requirement
Met?
Indicate
FM = Fully
Met
PM = Partially
Met
NM = Not
Met)
CIO Records
Management
Approval
11) Is the OPM records management
staff included in project status
meetings as needed?
12) Are proposed records schedules
submitted to the National Archives
and Records Administration (NARA)?
Phase 5: Evaluate System Readiness
Requirement
Met?
Indicate
FM = Fully
Met
PM = Partially
Met
NM = Not
Met)
CIO Records
Management
Approval
13) Are records management
requirements incorporated into the
system?
14) Has the agency Records Officer
reviewed any Test Reports to validate
the records requirement incorporation?
Phase 6: Deploy The System
Requirement
Met?
Indicate
FM = Fully
Met
PM = Partially
Met
NM = Not
Met)
CIO Records
Management
Approval
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 41
15) Is the agency records management
staff included in project status
meetings as needed?
16) Has the OPM Records Officer
been notified and granted approval of
deployment of the system?
17) Is the Mid-Cycle Review
complete? (Review to occur 3 years
after going to production to validate
records management requirements and
records schedules.)
18) Are disposition authorities being
implemented in accordance with
appropriate dispositions?
19) Has the Mid-Cycle Review report
been sent to the OPM records
management staff for review?
20) Is the OPM Records Officer
approval on the Mid-Cycle Review
certification document?
Phase 7: Decommission The System
Please reference NARA Code of
Federal Regulations - 36 CFR
1236.1 found at
http://www.archives.gov/about/regul
ations/part-1236.html#1236.14
Requirement
Met?
Indicate
FM = Fully
Met
PM = Partially
Met
NM = Not
Met)
CIO Records
Management
Approval
21) At the time of retirement or
rollover of the system, are records
preserved, retained, and fully
accessible for the full retentions in
accordance with appropriate
dispositions?
22) At the time of retirement or
rollover of the system, are temporary
records destroyed in accordance with
appropriate dispositions?
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 42
23) At the time of retirement or
rollover of the system, are permanent
records transferred to NARA in
accordance with the appropriate
dispositions?
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 43
APPENDIX A: ACRONYMS
Description: The following acronym list was created based on the acronyms found within the
OPM SDLC.
Group
Acronym
Description
A
ABL
Allocated Baseline
AO
Authorizing Official
C
CASE
Computer Aided Software Engineering
CBA
Cost/Benefit Analysis
CBT
Computer-Based Training
CCB
Configuration Control Board
CFO
Chief Financial Officer
CI
Configuration Item
CIO
Chief Information Officer
CM
Configuration Management
CMMI
Capability Maturity Model Integration
CMP
Configuration Management Plan
CO
Contracting Officer
COTS
Commercial Off-the-Shelf
CPIC
Capital Planning and Investment Control
CPU
Central Processing Unit
CR
Change Request
CSA
Configuration Status Accounting
D
DBDD
Database Design Description
DBMS
Database Management System
DOC
Document
DS
Data Specification
DR
Discrepancy Report
E
EA
Enterprise Architecture
ESC
Executive Steering Committee
F
FAI
Federal Acquisition Institute
FBL
Functional Baseline
FRD
Functional Requirements Document
FS
Feasibility Study
G
GAO
Government Accountability Office
H
HDW
Hardware
I
IAW
In Accordance With
ICP
Installation and Conversion Plan
ID
Identification (never “id”)
i.e.,
id est (Latin “that is”)
IPT
Integrated Project Team
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 44
Group
Acronym
Description
IRB
Investment Review Board
IS
Information System
IT
Information Technology
ITIAP
Information Technology Investment Analysis Package
J
JCL
Job Control Language
L
LAN
Local Area Network
LOE
Level of Effort
N
NS
Needs Statement
O
OCIO
Office of Chief Information Officer
OM
Operations Manual
OMB
Office of Management and Budget
OPM
U.S. Office of Personnel Management
P
PB
Product Backlog
PBL
Product Baseline
PLN
Plan
PM
Project Manager
PMBOK
Project Management Body of Knowledge
PMI
Project Management Institute
POC
Point of Contact
PP
Project Plan
Q
QA
Quality Assurance
QAP
Quality Assurance Plan
R
REF
Reference
RFC
Request for Change
RM
Requirements Management
ROM
Rough Order of Magnitude
RPT
Report
RTM
Requirements Traceability Matrix
S
SA&A
Security Assessment and Authorization
SDD
System Design Document
SEI
Software Engineering Institute
SFW
Software
SME
Subject Matter Expert
SPC
Specification
SQA
Software Quality Assurance
SRS
Software Requirements Specification
SSP
System Security Plan
STD
Standard
T
TMP
Templates
TP
Test Plan
TRM
Technical Reference Model
TST
Test Scripts
U
URD
User Requirements Document
V
VDD
Version Description Document
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 45
Group
Acronym
Description
VV&T
Verification, Validation & Testing
W
WBS
Work Breakdown Structure
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 46
APPENDIX B: GLOSSARY
Word/Term
Definition
Acceptance
Testing
The final stage in the testing process before the system is commissioned for
operational use
Agile
SDLC methodology which implements of a number of phases that are
repeated in cycles, with a feedback loop after each cycle is completed.
Agile is characterized by:
Direct involvement of the customer in product development
Use of multiple development iterations to learn about and evolve the
product
Customer willingness to share in the responsibility for decisions and
risk
Application
A system providing a set of services to solve some specific user problem.
Approval
Written notification by an authorized representative of the acquirer that the
developer’s plans, design, or other aspects of the project appear to be sound
and can be used as the basis for further work. Such approval does not shift
responsibility from the developer to meet contractual requirements.
Architecture
The structure of a computer system, either a part or the entire system; can
be hardware, software, or network
Audit
An independent examination of a work product to assess compliance with
specifications, standards, quality or security requirements, contractual
agreements, or other predetermined criteria
Automated Data
Processing
The processing of information by means of a computer.
Availability
The degree to which a system (or system component) is operational and
accessible when required for use
Backup
Verb. To copy software files onto a different media that can be sorted
separately from the original files and used to restore the original files, if
needed. The act of creating these files.
Noun. The set of copied files
Baseline
A work product (such as software or documentation) that has been formally
reviewed, approved, and delivered and can only be changed through formal
change control procedures
Baseline
Management
The processes for establishing cost and schedule and business-related
performance metric baselines for an IT investment and for managing and
reporting any subsequent changes to them
Build
(1) A version of software that meets a specified subset of the requirements
that the completed software will meet. (2) The period of time during which
such a version is developed. Note: The relationship of the terms "build"
and "version" is up to the developer; for example, it may take several
versions to reach a build, a build may be released in several parallel
versions (such as to different sites), or the terms may be used as synonyms.
Capability
A measure of the expected use of a system.
Central
Processing Unit
controls the operation of a computer by performing arithmetic and logical
operations and decoding and executing instructions
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 47
Word/Term
Definition
(CPU)
Change Request
(CR)
The formal documentation that is prepared for a request to change a
specification in accordance with the Software Configuration Management
Configuration Control Procedure
Client/Server
A network application in which the end-user interaction with the system
(server) is through a workstation (client) that executes some portion of the
application
Commercial Off-
The-Shelf
(COTS)
Software
Commercially purchased, third party software used to accomplish a specific
function such as spreadsheets, word processing, utilities, and graphics
Compatibility
The ability of two or more systems or components to perform required
functions while sharing the same hardware and software environment. Also,
the ability of two or more systems or components to exchange information
Computer Aided
Software
Engineering
(CASE)
The use of computers to aid in the software engineering activities that may
include but need not be limited to the application of software tools for
software design, requirements tracing, code production, testing, document
generation, and other software engineering activities.
Computer
Hardware
The physical part of a computer system; the machinery and equipment
Computer
Program
A combination of computer instructions and data definitions that enable
computer hardware to perform computational or control functions
Configuration
The way a computer is set up (functional and physical), which includes the
hardware (type of CPU, peripherals, etc.) and the software
Configuration
Audit
A review conducted to verify that the development of a configuration item
has been completed satisfactorily, that the item has achieved the
performance and functional characteristics specified in the functional and
allocated configuration identification, and that its operational and support
documents are complete and satisfactory
Configuration
Control
An element of configuration management consisting of the evaluation,
coordination, approval/disapproval and implementation of changes to
configuration items after formal establishment of their configuration
identification.
Configuration
Control Board
(CCB)
Evaluates scope, applicability, and effect of each requested change,
focusing on the items that affect cost, schedules, or compliance with
requirements and providing approval and disapproval based on business
objectives. The CCB has the authority to establish baselines, initiate or
change software, accept testing results, and approve the release of software
into production
Configuration
Identification
The process of identifying items to be placed under configuration control
Configuration
Management
Library
The tools and procedures to access the contents of the software baseline
library.
Configuration
Documents the plan for performing CM activities for a specific project or
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 48
Word/Term
Definition
Management
Plan
group of projects including resources, schedule, tools, and procedures
Configuration
Status
Accounting
An element of CM that focuses on recording and monitoring changes to
controlled system configurations and maintaining a controlled
documentation library
Code
To transform the system logic and data from design specifications into a
programming language. n. The computer program itself; pseudo-code is
code written in an English-like logical representation, source code is code
written in a programming language, object code is code written in machine
language.
CPIC
Capital Planning and Investment Control (CPIC): a management process for
ongoing identification, selection, control, and evaluation of investments in
information resources. The process links budget formulation and execution,
and is focused on agency missions and achieving specific program
outcomes. (See OMB Circular A-130, Section 6 at
http://www.whitehouse.gov/omb/Circulars_a130_a130trans4/#6.)
Data
Recorded information, regardless of medium or characteristics, of any
nature, including administrative, managerial, financial, and technical
Data Dictionary
A repository of information about data, such as its meaning, relationships to
other data, origin, usage and format
Data
Specification
(DS)
Describes the database organization and storage allocation and provides the
detailed data model of the logical and physical design, as well as other
necessary information
Database
A collection of logically related data stored together in one or more
computerized files; an electronic repository of information accessible via a
query language interface
Database
Management
System (DBMS)
A software system that controls storing, combining, updating, retrieving,
and displaying data records.
Developer
An organization that develops products ("develops" may include new
development, modification, reuse, reengineering, maintenance, or any other
activity that results in products) for itself or another organization
Documentation
Written and/or graphical information describing, defining, specifying,
reporting, or certifying activities, requirements, procedures, reviews, or
results
Earned Value
Management
A management technique which uses past performance to predict future
cost and schedule performance results. All work is planned, budgeted, and
scheduled in time-phased "planned value" increments constituting a cost
and schedule measurement baseline. (See OMB Circular A-11, Supplement
to Part 7, Capital Programming Guide.)
Enhancement
A change that makes a version of software or hardware better than the
previous version
Feasibility
The extent to which the benefits of a new or enhanced system will exceed
the total costs and also satisfies the business requirements
Feasibility Study
A formal study to determine the feasibility of a proposed system (new or
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 49
Word/Term
Definition
enhanced) in order to make a recommendation to proceed or to propose
alternative solutions
Function
A set of related actions, undertaken by individuals or tools that are
specifically assigned or fitted for their roles, to accomplish a set purpose or
end
Functional
Requirement
A requirement that specifies functions that a system must perform.
Functional
Requirements
Document
(FRD)
Documentation of initial definition of the system and the environment in
which it will operate
Functionality
The ability to perform all required functions
Goals
Signifies the scope, boundaries, and intent of each key process area.
Hardware
The hardware is the physical part of a computer system; the machinery and
equipment
Implementation
Installing and testing the final system, usually at the user (field) site; the
process of installing the system
Information
system
A discrete set of information resources organized for the collection,
processing, maintenance, transmission, and dissemination of information, in
accordance with defined procedures, whether automated or manual (per
OMB Circular A-130)
Information
system project
Temporary planned endeavor funded by an approved information
technology investment; thus achieving a specific goal and creating a unique
product, service, or result. A project has a defined start and end point with
specific objectives that, when attained signify completion
Information
Technology
Any equipment or interconnected system or subsystem of equipment, that is
used in the automatic acquisition, storage, manipulation, management,
movement, control, display, switching, interchange, transmission, or
reception of data or information by an executive agency. For purposes of
the preceding sentence, equipment is used by an executive agency if the
equipment is used by the executive agency directly or is used by a
contractor under a contract with the executive agency which (i) requires the
use of such equipment, or (ii) requires the use, to a significant extent, of
such equipment in the performance of a service or the furnishing of a
product. The term "information technology" includes computers, ancillary
equipment, software, firmware and similar procedures, services (including
support services), and related resources. The term "information technology"
does not include any equipment that is acquired by a Federal contractor
incidental to a Federal contract. The term "information technology" does
not include national security systems as defined in the Clinger-Cohen Act of
1996 (40 U.S.C. 1452). (See OMB Circular A-130, Section 6 at
http://www.whitehouse.gov/omb/Circulars_a130_a130trans4/#6.)
Integration Test
Testing in which software components, hardware components, or both are
combined and tested to evaluate the interaction between them
Integrity
The degree to which a system (or system component) prevents unauthorized
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 50
Word/Term
Definition
access to, or modification of, computer programs or data.
Interface
To interact or communicate with another system (or system component).
(verb)
An interface can be software and/or hardware (noun)
Interoperability
A measure of the ability of two or more systems (or system components) to
exchange information and use the information that has been exchanged
Investment
Spending by Program Office on information technology regardless of
amount or funding source. An IT investment may include a project or
projects for the development, modernization, enhancement, or maintenance
of a single IT asset or group of IT assets with related functionality and the
subsequent operation of those assets in a production environment. While
each asset or project would have a defined life-cycle, an investment that
covers a collection of assets intended to support an ongoing business
mission may not.
Lessons Learned
Any experiences discovered on previous activities that can be used to
expedite and/or improve future systems development
Level of Effort
Contract
A level of effort contract means that for a specific amount of money the
provider will produce as many deliverables as they can
Library
A configuration controlled repository for system components (for example,
documents and software)
Life Cycle
All the steps or phases a program or project passes through during its life;
from concept development to disposition
Maintainability
The ease with which a software system (or system component) can be
modified to correct faults, improve performance, or other attributes, or
adapt to a changed environment
Maintenance
Activities required to keep a software system operational after
implementation
Managed and
Controlled
The process of identifying and defining software work products that are not
part of a baseline and, therefore, are not placed under configuration
management but that must be controlled for the project to proceed in a
disciplined manner
Methodology
A set of methods, procedures, and standards that define the approach for
completing a system development or maintenance project
Metrics
A quantitative measure of the degree to which a system, component, or
process possesses a given attribute
Milestone
A scheduled event that is used to measure progress against a project
schedule and budget
Module
A software unit that is a logically separate part of the entire program
Needs Statement
Document describing the deficiency or justifying the exploration of
alternative solutions
Operations
Manual (OM)
Provides computer control personnel and computer operators in an
information processing center with a detailed operational description of the
system and its associated environment. Instructions for installation and
operation
Phase
A defined stage in the systems development life cycle; there are seven
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 51
Word/Term
Definition
phases in the OPM SDLC
Procedure
A series of steps (or instructions) required to perform an activity
Process
A finite series of activities as defined by its inputs, outputs, controls (for
example, policy and standards), and resources needed to complete the
activity
Product
General term for an item produced as the result of a process; can be a
system, subsystem, software component, or a document
Program
One or more major multi-year IT initiatives of such magnitude they must be
carried out through multiple related IT projects. A program encompasses
the missions, functions, operations, activities, laws, rules, and regulations
that an agency is authorized and funded by statute to administer and
enforce. It constitutes an ongoing operation.
Project
The complete set of activities associated with all life cycle phases needed to
complete a systems development or maintenance effort from start to finish
(may include hardware, software, and other components); the collective
name for this set of activities.
A project has a defined beginning and end. A project serves to develop,
modify, or enhance a product, service, or system and is constrained by the
relationships among scope, resources, and time. [Source: OPM (11/2011)
“IT Program Management Career Path Guide”, p. 3.]
Project
Management
The process of planning, organizing, staffing, directing, and controlling the
development and/or maintenance of a system
Project Plan
A plan that is updated, expanded and refined continually thought system
development; covers project scheduling, work breakdown structure (WBS),
staffing, resources, adjustments to the software development life cycle
structure, selection of tools and techniques, identification of applicable
reviews and approvals, CM methods, and other related topics
Project Team
Group of individuals associated with a specific project
Quality
The degree to which a system, component, product, or process meets
specified requirements.
Quality
Assurance
A discipline used by project management to objectively monitor, control,
and gain visibility into the development or maintenance process
Quality
Assurance Plan
A formal plan to ensure that delivered products satisfy contractual
agreements, meet or exceed quality standards, and comply with approved
systems development or maintenance processes
Regression
Testing
The rerunning of test cases that previously executed correctly in order to
detect errors introduced by the maintenance activity
Release
A configuration management activity wherein a specific version of software
is made available for use
Requirement
A capability needed by a user; a condition or capability that must be met or
possessed by a system (or system component) to satisfy a contract, standard,
specification, or other formally imposed documents
Requirements
Management
Establishes and controls the scope of system development efforts and
facilitates a common understanding of system capabilities between the
System Proponent, developers, and future users
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 52
Word/Term
Definition
Requirements
Traceability
Matrix
Provides a method for tracking the functional requirements and their
implementation through the development process
Resource
In management, the time, staff, capital and money available to perform a
service or build a product; also, an asset needed by a process step to be
performed
Reusability
A characteristic of some programming styles or languages (for example,
object-oriented programming) in which code written for one application can
be reused with different applications
Revision
A version that supersedes an earlier version to correct errors
Risk
A potential occurrence that would be detrimental to the project; risk is both
the likelihood of the occurrence and the consequence of the occurrence
Schedule
A list of tasks and activities, describing the past and/or future
accomplishments of a project/release, used to allocate work, specify
deadlines, and manage the project/release
Scope
The established boundary (or extent) of what must be accomplished; during
planning, this defines what the project will consist of (and just as important,
what the project will not consist of)
Scrum
Scrum is a popular Agile system development methodology. Scrum is
characterized by selfdirected development teams, operating in successive
iterations (typically 2 to 3 weeks as indicated by best practices), holds daily
team standup meetings of no longer than 15 minutes, continuously offers
the customer demos of the current solution, and adapts its development plan
at the end of each iteration.
Security
The establishment and application of safeguards to protect data, software,
and hardware from accidental or malicious modification, destruction, or
disclosure.
Software
Computer programs (code), procedures, documentation, and data pertaining
to the operation of a computer system
Software Design
Description
(SDD)
Documents the allocation of requirements, system/software designs, and
internal/external interfaces.
Software Process
A set of activities, methods, practices, and transformations that people use
to develop and maintain software and the associated products (e.g., project
plans, design documents, code, test cases, and user manuals).
Standard
An agreed-upon set of specifications for hardware or software
Stress Testing
Testing that determines the maximum capacity of the system, given user
requirements for response time and throughput
Subject Matter
Expert (SME)
An individual with a specific area of expertise.
Subsystem
A collection of components that meets the definition of a system, but is
considered part of a larger system.
System
A collection of components (hardware, software, interfaces) organized to
accomplish a specific function or set of functions; generally considered to
be a self-sufficient item in its intended operational use
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 53
Word/Term
Definition
System
Administrator
The person responsible for planning a system installation and use of the
system by other users.
Security
Assessment and
Authorization
Formerly known as the Certification and Accreditation (C&A) in the IT
Security and Privacy area.
System
Development
Life Cycle
(SDLC)
A consistent and repeatable process for planning, managing, and overseeing
IT programs and projects through all the steps or phases it passes through
during its life; from concept development to disposition.
System Security
Plan
A formal document that establishes the processes and procedures for
identifying all areas where security could be compromised within the
system (or subsystem).
Tailor
To modify a process, standard, or procedure to better match process or
product requirements.
Team
A collection of people, often drawn from diverse but related groups,
assigned to perform a well-defined function for an organization or a project.
Technical
Relating to agreements, conditions, and/or requirements affecting the
functionality and operation of a system. Compare to non-technical
Template
The outline or format for a document or memo. Defines what information
needs to be included in the document
Test
The process of exercising the product to identify differences between
expected and actual results and performance
Test Case
A specific set of test data and associated procedures developed for a
particular test.
Test Results and
Evaluation
Report
A compilation of test results and summary of the system’s readiness for
production.
Test Team
Individuals, independent of the software development organization, who are
designated by the project sponsor to test system’s readiness for production
Training
The formal process of depicting, simulating, or portraying the operational
characteristics of a system or system component in order to make someone
proficient in its use.
Training Plan
A formal document that outlines the objectives, needs, strategy, and
curriculum to be addressed for training users of the new or enhanced
system.
Unit
The smallest logical entity specified in the design of a software system;
must be of sufficient detail to allow the code to be developed and tested
independent of other units
Unit test
A test of one application to see if remediation efforts were successful. The
unit test does not test how well the application will work with other
applications
User Acceptance
Test
A formal test conducted by the end user of a system, to determine if the
system works according to specifications and should be accepted
User Manual
A formal document that contains all essential information for the user to
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 54
Word/Term
Definition
make full use of the new or upgraded system.
Verification,
Validation &
Testing Plan
Documentation of the testing strategy that provides acceptance testing for
all components of a system
Version
An initial release or re-release of a computer software configuration item,
associated with a complete compilation or recompilation of the computer
software configuration item; sometimes called a build
Version Control
A means to identify and manage configuration items as they change over
time, usually provided by a software tool designed for configuration
management
Version
Description
Document
A formal document that describes the exact version of a configuration item
and its interim changes. It is used to identify the current version; provides a
"packing list" of what is included in the release.
Work
Breakdown
Structure
A structure of well-defined work efforts and work elements that organizes
and defines the total scope of the project and provides for better planning,
scheduling and controlling of a project’s work efforts.
Version 1.1
April 2013 Page 55
APPENDIX C: REFERENCES
C.1 External and Internal Issuances Incorporated by Reference
C.1.1 External References
25 POINT IMPLEMENTATION PLAN TO REFORM FEDERAL INFORMATION
TECHNOLOGY MANAGEMENT” by Vivek Kundra, U.S. Chief Information Officer,
December 9, 2010: http://www.whitehouse.gov/sites/default/files/omb/assets/egov_docs/25-
point-implementation-plan-to-reform-federal-it.pdf
Beck, Kent; et al. (2001). "Manifesto for Agile Software Development". Agile Alliance
Chief Financial Officers Council guidance documents: http://www.cfoc.gov/
Clinger-Cohen Act of 1996, February 10, 1996, Subtitle III of Title 40 United States Code
(U.S.C.)
Government Accountability Office (GAO) Cost Estimating and Assessment Guide,
http://www.gao.gov/new.items/d093sp.pdf.
NARA Code of Federal Regulations - 36 CFR 1236, Electronic Records Management,
http://www.gpo.gov/fdsys/pkg/CFR-2011-title36-vol3/pdf/CFR-2011-title36-vol3-part1236.pdf
Office of Management and Budget (OMB), Circular A-11, Supplement to Part 7, The Capital
Programming Guide, v2.0.
http://www.whitehouse.gov/sites/default/files/omb/assets/a11_current_year/part7.pdf
Office of Management and Budget (OMB) memorandum M-10-27 of June 28, 2010.
http://www.whitehouse.gov/sites/default/files/omb/assets/memoranda_2010/m10-27.pdf
Project Management Institute (2008), “Project Management Body of Knowledge”, 4
th
edition
Records Management policy defined within the Federal Enterprise Records Management Profile,
Sections 4.1.1 through 4.1.6
http://www.archives.gov/records-mgmt/policy/rm-profile.html
Section 508 of the Rehabilitation Act, August 7, 1998
http://www.section508.gov/index.cfm?fuseAction=1998Amend
Software Engineering Institute, Capability Maturity Model Integration (CMMI) for Development
version 1.3, at http://www.sei.cmu.edu/library/abstracts/reports/10tr033.cfm
The Federal Acquisition Reform Act (FASA) and the Federal Acquisition Regulations (FAR)
Implementation of the Federal Acquisition Streamlining Act. See reference library at GSA’s
Version 1.1
April 2013 Page 56
Acquisition Central at www.acquisition.gov
C.1.2 Internal OPM References
IT Baseline Management Policy, available on OPM website at
http://www.opm.gov/about-us/our-people-organization/support-functions/cio/information-
technology-baseline-management-policy.pdf
Policy on Information Technology (IT) Procurement, available on THEO at
http://theo.opm.gov/policies/ispp/it_procurement.pdf
Information Security & Privacy Policy and Supporting Documents, available on THEO at
http://theo.opm.gov/policies/ispp/
Policy on Electronic Signatures, available on THEO at
http://theo.opm.gov/policies/electronic signature policyv6.pdf
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 57
APPENDIX D : OPM SDLC PHASE ACTIVITIES
Appendix D.1: Determine System Needs Phase Activities
Step
Description of Activity
Inputs/Outputs
Lead
Participants
1.
Determine type of development.
The Business Program Manager or Business Project Manager, with
assistance from a Technical Advisor, determines the type of development
needed to support the project.
The type of development is chosen from the following types:
New - A system will be implemented where no system currently exists
with the intended functionality or will replace an existing system.
COTS - A project that will implement a Commercial Off-the-Shelf
(COTS) product requiring integration or with modifications.
Cloud A project that will implement a Cloud solution requiring
integration or with modifications.
Enhancement - A project that will require either changes to an existing
systems architecture or interfaces.
Maintenance - A project that will make changes to an existing system,
but not change the architecture or interfaces.
Inputs:
Identified need or
Change Request
(CR)
Outputs:
Type of project
development
selected
Business Program
Manager or
Business Project
Manager
Technical
Advisor
2.
Determine a “Rough Order of Magnitude (ROM)” estimate of the cost of
the project.
The Business Program Manager or Business Project Manager determines
the initial estimated cost of the project with the assistance of a Technical
Advisor.
At this early stage, this cost is a high level estimate based on level of
effort (LOE), materials and equipment from development through
Inputs:
Identified need or
CR, Estimated IT
Security Resource
Hours/Cost
Outputs:
Estimated ROM
Business Program
Manager or
Business Project
Manager
Technical
Advisor
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 58
Step
Description of Activity
Inputs/Outputs
Lead
Participants
deployment. This cost can be derived using an automated estimating tool,
based on analogy, or other estimating method.
The estimated ROM cost is comprised of the following:
Labor Total estimated cost of labor
Materials Total estimated cost of materials (including purchased
software)
Equipment Total estimated cost of equipment (computers, facilities,
etc.)
cost
3.
Determine project risks, project complexity, project duration and special
interests which affect the project.
Project Risks: Low, Medium and High
Project Complexity: Low, Medium and High
Project Duration: Less than six months or greater than six months
Special Interests affecting Project: Yes or No
Inputs:
Identified need or
CR
Outputs:
Project Assessment
for Risk,
Complexity,
Duration and
Special Interest
Business Program
Manager or
Business Project
Manager
Technical
Advisor
4.
Determine the project documentation level based on the selected type of
project development, estimated ROM cost and project assessment for
Risk, Complexity, Duration and Special Interest as outlined in Appendix
E
Inputs:
Estimated ROM
cost;
Selected Type of
Project
Development;
Project Assessment
for Risk,
Complexity,
Duration and
Special Interest
Business Program
Manager or
Business Project
Manager
Technical
Advisor
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 59
Step
Description of Activity
Inputs/Outputs
Lead
Participants
Outputs:
Project
Documentation
Level
5.
Determine if the need requires the retirement of an existing system or part
of an existing system
Is the new need intended to replace an existing system?
Perform decommission if system or partial system exists.
Inputs:
Existing System,
Outputs:
Decision to
Decommission a
System
Business Program
Manager or
Business Project
Manager
Technical
Advisor
System Owner
6.
Begin Phase Work
Based on project category criteria from Appendix E:
- Project Documentation Level 1 and 2 Proceed to step 8 in this
procedure.
- Project Documentation Level 3 Proceed to the Build System
Components Phase or Develop System Design Phase. For some
minor changes to the system, the changes could be implemented
directly in the production environment.
- Project Documentation Level 4 Proceed to step 7 in this
procedure.
- Project Documentation Level 5 Proceed to step 7 in this
procedure
Inputs:
Decommissioned
System (if
applicable),
Project
Documentation
Level
Outputs:
Begin preparation
for Needs
Statement or
Begin preparation
for IT Investment
Analysis Package
or
Begin Build System
Components
or
Develop System
Design
Business Program
Manager or
Business Project
Manager
Technical
Advisor
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 60
Step
Description of Activity
Inputs/Outputs
Lead
Participants
7.
Document the Need by developing a Needs Statement
User/Business Program Manager or Business Project Manager
Develops Needs Statement (NS)
- Identify the benefits expected, existing and planned capabilities,
estimated costs, assessment of need.
Review OPM’s Technical Reference Model found in the Enterprise
Architecture (EA) document. The EA document can be requested
from the CIO Enterprise Architect.
Submit Needs Statement to the Executive Sponsor for internal review
Executive Sponsor provides comments and feedback on the Needs
Statement
Comments incorporated to the Final Needs Statement and Submitted
to CM for version control
Inputs:
Project
Documentation
Level,
Technical
Reference Model,
Needs Statement
Template,
Outputs:
Needs Statement
(versioned)
Business Program
Manager or
Business Project
Manager
Technical
Advisor
Executive
Sponsor,
Chief
Information
Officer (CIO),
Executive
Sponsor
CM Team,
SQA Team
8.
Prepare Information Technology Investment Analysis Package (ITIAP)
by conducting a Feasibility Study (FS) using the template provided.
Examine system objectives
- Analyze anticipated functions of the system, considering areas
such as:
New services
Increased capacity
Legislative and policy requirements
Privacy and security requirements
Audit controls
- Identify major performance objectives, such as:
Reduced staff and equipment costs
Increased processing speed and productivity
Improved management information services and controls over
automated decision making systems
Inputs:
Needs Statement
(versioned),
IT Investment
Analysis Package
Template,
Feasibility Study
Template,
Outputs:
IT Investment
Analysis Package
(draft),
Feasibility Study
(draft), Information
Business Program
Manager or
Business Project
Manager
Technical
Advisor, IT
Security Team
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 61
Step
Description of Activity
Inputs/Outputs
Lead
Participants
Compliance with regulations
- Identify assumptions and constraints
Operational life of the proposed system
Period of time for comparison of system alternatives
Input, output, and processing requirements
Financial constraints
Changing hardware, software and operating environment
Evaluate Alternatives
- Determine criteria for evaluating alternatives such as:
Cost
Priority
Development time
Ease of system use
- Identify and summarize alternatives to be considered during the
study including:
Use of one or more existing system
Development of one or more new system
The potential of purchasing an off-the-shelf system.
- Outline time and resource costs
Include the time and funding required for all activities of the
life cycle from definition through operation.
Use realistic estimates
Include factors such as:
The current workload of personnel
Staff absences due to vacation and illness
Lead time for procurement of equipment and software
Staff training
Identify preferred approach by weighing each alternative identified
during the evaluate alternatives process against the evaluation criteria
Develop detailed FS
- Describe system objectives by including such information as:
Type Classification
(FIPS-199), Privacy
Threshold Analysis,
SORN, Special
Security
Requirements
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 62
Step
Description of Activity
Inputs/Outputs
Lead
Participants
System output
System input
File descriptions
Validation criteria
Security, privacy, and control requirements, data storage and
retrieval
Any interfacing systems
- Describe current functional procedures whether automated or
manual
- Describe proposed system including such information as:
The overall system concept
Improvements anticipated after successful implementation of
the proposed system
9.
Prepare ITIAP by conducting the Cost/Benefit Analysis (CBA) using the
CBA template or any alternative template
Identify the alternatives for development and operation
- Describe the technical and operational characteristics of current
system and identify the input to and output form the system
- Summarize the functional objectives of the system and describe
the expected input to and output form the system
- Describe the alternative system that was discussed in the FS.
Determine the benefits per alternative
- Determine nonrecurring benefits for each system alternative
- Determine recurring benefits including:
Equipment
Software and data communications lease
Rental and maintenance
- Determine non-quantitative benefits such as:
Improved service
Reduced risk of incorrect processing
Improved information handling
Enhanced organizational image
Inputs:
Needs Statement,
Investment
Analysis Package
Template,
Cost/Benefit
Analysis Template
Outputs:
IT Investment
Analysis Package
(draft),
Cost/Benefit
Analysis (draft)
Business Program
Manager or
Business Project
Manager
Technical
Advisor
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 63
Step
Description of Activity
Inputs/Outputs
Lead
Participants
Determine the cost per alternative
- Development costs
- Operational costs
- Nonrecurring costs
- Recurring costs
Develop a detailed CBA
10.
Complete the ITIAP with the Needs Statement as the Appendix
Chief Information Officer (CIO) reviews the package
Submit package to Investment Review Board (IRB) and to CM to be
baselined.
Inputs:
IT Investment
Analysis Package
(draft)
Outputs:
Reviewed and
baselined IT
Investment
Analysis Package
Business Program
Manager or
Business Project
Manager
Technical
Advisor,
Chief
Information
Officer,
Investment
Review Board
11.
IRB conducts review of the IT Investment Analysis Package which
contains the Cost Benefit Analysis.
IRB renders decision to approve or disapprove.
For detailed steps on the IRB refer to the OPM IRB Charter
Inputs:
IT Investment
Analysis Package
Outputs:
Approved IT
Investment
Analysis Package
Investment Review
Board
CIO
12.
Charter the Project
Formally establish the work as a Project
Budget is established for the IT Project which is to be managed by the
Business Program Manager or Business Project Manager
Assign a Technical Project Manager
Inputs:
Approved IT
Investment
Analysis Package
Outputs:
Technical Project
Manager is
CIO
Business
Program
Manager or
Business
Project
Manager
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 64
Step
Description of Activity
Inputs/Outputs
Lead
Participants
A Technical Project Manager is assigned or transferred to the work
assigned
13.
Define High Level System Requirements
Gather user requirements
Determine functional requirements
- Identify the functional requirements
- Define current procedures including:
Organizational and personnel responsibilities
Equipment being used
Input/output including volume, sources and frequency
Deficiencies such as time delays
- Define proposed functions include:
Information flows
Business logic
Manual procedures
Security considerations
- Identify organizational, operational, and user impacts
Define performance requirements. Determine:
- Acceptable online response time and batch turnaround time (as
applicable)
- Capacity limits (as applicable)
- Accuracy and validity requirements
Identify and define applicable standards and guidelines:
Inputs:
IT Invest Analysis
Package,
User Requirements
Document
Template,
Applicable
Standards and
Guidelines
Outputs:
User Requirements
Document (draft),
Security Impact
Analysis document
Business Program
Manager or
Business Project
Manager
Technical
Advisor, IT
Security
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 65
Step
Description of Activity
Inputs/Outputs
Lead
Participants
- Review applicable program office standards
- Review the OPM Enterprise Architecture and Technical Reference
Model
- Review the OPM Information Security and Privacy Policy
- Review Section 508 standards
Capture requirements in the User Requirements Document (URD)
- Review applicable documentation (Needs Statement, ITIAP)
- Define assumptions and constraints that will affect development
and operation of the system.
The Technical Advisor provides input and advice for the URD
14.
Deliver the Final User Requirements Document
Staff the URD with users and the executive sponsor for comment and
approval
Incorporate user comments and deliver the final User Requirements
Document to Configuration Management to be placed under version
control.
Inputs:
Customer
comments on User
Requirements
Document
Outputs:
Final User
Requirements
Document
(versioned)
Business Program
Manager or
Business Project
Manager
Technical
Advisor
CM Team
Users and
Executive
Sponsor
15.
Conduct Phase Exit Review
Business Program Manager, Business Project Manager or Product
Owner notify the project team and extended project team (users,
POCs, support areas) that a Phase Exit Review has been scheduled.
- Request that all approvers provide feedback at least one week
before the exit meeting is to be held. (This will allow the time to
Inputs:
Phase Deliverables
produced during
current phase,
New and existing
issues
Outputs:
Business Program
Manager or
Business Project
Manager
Technical
Advisor
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 66
Step
Description of Activity
Inputs/Outputs
Lead
Participants
work issues and develop action plans prior to the exit meeting)
- Invite participants to attend the exit meeting using the Phase Exit
Review Memo that is within the Phase Exit Review Package along
with the review material (any other material relevant to the exiting
stage which include but are not limited to known issues, and
unplanned deliverables)
- The participants should be familiar with planned deliverables since
it is standard procedure for them to review drafts as they are
developed.
If this is not the case a list of the planned deliverables should
also be distributed at this time.
Review the current outline (at a minimum, a detailed plan for the next
phase and high-level plans for the remainder of the project).
Review other relevant materials to verify if they are in accordance
with OPM’s SDLC
Receive position from the list of approvers (to include the Executive
Sponsor, CIO, Technical Advisor, Business Program Manager or
Business Project Manager) using the Phase Exit Position Response
Form within the Phase Exit Review Package. This position can be
concur, concur with qualifications, or non-concur. The implication of
each is as follows:
- Concur Proceed with the project according to the current plan.
(Ex. The Approver is unaware of any issues for the current phase)
- Concur with qualifications There are issues or concerns and the
project can proceed according to the current plan if an acceptable
action plan is developed for each issue or concern by the meeting.
(Ex. There is no plan for testing an interface to an existing system
that is being changed)
Plans for
addressing issues
and risks,
Concurrence that
all activities for this
phase is complete
and movement to
next phase has been
approved.
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 67
Step
Description of Activity
Inputs/Outputs
Lead
Participants
- Non-concur There are very significant issues or concerns and the
project should not move to the next phase until those issues or
concerns are resolved. (Ex. Funding for the project has been
withdrawn)
Prepare acceptable action plan to address each issue or concern
received.
Conduct Exit Meeting
- Present positions from the Approvers, along with issues and/or
concerns, and any other issues that may be open
- Action plans must be presented for each issue or concern
Document the meeting including positions, issues, concerns, action
plans, and follow-up activity
Obtain concurrence on current stage deliverables, and begin the next
phase of development
All items are to be controlled by CM.
Appendix D.2 : Define System Requirements Phase Activities
Step
Description of Activity
Inputs/Outputs
Lead
Participants
1.
Scope the Project
Estimate size, resources and schedule
Inputs:
Needs Statement,
User Requirements
Document
Outputs:
Project Estimates
Technical PM
Project Team
2.
Identify, analyze, and document potential risks.
Inputs:
Technical PM
Business
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 68
Step
Description of Activity
Inputs/Outputs
Lead
Participants
Identify Risks
- Risks may occur in the following areas:
Budget
Schedule
Development
Design
- Utilize Lessons-Learned from previous projects as a significant
source for identifying potential risks on a new project
- Categorize Risks as follows: (see Risk Types, Items and Cause of
Impact to help with the selection of category):
Technical Risks associated with creating a new capability or
capacity
Supportability Risks associated with implementing,
operating, and maintaining a new capability
Cost Risks associated with schedule estimates inaccuracy
Schedule Risks associated with planned activities
Analyze Risks
- Characterize
Determine the impact of the risk on the project if it occurs.
Rate as high, medium, or low.
Determine the likelihood of the risk occurring. Rate as high,
medium, or low.
- Strategy
Determine what needs to be done to prevent the risk from
becoming a reality or to minimize its impact.
Develop strategies for eliminating or reducing the risks and
incorporate the strategies into project planning
- Monitoring
Determine metrics to monitor the risk (or probability of risk) to
identify when it begins to become a problem
Identify how tasks will be monitored to detect problems early.
This typically includes monitoring expenditures versus
Needs Statement,
Project Estimates,
User Requirements
Document,
Lessons Learned
from previous
projects as
applicable,
IT Security
Analysis,
Risk Matrix
Template
Outputs:
Project risks,
Security Analysis
Impact document,
Updated Risk
Matrix
Program
Manager or
Business
Project
Manager,
Project Team,
IT Security
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 69
Step
Description of Activity
Inputs/Outputs
Lead
Participants
progress for cost risk; scheduled progress versus actual
progress for schedule risk; requirements tracking for
operational and support risks, and perhaps technical
performance measurement plans for technical risks
- Management
Manage the risk by monitoring and reporting on every open
risk as required.
Document and review risks.
- Update the Risk Matrix
3.
Develop Project Plan
Note: Because project planning is an iterative activity, detailed planning
of the subsequent phases can occur.
Develop the Project Plan and include the Quality Assurance Plan
(QAP) and Configuration Management Plan (CMP) as appendices if
applicable.
- Review the scope of the work
Ascertain the users’ requirements, constraints and
contributions from discussions with the user community and/or
Business Program Manager or Business Project Manager
Record the understanding of the user’s goals and objectives
regarding overall cost schedule and product quality.
Record the understanding of management’s risk tolerance level
Record the understanding of products and their characteristics
to be delivered to the user
- Determine technical approach
Select an appropriate life cycle model for performing required
activities and appropriate packaging techniques for required
products
Refer to Methodologies for reference of various life cycle
models
Incorporate the appropriate project activities into the Project
Plan
Inputs:
Updated Risk
Matrix,
Needs Statement,
Information
Technology (IT)
Investment
Analysis Package
(ITIAP) (if
applicable),
Project Estimates,
Methodologies
Outputs:
Draft Project Plan,
Draft QAP,
Draft CMP
Technical PM
Project Team,
Business
Program
Manager or
Business
Project
Manager
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 70
Step
Description of Activity
Inputs/Outputs
Lead
Participants
Note: Because project planning is an iterative activity, detailed planning
of the subsequent phases can occur.
Develop the Project Plan and include the QAP and CMP as
appendices if applicable.
- Determine technical approach
Determine the activities, methods, techniques, and products
that will help achieve the goals and objectives established for
the project.
- Define, schedule, and budget the work
- Organize the project team
Identify the personnel that compose the project team. Clearly
state the responsibility for each critical function of the project
and establish lines of communication.
Assign the key Roles & Responsibilities for each phase of the
life cycle.
- Determine resource requirements
- Address special project considerations
4.
Create the Quality Assurance Plan (QAP)
Include the following:
Quality objectives in measurable terms
Responsibilities of the Software Quality Assurance (SQA) team
Resource requirements for the SQA team
SQA team participation in Project Plan and procedures
Evaluations to be performed by SQA team
Audits and reviews to be conducted by SQA team
Documenting and tracking noncompliance issues and the escalation
procedures
Documentation that SQA team is to produce
Method, audience, and frequency of providing feedback on SQA
activities
Inputs:
Project Plan,
QAP Template
Outputs:
Draft QAP
SQA Team
Technical PM
5.
Implement the SQA Plan
Inputs:
SQA Team
Technical PM
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 71
Step
Description of Activity
Inputs/Outputs
Lead
Participants
The SQA team performs the SQA function as defined in the QAP
Problems or non-conformances with requirements are documented
and reported to the Technical PM or appropriate authority
Senior Management addresses noncompliance issues that cannot be
resolved within the project
QAP
Outputs:
Implemented QAP
Project Team
6.
Create the Configuration Management Plan (CMP)
Define CM activities and responsibilities and required resources
Specifically address the following:
- Identify items that need to be placed under control which includes:
Configuration Items (CIs) (software, hardware,
communications, and databases)
Technical documentation or baselines describing the CIs
Management documentation (describes the process used to
develop or manage the development of the CIs such as plans,
standards and procedures)
- System and software baselines
Specifically address the following:
- Configuration control
CCB Decision making body for the program area projects.
Evaluates the scope, applicability, and effect of requests by
providing approval or disapproval based on defined strategic
initiatives, program business objectives, and budgetary
parameters with a focus on items that could affect cost,
schedules or compliance with technical requirements.
Change Request (CRs) A request to change technical
requirements approved for the project that may affect the
scope of the system or may have an impact on the overall cost,
schedule, and technical capability and are usually generated by
system user. They must be approved by the project CCB
before resources are assigned to implement the change.
Discrepancy Reports (DRs) Software problems requiring
corrective maintenance
Inputs:
Project Plan,
CMP Template
Outputs:
Draft CMP
CM Team
Technical PM
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 72
Step
Description of Activity
Inputs/Outputs
Lead
Participants
Requests for Change (RFCs) Generated by personnel within
OPM who wishes to initiate system enhancements, which are
usually activities that have been planned for future
implementation.
Specifically address the following:
- Configuration status accounting
Focuses on recording and monitoring changes to controlled
system configurations and maintaining a controlled
documentation library.
- Configuration Audits
Conduct audits on the Configuration Items identified in the
CMP
7.
Prepare the System Architecture as outlined in the Enterprise Architecture
(EA) document. The EA document can be requested from the CIO
Enterprise Architect.
Inputs:
User Requirements
Document,
Needs Statement,
OPM Enterprise
Architecture and
associated
Reference Models
Outputs:
System
Architecture
Technical PM
Project Team,
Business
Program
Manager or
Business
Project
Manager, CIO
Enterprise
Architect
8.
Review the System Architecture and provide comments
Review the System Architecture for approval.
Inputs:
System
Architecture
Outputs:
Reviewed and
approved System
Architecture
Technical PM
Project Team,
Business
Program
Manager or
Business
Project
Manager,
Other
Stakeholders,
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 73
Step
Description of Activity
Inputs/Outputs
Lead
Participants
CIO Enterprise
Architect
9.
Deliver the Final System Architecture
Incorporate stakeholder comments and deliver the final System
Architecture to Configuration Management (CM) to be baselined.
Inputs:
Reviewed and
approved System
Architecture
Outputs:
Baselined System
Architecture
Technical PM
Business
Program
Manager or
Business
Project
Manager, CM
10.
Create a Software Requirements Specification (SRS)
Document the requirements using the SRS Template
Ensure all non-software requirements are documented
If applicable, load the SRS into automated requirements management
tool, which assigns a unique tag number
If an automated tool is not available, ensure that each requirement is
numbered and has attributes clearly associated with it (e.g.,
Requirements Traceability Matrix).
Note: Trace software requirements through design, development, and
testing phases.
Inputs:
Validated
requirements list,
System
Architecture,
Requirements
Traceability
Matrix/Requiremen
ts Management
(RM) Tool
Outputs:
Updated draft SRS,
Draft RTM or
Updated RM Tool
Requirements Team
Project Team
11.
Review SRS and Provide Comments
Review the SRS for approval.
Inputs:
Internally
Approved SRS
Outputs:
Customer Review
comments and
approval
Requirements Team
Technical PM,
QA Team,
Business
Program
Manager or
Business
Project
Manager
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 74
Step
Description of Activity
Inputs/Outputs
Lead
Participants
12.
Deliver the Final SRS
Incorporate customer comments and deliver the final SRS to
Configuration Management (CM) to be baselined.
Inputs:
Customer Review
comments and
approval
Outputs:
Baselined SRS
Requirements Team
Technical PM,
CM Team,
QA Team,
Business
Program
Manager or
Business
Project
Manager
13.
Create the Data Specification
Review the User Requirements Document
Categorize and define the data
- Identify static and dynamic data requirements
- Identify internally generated data
Define data constraints
- Identify source of input
- Identify input/output medium and device
- Identify data recipients
- Specify conversion factors
- Specify frequency of update and processing
Identify input responsibilities
Identify data collection requirements
- Describe detailed formats
- Identify data communication media
- Determine timing of input
Document data requirements using the Data Specification (DS)
Define assumptions and constraints that will affect development and
operation of the system.
Inputs:
Data Specification
Template,
User Requirements
Document, FIPS
199 Document
Outputs:
Data Specification,
Required Data
Security Controls
based on Data
Classification
Technical PM
Requirements
Management
Team,
Software
Development
Team,
Project Team,
IT Security
Team
14.
Review Data Specification and provide comments
Review the Data Specification for approval.
Inputs:
Internally
Approved Data
Specification
Technical PM,
QA Team
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 75
Step
Description of Activity
Inputs/Outputs
Lead
Participants
Outputs:
Customer Review
comments and
approval
15.
Deliver the final Data Specification
Incorporate customer comments and deliver the final Data Specification
to Configuration Management (CM) to place baselined.
Inputs:
Customer Review
comments and
approval
Outputs:
Baselined Data
Specification
Technical PM,
CM Team,
QA Team,
Business
Program
Manager or
Business
Project
Manager
16.
Create Test Plan (Unit & Integration)
Review the baselined SRS
Include Test Strategy
Include Testing of security components (including Role based Access,
Data Restrictions, Audit Logging)
Note: This Test Plan (Unit & Integration) is a test plan that is an internal
testing plan for the software developers and does not replace the
Verification, Validation & Testing Plan that is to be done by an
Acceptance Team or the Business Program Manager or Business Project
Manager/User
Inputs:
Baselined SRS,
Test Plan (Unit &
Integration)
Template
Outputs:
Draft Test Plan
(Unit &
Integration)
Software
Development Lead
Software
Development
Team,
Requirements
Team, IT
Security
17.
Review Test Plan (Unit & Integration) and Provide Comments
Review the Test Plan (Unit & Integration) for approval.
Inputs:
Approved Test Plan
(Unit &
Integration)
Outputs:
Review comments
and approval
Software
Development Lead
Technical PM,
Software
Development
Lead,
QA Team, IT
Security
18.
Deliver the Test Plan (Unit & Integration) Document
Incorporate comments and deliver the final Test Plan to CM to place
Inputs:
Review comments
Software
Development Lead
Technical PM,
Software
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 76
Step
Description of Activity
Inputs/Outputs
Lead
Participants
under version control.
and approval
Outputs:
(baselined) Test
Plan (Unit &
Integration)
Development
Lead,
QA Team,
CM Team
19.
Create Training Plan
Review the baselined SRS
Identify Training Audience
Include Training Approach
- Identify training methods, techniques, and tools
Techniques include but are not limited to computer-based
training (CBT), self-paced written manual, peer training,
hands-on practical session, classroom lecture
Tools include but are not limited to online terminal, training
manual, classroom, and computer center
- Identify training required for revised office procedures
- Develop curriculum
Determine the job classifications of the individuals that will
need to be trained on the use of the system.
Determine the system functions that each job class must be
familiar with to enable them to successfully interface with the
system.
Inputs:
Baselined SRS,
Training Plan
Template
Outputs:
Draft Training Plan
Training Team
Project Team
20.
Review Training Plan and Provide Comments
Review the Training Plan for approval.
Inputs:
Internally
Approved Training
Plan
Outputs:
Customer Review
comments and
approval
Training Team
Technical PM
Training Team,
Software
Development
Lead
SQA Team,
Business
Program
Manager or
Business
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 77
Step
Description of Activity
Inputs/Outputs
Lead
Participants
Project
Manager
21.
Deliver the Training Plan Document
Incorporate customer comments and deliver the final Training Plan to CM
to be baselined
Inputs:
Customer Review
comments and
approval
Outputs:
Final (baselined)
Training Plan
Training Team
Technical PM,
Software
Development
Lead
SQA Team,
Business
Program
Manager or
Business
Project
Manager
22.
SQA audits the process and products
Refer to the QAP for detailed schedules of the process and products to be
audited.
Inputs:
QAP,
Processes and
Procedures for
Requirements
Phase,
SQA Audit Report
Template
Outputs:
SQA Audit Reports
SQA Team
Project Team,
Business
Program
Manager or
Business
Project
Manager
23.
Update the Project Plan
Develop Work Breakdown Structure (WBS)
Track Project Activity
Update plan with hardware and software purchases
Update estimates
Create project schedule
Re-assess risks if necessary
Project Plan is reviewed and placed under CM control to be version
Inputs:
Draft Project Plan,
WBS Task List,
WBS Task
Description
Outputs:
Version controlled
Project Plan
Technical PM
Project Team,
QA Team,
CM Team
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 78
Step
Description of Activity
Inputs/Outputs
Lead
Participants
controlled.
24.
Conduct Phase Exit Review
Technical PM with assistance from Business Program Manager,
Business Project Manager or Product Owner notifies the project team
and extended project team (users, Points of Contact (POCs), support
areas) that a Phase Exit Review has been scheduled.
- Request that all approvers provide feedback at least one week
before the exit meeting is to be held. (This will allow the Project
manager time to work issues and develop action plans prior to the
exit meeting)
- Invite participants to attend the exit meeting using the Phase Exit
Review Memo along with the review material (Project Plan, and
any other material relevant to the exiting stage which include but
are not limited to known issues, and unplanned deliverables)
- The participants should be familiar with planned deliverables since
it is standard procedure for them to review drafts as they are
developed.
If this is not the case a list of the planned deliverables should
also be distributed at this time.
Review the current Project Plan (at a minimum, a detailed plan for the
next phase and high-level plans for the remainder of the project).
Review other relevant materials to verify if they are in accordance
with OPM’s SDLC
Receive position from the list of approvers (to include the Technical
PM, Chief Architect, IT Security, Business Program Manager or
Business Project Manager) using the Position Response Form. This
position can be concur, concur with qualifications, or non-concur.
The implication of each is as follows:
- Concur Proceed with the project according to the current plan.
(Ex. The Approver is unaware of any issues for the current phase)
- Concur with qualifications There are issues or concerns and the
project can proceed according to the current plan if an acceptable
Inputs:
Phase Deliverables
produced during
current phase,
Initial Project Plan
prior to updates for
next phase,
Latest version
controlled Project
Plan,
New and existing
issues,
Phase Exit Package
Template
Outputs:
Positions from the
approvers,
Issues/concerns (if
any) from review of
the deliverables,
Action plans to
resolve all
issues/concerns,
Risks,
Phase Exit Package
Technical PM
Business
Program
Manager or
Business
Project
Manager,
Project Team
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 79
Step
Description of Activity
Inputs/Outputs
Lead
Participants
action plan is developed for each issue or concern by the meeting.
(Ex. There is no plan for testing an interface to an existing system
that is being changed)
- Non-concur There are very significant issues or concerns and the
project should not move to the next phase until those issues or
concerns are resolved. (Ex. Funding for the project has been
withdrawn)
Prepare acceptable action plan to address each issue or concern
received. Note: Sometimes action plans extend beyond the Phase
Milestone and that is acceptable as long as it will not negatively
impact the current Project Plan. Project Plan is high priority for
successful management of the project.
Conduct Exit Meeting
- Present positions from the Approvers, along with issues and/or
concerns, and any other issues that may be open
- Action plans must be presented for each issue or concern
Document the meeting including positions, issues, concerns, action
plans, and follow-up activity
Obtain concurrence on current stage deliverables, and begin the next
phase of development
Appendix D.3: Design System Components Phase Activities
Step
Description of Activity
Inputs/Outputs
Lead
Participants
1.
Begin the system design activities
Review the Software Requirements Specification (SRS) and the
Requirements Traceability Matrix (RTM) to get a clear understanding
of what the system should do and how the system should respond and
look.
- Gather user and/or customer input if necessary
Design and document the following:
Inputs:
Change Request,
SRS,
RTM,
Software Design
Description (SDD)
Template,
Software
Development Lead
Project Team,
IT Security
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 80
Step
Description of Activity
Inputs/Outputs
Lead
Participants
- General system characteristics ensuring each unit has a unique
identifier (They may already be defined based on the
requirements.)
- User interface at the desktop layer
- Business rules layer or the application logic
- Interfaces from application to application
- Interfaces from application to database
- Process flow and module hierarchy
- Screen templates or prototypes that depict
- Menu structure and standard screen background
- Security Considerations based on System Security Categorization
For a Change to an existing system, review the Change request and
update the system design as needed
OPM Naming
Conventions
Standard
Outputs:
Software design
units
Conceptual
understanding of
requirements,
draft SDD
2.
Review the Software Design Description
Conduct a formal review of the SDD.
Include representatives from:
Other development and maintenance teams whose programs interface
with the units being designed
The acceptance test team (customer) staff if applicable
User and sponsor organizations
Inputs:
draft SDD
Updated RTM,
Outputs:
Reviewed SDD
Software
Development Lead
Project Team,
Quality
Assurance (QA)
Team, IT
Security,
Other Subject
Matter Experts
(SMEs)
3.
Review SDD and provide comments
Review the SDD for approval.
Inputs:
Reviewed SDD
Outputs:
Customer review
comments and
approval,
Updated SDD
Technical PM
Business
Program
Manager or
Business
Project
Manager
4.
Deliver the Final SDD
Incorporate customer comments and deliver the final SDD to
Configuration Management (CM) to be baselined.
Inputs:
Customer review
comments and
approval,
Technical PM
Software
Development
Lead,
CM Team
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 81
Step
Description of Activity
Inputs/Outputs
Lead
Participants
Updated SDD
Outputs:
Final (baselined)
SDD
5.
Create Database Design Description
Review the SRS and the Data Specification (DS) to get a clear idea of
what the system should do and how the system should respond and
look.
- Gather user and/or customer input if necessary.
Document the unique database names. Specify the:
- Code Name, tag, or label by which each database table or file will
be uniquely identified.
- Additional descriptive information whether or not it is implied in
the identification code such as system using the database, the
database status, and a physical description of the database table or
file.
- Database mappings and data model
Document any special instructions for database usage.
- Security Implementation based on Data Categorization
Reference all support software.
- Include 3
rd
party, interfacing, and Commercial Off-the-Shelf
(COTS) software.
- Descriptions should include name, function, major operating
characteristics, and machine run instructions for using the support
software
- Cite the support software documentation by title, number, and
appropriate sections.
Document the Database Management System (DBMS) Configuration.
Include:
- The operating system and storage device on which the DBMS is to
be located.
- Identification of the application software
Inputs:
Change Request
DBDD Template
SRS,
DS
OPM Naming
Conventions
Standard,
OPM Enterprise
Architecture
Outputs:
Conceptual
understanding of
requirements
Draft DBDD
Software
Development Lead
Software
Development
Team
(Database
Lead),
Project Team,
IT Security
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 82
Step
Description of Activity
Inputs/Outputs
Lead
Participants
- All related computer programs that run the database
- The amount of online and offline storage required.
- Special hardware or software required to maintain backup copies
or archived files
- Identification of the Database Schema including the names of all
of database related application programs and data files, as well as
the file sizes of each and data record layouts and descriptions.
For a Change to an existing system, update the database design as
needed
6.
Review the Database Design Description
Conduct a formal review of the DBDD.
Include representatives from:
Other development and maintenance teams whose programs interface
the units being designed
The acceptance test team staff if applicable
User and sponsor organizations
Inputs:
draft DBDD
Updated RTM
Outputs:
Reviewed DBDD
Software
Development Lead
Project Team,
Quality
Assurance (QA)
Team, IT
SecurityTeam,
Other Subject
Matter Experts
(SMEs)
(Database
Lead),
7.
Review DBDD and provide comments
Review the DBDD for approval.
Inputs:
Internally
Approved DBDD
Outputs:
Customer Review
comments and
approval
Technical PM
Business
Program
Manager or
Business
Project
Manager
8.
Deliver the Final DBDD
Incorporate customer comments and deliver the final DBDD to CM to be
baselined.
Inputs:
Customer Review
comments and
approval
Outputs:
Final (baselined)
Technical PM
Software
Development
Lead (Database
Lead),
CM Team
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 83
Step
Description of Activity
Inputs/Outputs
Lead
Participants
DBDD
9.
Expand the Requirements Traceability Matrix (RTM) to reflect the design
units.
Note: Use an automated tool if applicable to update the RTM.
Ensure all requirements have been included in a design unit.
Inputs:
Software design
units,
SDD,
DBDD
baselined RTM
Outputs:
Expanded baselined
RTM
Requirements Team
Software
Development
Lead,
Project Team,
QA Team,
CM Team
10.
Create the System Security Plan (SSP) as directed in the Information
Security and Privacy Policy Web pages located at
http://theo.opm.gov/policies/ispp/
Input:
Applicable security
standards,
SRS
Output:
Understanding of
security standards,
draft SSP
Technical PM
IT Security
Team,
Project Team,
QA Team
11.
Review the SSP and provide comments
Review the SSP for approval.
Inputs:
Customer-ready
SSP
Internally
Approved SSP
Outputs:
Customer Review
comments and
approval
Technical PM
Business
Program
Manager or
Business
Project
Manager, IT
Security Team
12.
Deliver the Final SSP
Incorporate customer comments and deliver the final SSP to CM to be
placed under control.
Inputs:
Customer Review
comments and
approval
Outputs:
Technical PM
IT Security
Team,
CM Team
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 84
Step
Description of Activity
Inputs/Outputs
Lead
Participants
Final (baselined)
SSP
13.
Update Test Plan (Unit & Integration)
Review test strategy to ensure it coincides with the designs
Create test identifiers
Update test execution
Submit to CM to be version controlled.
Inputs:
Version controlled
Test Plan (Unit &
Integration)
Outputs:
Updated Test Plan
(Unit &
Integration)
Software
Development Lead
Software
Development
Team,
Project Team,
CM Team
14.
Review Training Plan
Provide comments and update the plan as applicable.
Review the Training Plan for approval.
Inputs:
Customer-ready
Training Plan
Outputs:
Customer Review
comments and
approval
Technical PM
Business
Program
Manager or
Business
Project
Manager
15.
Deliver the Training Plan Document
Incorporate customer comments and deliver the final Training Plan to CM
to be baselined.
Inputs:
Customer Review
comments and
approval
Outputs:
Final (baselined)
Training Plan
Project Manager
Training
Manager,
CM Team
16.
Develop Training Material as required.
Review the Training Plan and SRS
Develop the applicable training materials that are defined in the
Training Plan and SRS
Examples of these materials include:
- Lesson Plans
- User Training Guides
- Computer-based Training (CBT)
Inputs:
Training Plan
SRS
Outputs:
Training Materials
Training Team
Project Team
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 85
Step
Description of Activity
Inputs/Outputs
Lead
Participants
- Web-based Training
- Pocket Guides
- System Support Guides
- Training Evaluations
Note: References for some of these training materials are listed in the
OPM SDLC
17.
Develop User Manual
Review the SRS and the User Requirements Document (URD), as
needed
Assign User Manual responsibility to Software Development team
member(s)
Develop User Manual
Review the SRS
Refer to the SDD and the DBDD for pertinent information
Ensure User Manual is consistent with the actual system operation, the
SDD, and the DBDD
Conduct a formal review of the User Manual
Approve (baseline) the User Manual
Inputs:
SRS
SDD
DBDD
URD
Outputs:
Approved and
baselined User
Manual
Software
Development Lead
Software
Development
Team
Project Team
18.
SQA audits the process and products
Refer to the SQA Plan for detailed schedules of the processes and
products.
Inputs:
SQA Plan
Processes and
Procedures for
Design Phase
activities
Outputs:
SQA Audit Reports
SQA Team
Project Team
19.
Update Project Plan
Track Project Activity
Update estimates and risks
Update project schedule
Project Plan is reviewed and placed under CM control to be version
Inputs:
Project Plan,
WBS Task List,
WBS Task
Description
Outputs:
Technical PM
Project Team
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 86
Step
Description of Activity
Inputs/Outputs
Lead
Participants
controlled.
Version controlled
Project Plan
20.
Project Plan is reviewed and placed under CM control to be version
controlled.
Inputs:
Updated Project
Plan
CM Procedures
Outputs:
Version Controlled
Project Plan
Technical PM
CM Team
21.
Conduct Phase Exit Review
Notify the project team and extended project team (users, POCs,
support areas) that a Phase Exit Review has been scheduled.
- Require that approvers provide feedback at least one week before
the exit meeting is to be held. (This will allow the Project
manager time to work issues and coordinate action plans prior to
the exit meeting)
- Invite participants to attend the exit meeting using the Phase Exit
Review Memo along with the review material (Project Plan, and
any other material relevant to the exiting stage which include but
are not limited to known issues, and unplanned deliverables)
- The participants should be familiar with planned deliverables since
it is standard procedure for them to review drafts as they are
developed.
If this is not the case a list of the planned deliverables should
also be distributed at this time.
Review the current Project Plan (at a minimum, a detailed plan for the
next phase and high-level plans for the remainder of the project).
Review other relevant materials to verify if they are in accordance
with OPM’s SDLC
Receive position from the list of approvers (to include the Technical
PM, Business Program Manager or Business Project Manager) using
the Position Response Form. This position can be concur, concur with
Inputs:
Phase Deliverables
produced during
current phase
Initial Project Plan
prior to updates for
next phase
Latest version
controlled Project
Plan
New and existing
issues,
Phase Exit Package
Template
Outputs:
Positions from the
approvers,
Issues/concerns (if
any) from the
review of the
deliverables,
Action plans to
resolve all
Technical PM
Project Team
Business
Program
Manager or
Business
Project
Manager,
QA Team
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 87
Step
Description of Activity
Inputs/Outputs
Lead
Participants
qualifications, or non-concur. The implication of each is as follows:
- Concur Proceed with the project according to the current plan.
(Ex. The Approver is unaware of any issues for the current phase)
- Concur with qualifications There are issues or concerns and the
project can proceed according to the current plan if an acceptable
action plan is developed for each issue or concern by the meeting.
(Ex. There is no plan for testing an interface to an existing system
that is being changed)
- Non-concur There are very significant issues or concerns and the
project should not move to the next phase until those issues or
concerns are resolved. (Ex. Funding for the project has been
withdrawn)
Prepare acceptable action plan to address each issue or concern
received. (Note: Sometimes action plans extend beyond the Phase
Milestone which is acceptable as long as it will not negatively impact
the current project schedule)
Conduct Exit Meeting
- Present positions from the Approvers, along with issues and/or
concerns, and any other issues that may be open
- Action plans must be presented for each issue or concern
Document the meeting including positions, issues, concerns, action
plans, and follow-up activity
Obtain concurrence on current stage deliverables, and begin the next
phase of development
issues/concerns
Risks,
Phase Exit Package
Appendix D.4: Build System Components Phase Activities
Step
Description of Activity
Inputs/Outputs
Lead
Participants
1.
Verify that the Development and Test environment has been
Inputs:
Software
Project Team,
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 88
Step
Description of Activity
Inputs/Outputs
Lead
Participants
installed properly
Review the Segment Architecture
Review the User Requirements Document (URD) and the
Software Requirements Specification (SRS)
Assemble and install the hardware software,
communications equipment, databases, and other items
required to support the programming and testing effort.
Segment Architecture,
URD,
DS,
SRS
Outputs:
Development and test
environment in place,
Environment configured
appropriately for development
Development Lead
Network Team
2.
Review and/or plan coding and testing activities
Obtain training on coding and testing methodologies,
techniques and tools.
Review the Project Plan for schedule of activities and for
any standards or tools that should be used during this phase.
Verify objects included in the Software Design Description
and Database Design Description have been included in the
schedule and assigned to the appropriate members of the
development team
Inputs:
Project Plan,
Software Design Description,
Database Design Description
Outputs:
Training, Schedule of
activities for coding and
testing
Software
Development Lead
Project Team,
IT Security
Team
3.
Code individual software units and database in the
programming language(s) selected for the project
Note 1: Regardless of the platform, development of code
should adhere to a consistent set of programming techniques
and error prevention procedures. This will promote reliable,
maintainable code, developed in the most efficient and cost
effective manner.
Review the SDD/DBDD and the SRS
Analyze reuse opportunities
- Reuse available source code assets found in the
Configuration Management Library (CML)
- Determine if source code requires classification or
security protection
- Reuse available test assets
Inputs:
Change Request, SDD,
DBDD,
SRS,
Project Plan,
Reusable source code assets
Outputs:
Developed units,
Code reviews
Software
Development Lead
Software
Development
Team
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 89
Step
Description of Activity
Inputs/Outputs
Lead
Participants
Develop code
- If a Computer Aided Software Engineering (CASE) tool
is being used, use the tool to generate code from the
SDD and DBDD
- Generate source code and machine-readable modules.
- Generate the physical files and database structure.
- Generate video screens, report generation codes, and
plotting instructions as applicable.
- If conversion of an existing system or data is necessary,
generate the program(s) described in the Installation &
Conversion Plan (ICP).
Write code instructions in the selected programming
language that will perform the logic documented in the
SDD/DBDD.
Add comments into the code at appropriate locations to
provide clarifications of the function and logic being
performed.
The types of software units and programs include but are
not limited to:
- Utility Programs edit or sort routines, control of user
access to functions, or error message handling routines
- Input and Output Modules anticipatory retrieval and
caching of data from the database for output, deferred
storage or data formatting
- Application Programs performs actual business logic
- Command Language written in operating system
command language or job control language and that are
used to execute batch jobs, compile programs, execute
programs, and control peripheral devices
Update the SDD/DBDD to reflect any required deviations
from the documented design.
For a Change to an existing system, implement the changes
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 90
Step
Description of Activity
Inputs/Outputs
Lead
Participants
as needed
Note 2: The developers should meet at scheduled intervals to
discuss problems encountered and to facilitate program
integration and uniformity
Note 3: Program uniformity should be achieved by using a
standardized set of naming conventions for programs, data
elements, variables, and files.
Note 4: All code should be backed up on a daily basis in the
CM Library. It should be stored in an offsite location to avoid
catastrophic loss if applicable. (See the Project Plan and
Configuration Management Plan (CMP) for code backup
details.)
Review code
4.
Compile individual code units and correct errors
Compile the source code with error and syntax checking
Identify error messages
Modify the source code to correct the problem
Recompile the program after the changes have been made
Recheck the source code
Repeat the process until no error messages are generated
Inputs:
Developed units,
Code reviews,
Reusable source code assets
Outputs:
Error free compiled code
Software
Development Lead
Software
Development
Team
5.
Inspect and modify code
Note: The inspection team may include experts outside of the
project. Code inspections should be identified as milestones in
the Project Plan.
Perform a review of code using the coding standards that
are referenced in the project plan
Evaluate for:
- Traceability to the requirements and design of the
software item
- External consistency with the requirements and design
of the software item
- Test coverage of the units
Inputs:
Error free compiled code
Project Plan,
Outputs:
Reviewed code
Software
Development Lead
Software
Development
Team
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 91
Step
Description of Activity
Inputs/Outputs
Lead
Participants
- Appropriateness of coding methods and standards used
- Feasibility of the software integration, software testing,
operation and maintenance
Provide feedback to developer of code
Update code with comments received from code inspections
6.
Expand the Requirements Traceability Matrix (RTM) to reflect
the code units and modules
Note: Use an automated tool if applicable to update the RTM.
Ensure all requirements have been included in a code unit or
module
Inputs:
Coded units and modules,
baselined RTM
Outputs:
Expanded baselined RTM
Requirements Team
Software
Development
Lead,
Project Team,
QA Team,
CM Team
7.
Update/Develop Software Test Procedures in the Test Plan
(Unit & Integration)
Review Test Plan (Unit & Integration)
Review SDD, DBDD, and SRS as applicable
Document a procedure for each unit test to be executed for
the program
Examples of what each unit test should contain are as
follows:
- Name of the software module to be tested
- Description and objective of the test
- Any test stubs or drivers to be used in executing the test
- Test data to be used in the test
- Job control language to be executed
- Expected results
- Steps to be taken to execute the test
Review the Test Plan (Unit & Integration)
Version control software test procedures
Inputs:
SDD,
DBDD,
SRS,
Test Plan (Unit &
Integration),
Test Script Samples
Outputs:
Updated Test Plan (Unit &
Integration)
Software
Development Lead
Software
Development
Team
8.
Execute unit tests and place tested code under configuration
control
Unit test code
Inputs:
Code,
Test Result & Evaluation
Report Template,
Software
Development Lead
Software
Development
Team,
CM Team
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 92
Step
Description of Activity
Inputs/Outputs
Lead
Participants
Test each unit and database ensuring it satisfies its
requirements.
Correct any problems found and unit test code again
Repeat this process until no problems are found
Place code (units) under Configuration Management (CM)
control
Report integration testing results using Test Results &
Evaluation Report Template
Place Test Results & Evaluation Report Template under
CM control
Updated Test Plan (Unit &
Integration)
Outputs:
CM controlled and Unit tested
code,
Test Results & Evaluation
Report
9.
Define Integration Tests
Update the TP (Unit & Integration) as necessary
It should identify the following:
- Each integration test to be executed
- System and program requirements to be tested
- Location of each test in the hierarchy of the testing to be
performed
- Software units and programs that are to be included in
the test
- Required test data, including database fields
- External (or existing) programs needed to support the
test
- Procedure for reporting errors, test results, and
reworking and retesting programs
- External APIs/interfaces
- Expected test results
Review the Integration Test Procedures
Approve (baseline) software test procedures
Inputs:
Updated Test Plan (Unit &
Integration)
SDD,
DBDD,
SRS,
Test Script Samples,
Unit tested code
Outputs:
Updated Test Plan (Unit &
Integration)
Software
Development Lead
Software
Development
Team,
CM Team
10.
Integrate software units and components and test as the
aggregates are developed in accordance with the TP (Unit &
Integration)
Inputs:
Test Plan (Unit &
Integration),
Software
Development Lead
Software
Development
Team
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 93
Step
Description of Activity
Inputs/Outputs
Lead
Participants
Compile the source code with error and syntax checking
Identify error messages
Modify the source code to correct the problem
Recompile the program after the changes have been made
Recheck the source code
Repeat the process until no error messages are generated
Ensure each aggregate satisfies the requirements of the
software item and that the software item is integrated at the
conclusion of the integration activity.
Unit Tested code
Outputs:
Error free compiled code
11.
Inspect and modify code
Perform a review of code using the coding standards that
are referenced in the project plan
Provide feedback to the developer of code
Evaluate the integration with the following criteria in mind:
- Traceability to the system requirements
- External consistency with the system requirements
- Internal consistency
- Test coverage of the requirements of the software item
- Appropriateness of test standards and methods used
- Conformance to expected results
Update code with comments received from code inspections
Inputs:
Project Plan
Error free Compiled code,
Unit Tested Code
Outputs:
Reviewed code,
Modified code
Software
Development Lead
Software
Development
Team
12.
Execute Integration Tests and place code under CM control
Create developmental baseline and Build Notification
Conduct integration testing using the TP (Unit &
Integration).
Correct any discrepancies and retest code until no
discrepancies are found
(Optional) Report integration testing results using Test
Results & Evaluation Report Template (some customers
may require a report of the integration testing results)
Place code under CM control
Inputs:
Make files/Job Control
Language (JCL),
Modified code
Build Notification Template
Test Plan (Unit & Integration)
Test Results & Evaluation
Report Template
Outputs:
Updated Make files/JCL,
Software
Development Lead
Software
Development
Team, CM
Team
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 94
Step
Description of Activity
Inputs/Outputs
Lead
Participants
Handoff instructions and code to CM for CM build
CM controlled and Integration
Tested Code,
Updated Test Results &
Evaluation Report,
Build Instructions
13.
Perform software build (establish baseline)
Document the internal build procedures and results in the
Build Instructions
- Identify errors and describe the corrective action that
was taken
Distribute Build Notification
Handoff software to Software Test Team
Inputs:
CM controlled and Integration
Tested Code,
Build Instructions,
Make files or JCL used to
control the build
Outputs:
Updated Build Instructions,
Build Notification,
Software Build of code,
Updated make files or JCL
used to control the build
CM Team
Software
Development
Team
14.
Develop Version Description Document (VDD)
Review FRD, SRS, SDD, DS, DBDD, and SSP, and source
code and related code documentation
Receive input from Developers
Draft the VDD plan
Inputs:
FRD,
SRS,
SDD,
DS,
DBDD,
SSP,
Source code,
Related code documentation
Outputs:
Draft VDD
CM Team
Project Team
15.
Develop Verification, Validation, & Testing (VV&T) Plan
Review FRD, SRS, SDD, DS, DBDD, and SSP
Receive user input
Review test strategy to include any revision resulting from
Inputs:
FRD,
SRS,
SDD,
Software Test
Team
Project Team
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 95
Step
Description of Activity
Inputs/Outputs
Lead
Participants
the this phase’s activities
Review the following to ensure they are accurate:
- Performance requirements
- Test methods
- Test conditions
- Test data criteria
Draft the VV&T plan
Approve (baseline) the VV&T Plan
DS,
DBDD,
SSP
Outputs:
VV&T plan
16.
Finalize the Training Plan
Identify modifications that need to be made to the training
approach to reflect the impact of any changes that may have
occurred during this phase. Consider the following:
- Training schedules
- Student attendance lists (if applicable)
- Training requirements
- Training materials
Review the Training Plan
Approve (baseline) Training Plan
Inputs:
SRS,
DBDD,
SDD
Outputs:
Finalized Training Plan
Training Team
Project Team
17.
Develop Operations Manual
Review SRS, DBDD, SDD
Describe system runs. Include
- Purpose of each run
- Run management requirements
- Descriptions of all related files and databases
- Requirements and procedures for report generation and
reproduction
- Any restart and recovery procedures
Review the Operations Manual
Approve (baseline) Operations Manual
Inputs:
SRS,
SDD,
DBDD
Operations Manual (Client-
Server) or Enterprise Server
Template
Outputs:
Baselined Operations Manual
(Client-Server) or Enterprise
Server
Operations Team
Project Team
18.
Develop Installation and Conversion Plan (ICP)
Review SRS, DBDD, SDD
Inputs:
ICP Template,
Operations Team
Project Team,
IT Security
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 96
Step
Description of Activity
Inputs/Outputs
Lead
Participants
Develop procedures that must be followed when the system
is installed: Include
- Support materials needed such as Legacy Data
Migration Schedule
- Personnel requirements
- Security requirements
- Special training needs if any
- Installation schedule
- Inventory of hardware and software to be installed
- Operation facility requirements
- Procedures to be followed during installation
Develop ICP
Review ICP
Approve (baseline) ICP
SRS,
DBDD,
SDD
Outputs:
Baselined ICP
Team
19.
QA audits the Processes and Products
Inputs:
Products and processes
produced during this phase
Outputs:
Results from the Reviews and
Audits conducted
SQA Team
Project Team
20.
Update Project Plan
Track project activities
Update estimates
Update risks
Update schedule
Project Plan is reviewed and placed under CM control to be
version controlled.
Inputs:
Project Plan,
WBS Task List,
WBS Task Description
Outputs:
version controlled Project
Plan
Technical PM
Project Team
21.
Conduct Phase Exit Review
Notify the project team and extended project team (users,
POCs, support areas) that a Phase Exit Review has been
scheduled.
Inputs:
Phase Deliverables produced
during current phase,
Initial Project Plan prior to
Technical PM
Business
Program
Manager or
Business
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 97
Step
Description of Activity
Inputs/Outputs
Lead
Participants
- Request that approvers provide feedback at least one
week before the exit meeting is to be held. (This will
allow the Technical Project Manager time to work
issues and develop action plans prior to the exit
meeting)
- Invite participants to attend the exit meeting using the
Phase Exit Review Memo along with the review
material (Project Plan, and any other material relevant to
the exiting stage which include but are not limited to
known issues, and unplanned deliverables)
- The participants should be familiar with planned
deliverables since it is standard for them to review drafts
as they are developed.
If this is not the case a list of the planned
deliverables should also be distributed at this time.
Review the current Project Plan (at a minimum, a detailed
plan for the next phase and high-level plans for the
remainder of the project).
Review other relevant materials to verify if they are in
accordance with OPM’s SDLC
Receive position from the list of approvers (to include the
Technical PM, Business Program Manager or Business
Project Manager) using the Position Response Form. This
position can be concur, concur with qualifications, or non-
concur. The implication of each is as follows:
- Concur Proceed with the project according to the
current plan. (Ex. The Approver is unaware of any
issues for the current phase)
- Concur with qualifications There are issues or
concerns and the project can proceed according to the
current plan if an acceptable action plan is developed for
each issue or concern by the meeting. (Ex. There is no
updates for next phase,
Latest version controlled
Project Plan,
New and existing issues,
Phase Exit Package Template
Outputs:
Positions from the approvers,
Issues/concerns (if any) from
the review of the deliverables,
Action plans to resolve all
issues/concerns
Risks,
Phase Exit Package
Project
Manager,
Project Team
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 98
Step
Description of Activity
Inputs/Outputs
Lead
Participants
plan for testing an interface to an existing system that is
being changed)
- Non-concur There are very significant issues or
concerns and the project should not move to the next
phase until those issues or concerns are resolved. (Ex.
Funding for the project has been withdrawn)
Prepare acceptable action plan to address each issue or
concern received. (Note: Sometimes action plans extend
beyond the Phase Milestone and that is acceptable as long
as it will not negatively impact the current Project Plan)
Conduct Exit Meeting
- Present positions from the Approvers, along with issues
and/or concerns, and any other issues that may be open
- Action plans must be presented for each issue or
concern
Document the meeting including positions, issues, concerns,
action plans, and follow-up activity
Obtain concurrence on current stage deliverables, and begin the
next phase of development
Appendix D.5: Evaluate System Readiness Phase Activities
Step
Description of Activity
Inputs/Outputs
Lead
Participants
1.
Finalize the Test Environment and components of the test to be
executed.
Verify the system test environment meets the specific
requirements related to the actual production system.
- Ensure the hardware has been installed and that
computer time has been made available for the test team
(if the tests are to be run using the production
hardware).
Inputs:
Verification, Validation &
Testing (VV&T) Plan
Outputs:
Finalized test environment,
Test procedures,
Test data,
Updated VV&T Plan
Test Team
Project Team,
IT Security
Team
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 99
Step
Description of Activity
Inputs/Outputs
Lead
Participants
- Ensure security access to files and data base areas are in
place for the test.
Finalize Test Procedures and Scenarios by making any
necessary changes to the procedures in the following areas:
- Objectives of each test or test description,
- Resources needed to execute the test,
- Steps to be taken to execute the test,
- Expected results.
Finalize Test Data
- Modify the data, if necessary, to allow all test conditions
to be executed.
- Make any necessary final modifications to the test data
by using utilities provided by the Database Management
System (DBMS), Structured Query Language (SQL) or
other data manipulation tools.
2.
Prepare to execute tests, begin execution of tests, and verify
results:
Review the following:
- VV&T Plan,
- OPM’s IT Security Policy,
- System Security Plan (SSP),
- Software Requirements Specification (SRS),
- Test Results & Evaluation Report (Unit & Integration
Results),
- Related opened and deferred, Change Requests (CRs).
Verify:
Access and data security requirements are met and
procedures to assign and activate user IDs.
Under normal and high-load conditions:
- System response timing,
- Memory,
- Performance,
Inputs:
Finalized test environment,
Test procedures,
Test data,
Updated VV&T Plan,
OPM’s IT Security Policy,
SSP,
SRS,
Test Results & Evaluation
Report (Unit & Integration
Results),
Opened/deferred CRs
Software components
Outputs:
Refreshing of the test
activities and related material
Test Team
Project Team,
Business
Program
Manager or
Business
Project
Manager/Users,
IT Security
Team
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 100
Step
Description of Activity
Inputs/Outputs
Lead
Participants
- Security and functional accuracy of logic and
numerical calculations,
- Query and report capabilities
Any inter-system incompatibilities, performance
inadequacies or other deficiencies due to ambiguities or
omissions in the systems requirements.
Follow the steps necessary to execute each test procedure
(or scenario) as documented in the VV&T Plan.
- If additional steps are necessary to execute the test,
record the additional steps in the test procedure
documentation.
Note 1: Users are expected to participate in the system tests to
gain their confidence in the software product and to receive an
early indication of any problems from the user’s perspective.
Note 2: Inform users that errors and discrepancies may occur
during testing and explain the error correction, configuration
management and retest process.
Tested software components
Test results
3.
Record and Verify Test Results
Upon completion of individual tests identified in the
VV&T Plan, compare the actual results against expected
results
If deviations from the expected results are discovered,
review the predetermined results to ensure the results are
correctly stated.
Record and track results in the Test Results and Evaluation
Report each time a test or retest is performed and log the
information in chronological order to serve as a historical
document of the test.
Note: Any failed components should be migrated back to the
Build Phase for rework and passed components should be
migrated ahead for security testing.
Inputs:
Tested software components
VV&T Plan
Test results
Outputs:
Change Requests (CRs),
Test Results and Evaluation
Report
Test Team
Project Team
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 101
Step
Description of Activity
Inputs/Outputs
Lead
Participants
4.
Report findings (discrepancies) by completing a CR
Note: Supporting documentation may include images of the test
data before and after the test was executed, series of screen
shots with narratives showing the exact sequence of events that
led up to the error and actual system reports with errors
highlighted
If appropriate, minor problems can be corrected and
regression tested by the project team programmers within
the time frame allotted for the system testing.
If corrective action tool is used, record findings in tool.
If tool is not used, use the CR Form to record findings.
Inputs:
Tested software components
Test results,
CR Form if applicable
Outputs:
CRs
Test Team
Project Team
5.
Submit CRs to Configuration Control Board
Any corrections or changes to the software product must be
controlled under configuration management.
Major problems may be cause to suspend or terminate the
system test, which should then be rescheduled to begin after
all of the problems are resolved.
Inputs:
CRs
Outputs:
Decision made on CRs from
the CCB
Test Team
Project Team,
CM Team
6.
Retest corrections submitted
Repeat steps 2-6 as appropriate until all tests have been
executed and documented in the Test Results and Evaluation
Report
Inputs:
Reworked modules
Outputs:
Completely tested modules
Test Team
CM Team
7.
Evaluate the Results
Compile the outcome of each individual test documented in
the VV&T plan into the Test Results & Evaluation Report
along with evaluation of test methods and test procedures.
Compare the test results to the expected results recorded as
part of the test documentation
Submit the Test Results and Evaluation Report to the CCB
for final review and approval (baseline)
Close out any open CRs
Inputs:
Test Result
VV&T Plan
Open CRs
Outputs:
Test Results and Evaluation
Report
Risk Assessments
Closed CRs
Test Team
Project Team,
IT Security
Team
8.
Expand the Requirements Traceability Matrix (RTM) to reflect
Inputs:
Requirements Team
Software
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 102
Step
Description of Activity
Inputs/Outputs
Lead
Participants
the test cases.
Note: Use an automated tool if applicable to update the
Traceability Matrix.
Ensure all requirements have been included in a test case.
Verification, Validation, &
Testing Plan (test cases),
SDD,
DBDD
baselined RTM
Outputs:
Updated baselined RTM
Development
Lead,
Project Team,
QA Team,
CM Team
9.
Conduct Configuration Audit
Assess whether the system, subsystem or configuration item
meets its technical requirements and if any adhoc changes
are scheduled for the delivery
Inputs:
System
Subsystem
Configuration items
Outputs:
Configuration Audit Report
CM Team
Project Team
10.
Update the Version Description Document (VDD)
Review Build Notification, Functional Requirements
Document (FRD), SRS, Software Design Description
(SDD), Data Specification (DS), Database Design
Description (DBDD), and SSP, and source code and related
code documentation
Receive input from Developers if necessary
Update the VDD with new information if applicable
Inputs:
Build Notification
FRD
SRS
SDD
DS
DBDD
SSP
Source code
Related code documentation
Outputs:
Updated VDD
CM Team
Project Team
11.
Finalize the Installation & Conversion Plan (ICP)
Update as required the ICP based on any modifications
necessary to the system as a result of testing.
Address all applicable installation and conversion
procedures including pilot and production sites.
Sample problems or applications should be provided as test
cases to ensure correct installation and operation.
Inputs:
Modifications
ICP
Outputs:
Updated and baselined ICP
Operations Team
CM Team
Project Team
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 103
Step
Description of Activity
Inputs/Outputs
Lead
Participants
Conduct a formal review of the ICP
Approve (baseline) the ICP
12.
Test Training Material as required.
Review the Training Plan and SRS
Review the applicable training materials that are defined in
the Training Plan and SRS
Examples of these materials include:
- Lesson Plans
- User Training Guides
- Computer-based Training (CBT)
- Web-based Training
- Pocket Guides
- System Support Guides
- Training Evaluations
Note: References for some of these training materials are listed
in the OPM SDLC
Inputs:
Training Plan
SRS
Training Materials
Outputs:
Tested Training Materials
Training Team
Project Team
13.
Test User Manual
Review the SRS and the User Requirements Document
(URD), as needed
Test the User Manual as applicable
Refer to the SDD and the DBDD for pertinent information
Ensure User Manual is consistent with the actual system
operation, the SDD, and the DBDD
Inputs:
SRS,
SDD,
DBDD,
URD,
User Manual
Outputs:
Tested User Manual
Software
Development Lead
Software
Development
Team
Project Team
14.
Complete the Security Assessment and Authorization (SA&A)
for the system.
Review OPM’s IT Security and Privacy Policy
Create the SA&A package which includes:
- SSP
- Project Plan (Risk Assessment and Mitigation section)
- VV&T (security section)
- Test Results and Evaluation Report (security section)
Inputs:
OPM’s IT Security and
Privacy Policy,
SSP,
Project Plan (Risk
Assessment and Mitigation
section),
VV&T (security section), Test
Technical PM
Security Team,
Test Team,
Project Team,
Certifying
Official (CO)
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 104
Step
Description of Activity
Inputs/Outputs
Lead
Participants
- Certification Statement
- Accreditation Recommendation
Ensure that the steps outlined in the OPM IT Security and
Privacy Policy, which are applicable to the type of software
that was developed, have been completed
Results and Evaluation Report
(security section)
Outputs:
SA&A Package
15.
Seek Authorization by the Authorizing Official (AO) by
submitting the SA&A Package
The AO can make one of the three authorization decisions:
- Authorize the system to operate
- Grant interim operating approval for a specific time
pending satisfactory completion of satisfied
requirements
- Deny permission to operate until identified deficiencies
are corrected
Inputs:
SA&A Package
Outputs:
AO decision
AO
Project Team,
CO, IT Security
Team
16.
SQA audits the process and products
Inputs:
Processes and procedures for
Evaluation Phase
Outputs:
QA Audit Reports
SQA Team
Project Team
17.
Update Project Plan
Determine if the project estimates for resources, cost, and
schedule need to be revised.
Review the Project Plan for accuracy and completeness of
all of this phase’s activities.
Project Plan is reviewed and placed under CM control to be
version controlled.
Inputs:
Project Plan,
WBS Task List,
WBS Task Description
Outputs:
Version controlled Project
Plan
Technical PM
Project Team
18.
Conduct Phase Exit Review
Notify the project team and extended project team (users,
POCs, support areas) that a Phase Exit Review has been
scheduled.
- Request that approvers provide feedback at least one
week before the exit meeting is to be held. (This will
Inputs:
Phase Deliverables produced
during current phase,
Initial Project Plan prior to
updates for next phase,
Updated Project Plan,
Technical PM
Business
Program
Manager or
Business
Project
Manager,
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 105
Step
Description of Activity
Inputs/Outputs
Lead
Participants
allow the Project manager time to work issues and
develop action plans prior to the exit meeting)
- Invite participants to attend the exit meeting using the
Phase Exit Review Memo along with the review
material (Project Plan, and any other material relevant to
the exiting stage which include but are not limited to
known issues, and unplanned work product(s))
- The participants should be familiar with planned
deliverables since it is common practice for them to
review drafts as they are developed. If this is not the
case, a list of the planned deliverables should also be
distributed at this time.
Review the current Project Plan (at a minimum, a detailed
plan for the next phase and high-level plans for the
remainder of the project).
Review other relevant materials to verify if they are in
accordance with OPM’s SDLC
Receive position from the list of approvers (to include the
Technical PM, IPT members, Business Program Manager or
Business Project Manager) using the Position Response
Form. This position can be concur, concur with
qualifications, or non-concur. The implication of each is as
follows:
- Concur Proceed with the project according to the
current plan. (Ex. The Approver is unaware of any
issues for the current phase)
- Concur with qualifications There are issues or
concerns and the project can proceed according to the
current plan if an acceptable action plan is developed for
each issue or concern. (Ex. There is no plan for testing
an interface to an existing system that is being changed)
- Non-concur There are very significant issues or
New and existing issues
Outputs:
Positions from the approvers,
Issues/concerns (if any) from
review of the deliverables,
Action plans to resolve all
issues/concerns,
Concurrence
Project Team
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 106
Step
Description of Activity
Inputs/Outputs
Lead
Participants
concerns and the project should not move to the next
phase until those issues or concerns are resolved. (Ex.
operating system changed during development)
Prepare acceptable action plan to address each issue or
concern received. (Note: Sometimes action plans extend
beyond the Phase Milestone and that is acceptable as long
as it will not negatively impact the current Project Plan)
Conduct Exit Meeting
- Present positions from the Approvers, along with issues
and/or concerns, and any other issues that may be open
Action plans must be presented for each issue or concern
Document the meeting including positions, issues, concerns,
action plans, and follow-up activity
Obtain concurrence on current phase deliverables, and begin
the next phase of development
Appendix D.6 : Deploy the System Phase Activities
Step
Description of Activity
Inputs/Outputs
Lead
Participants
1.
Prepare the pilot (test) site for installation
Ensure the pilot environment is correctly established by
reviewing all equipment and site facilities.
- Notify affected personnel and organizations about the
upcoming installing and conversion, and schedule
meetings to ensure that all affected personnel are
aware of any procedural changes.
- Consider selecting a site that is most closely aligned
with the most complex installation as possible to
ensure that all installation and operational issues are
Inputs:
ICP
Outputs:
Review of the environment
Operations Team
Project Team
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 107
Step
Description of Activity
Inputs/Outputs
Lead
Participants
adequately tested
- At the pilot site, perform a review of the equipment
and physical environment where the equipment will be
located to ensure that all safety regulations have been
followed and that the installation and conversion
procedures were carried out in accordance with the
Installation Conversion Plan (ICP)
2.
Execute the ICP at the pilot site
Install the hardware and software for the new system at
the pilot site in accordance with the ICP.
Verify that only required hardware and software are
installed in the pilot test environment
Convert or install the necessary data and databases and
initiate system performance monitoring functions
Inputs:
ICP
System hardware
System software
Outputs:
Installation and conversion of
the system
Operations Team
Project Team
3.
Control Pilot Environment
Ensure that the integrity of the system is preserved during
installation.
Review the list of equipment to ensure that all
components necessary for the pilot site are installed.
Inputs:
Pilot environment
Outputs:
controlled pilot environment
Operations Team
Project Team
4.
Complete the pilot tests
Verify by inspection or test that data conversion has been
implemented correctly.
If problems are encountered, follow the problem
resolution procedures defined in the ICP
Inputs:
ICP
installed and converted
system
Outputs:
Passed pilot tests
Operations Team
Project Team
5.
Conduct Pilot Site Training
Complete the training modules, acquire the necessary
training resources, schedule the training sessions, and
notify the system users about the schedule
Monitor training activities to determine if the selected
training techniques are achieving the desired results
Analyze feedback received from personnel attending the
Inputs:
Training Plan
Outputs:
Feedback from training
conducted
Training Team
Project Team
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 108
Step
Description of Activity
Inputs/Outputs
Lead
Participants
pilot training sessions, and based on this analysis, refine
the training procedures/materials to ensure the training
objectives are met
6.
Determine Pilot Readiness
Notify the Project Sponsor and user organization that
piloting activities are ready to begin
Be prepared to discuss the steps of the installation
process, the equipment installed, and tests performed to
show the users that the system is ready to be used in the
pilot environment
Inputs:
Feedback from training
conducted
Pilot test results
ICP
Outputs:
System that is ready to be
operated in the pilot
environment
Technical PM
Project Team
Business
Program
Manager or
Business
Project
Manager
7.
Operate the system in the Pilot Environment
Ensure the system performs the transactions or functions
for which it was designed
- System performance meets or exceeds required
capabilities
- Necessary computer time has been scheduled for the
system
- Resources necessary for the system to run correctly
are available
- Personnel are available to run the pilot system in
parallel with the existing systems
Inputs:
User’s Manual
Outputs:
System operating in the pilot
environment
Operations Team
Project Team
8.
Document results and make recommendations
Document system performance and problems in a Pilot
Test Report or documentation can be created by
automated techniques, such as:
- Using the operating system’s ability to capture
information concerning Central Processing Unit
(CPU) time
- Disk input and output
- Number of lines printed
Inputs:
System operating in the pilot
environment
Outputs:
Results and recommendations
based on the system’s reaction
to operating in the pilot
environment
Operations Team
Project Team
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 109
Step
Description of Activity
Inputs/Outputs
Lead
Participants
- Elapsed time
- The number of jobs or steps processed.
9.
Approve System in Pilot Environment
Review Pilot Test Results with the Business Program
Manager or Business Project Manager, Technical PM.
Highlight:
- Project requirements and functions performed in the
pilot environment,
- Results of pilot operation,
- Any outstanding system problems
Receive approval to move forward to promote system to
production.
Inputs:
Results and recommendations
based on the system’s reaction
to operating in the pilot
environment
Outputs:
Approval to promote system
to production
Operations Team
Business
Program
Manager or
Business
Project
Manager
Technical PM
10.
Establish Production Baseline
Maintain strict version and configuration control over this
baseline
Conduct periodic audits to verify that only approved
requirements and changes are incorporated into the
baseline
Ensure Service Level Agreements (SLA) or Operating
Level Agreements (OLA) are ready to be implemented for
the production environment
Inputs:
All software related products
Established system CM
procedures
Established SLA/OLA
Outputs:
Controlled production
baseline
CM Team
Project Team,
Business
Program
Manager or
Business
Project
Manager
11.
Conduct Training for all users
Modify training materials to reflect any corrections or
changes to the system that may have resulted from
deficiencies found during pilot testing
Schedule training classes for all affected personnel
Ensure that training facilities and equipment have been
reserved in advance
Conduct training sessions in accordance with the Training
Plan
Elicit feedback from personnel to ensure training
Inputs:
Training Plan
Training Materials
Outputs:
Updated Training Plan
Updated Training Materials
Feedback from training
Training Team
Project Team
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 110
Step
Description of Activity
Inputs/Outputs
Lead
Participants
objectives were met
Evaluate effectiveness of training
Make recommendations for changes to training
procedures or materials to ensure that training objectives
are met
Respond to recommendations made as a result of
analyzing feedback
12.
Prepare the production site for installation
Ensure the production environment is correctly
established by reviewing all equipment and site facilities.
- Notify affected personnel and organizations about the
upcoming installing and conversion, and schedule
meetings to ensure that all affected personnel are
aware of any procedural changes.
- At the production site, perform a review of the
equipment and physical environment where the
equipment will be located to ensure that all safety
regulations have been followed and that the
installation and conversion procedures were carried
out in accordance with the ICP
Inputs:
ICP
Outputs:
review of the environment
Operations Team
Project Team
13.
Execute the ICP at the production site
Install the hardware and software for the new system at
the production site in accordance with the ICP.
Install the system in production mode and establish user
password and security authorization when required
Complete all conversions of data and databases
Inputs:
ICP
Hardware
Software
Outputs:
Installation and conversion of
the system
Operations Team
Project Team,
IT Security
Team
14.
SQA audits the process and products
Inputs:
Products and processes
produced during this phase
Outputs:
SQA Audit Reports
SQA Team
Project Team
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 111
Step
Description of Activity
Inputs/Outputs
Lead
Participants
15.
Update Project Plan
Determine if the project estimates for resources, cost, and
schedule need to be revised.
Review the Project Plan for accuracy and completeness of
all of this phase’s activities.
Project Plan is reviewed and placed under CM control to
be version controlled.
Inputs:
Project Plan,
WBS Task List,
WBS Task Description
Outputs:
Version controlled Project
Plan
Technical PM
Project Team
16.
Conduct Phase Exit Review
Notify the project team and extended project team (users,
POCs, support areas) that a Phase Exit Review has been
scheduled.
- Request that approvers provide feedback at least one
week before the exit meeting is to be held. (This will
allow the Project manager time to work issues and
develop action plans prior to the exit meeting)
- Invite participants to attend the exit meeting using the
Phase Exit Review Memo along with the review
material (Project Plan, and any other material relevant
to the exiting stage which include but are not limited
to known issues, and unplanned deliverables)
- The participants should be familiar with planned
deliverables since it is standard procedure for them to
review drafts as they are developed. If this is not the
case, a list of the planned deliverables should also be
distributed at this time.
Review the current Project Plan for task completion
Review other relevant materials to verify if they are in
accordance with OPM’s SDLC
Receive position from the list of approvers (to include the
Technical PM, IPT members, Business Program Manager
or Business Project Manager) using the Position Response
Form. This position can be concur, concur with
Inputs:
Phase Deliverables produced
during current phase
Initial Project Plan prior to
updates for production rollout
Updated Project Plan
New and existing issues
Outputs:
Issues
Plans for addressing issues
Risks
Technical PM
Project Team
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 112
Step
Description of Activity
Inputs/Outputs
Lead
Participants
qualifications, or non-concur. The implication of each is
as follows:
- Concur Proceed with the project according to the
current plan. (Ex. The Approver is unaware of any
issues for the current phase)
- Concur with qualifications There are issues or
concerns and the project can proceed according to the
current plan if an acceptable action plan is developed
for each issue or concern by the meeting. (Ex. There
is no plan for testing an interface to an existing system
that is being changed)
- Non-concur There are very significant issues or
concerns and the project should not move to
production until those issues or concerns are resolved.
(Ex., Operating system changed during development)
Prepare acceptable action plan to address each issue or
concern received. (Note: Sometimes action plans extend
beyond the Phase Milestone and that is acceptable as long
as it will not negatively impact the current Project Plan)
Conduct Exit Meeting
- Present positions from the Approvers, along with
issues and/or concerns, and any other issues that may
be open
- Action plans must be presented for each issue or
concern
Document the meeting including positions, issues,
concerns, action plans, and follow-up activity
Obtain concurrence on current phase deliverables, and
begin the rollout into production
17.
Complete the System Sign-off Package with approval by the
Technical PM and Business Program Manager or Business
Project Manager concurrent approval
Inputs:
Installation and conversion of
the system
Technical PM
Business
Program
Manager or
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 113
Step
Description of Activity
Inputs/Outputs
Lead
Participants
Outputs:
System Sign-off Package
Business
Project
Manager
Appendix D.7: Decommission the System Phase
Ste
p
Description of Activity
Inputs/Outputs
Lead
Participants
1.
Complete the Decommission Form.
Fill in and complete the decommission form as much as
possible
Some information may need to be filled in as the system is
decommissioned
Inputs:
Identified Need or a Change
Request (CR)
Decommission Form
Template
Outputs:
Filled in Decommission Form
System Owner
Technical
Advisor, IT
Security Team
2.
Announce the decommissioning of the target system.
Notify all known users of the system of:
- The decision to terminate the operation of the system
before the actual termination date
- The planned date after which the system will no
longer be available
- Include those responsible for other interfacing
systems, and operations staff members involved in
running the system
Inputs:
Filled in Decommission Form
Outputs:
Notification of the system be
decommissioned
System Owner
IT Security
Team
3.
Begin decommissioning the target system.
Decommission the target system
Coordinate with affected systems that need data/files
transferred/migrated
Coordinate with replacement system PM team to ensure
Inputs:
Target System
System artifacts and files
Outputs:
Archived files and artifacts
Equipment/facilities prepared
System Technical
Project Manager
Project Team
supporting the
targeted system,
IT Security
Team
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 114
Ste
p
Description of Activity
Inputs/Outputs
Lead
Participants
smooth transition from the old system to the new
for disposal
4.
Modify affected system interfaces as required.
Inputs:
Change Request
System interface agreement
System design document
Outputs:
Modified systems
Affected system
PMs
Affected system
project teams
5.
Test affected systems.
Inputs:
System test plan
Outputs:
Test Results and Evaluation
Report
Affected system
PMs
Affected system
project teams
6.
Update policies and procedures.
Based on changes to the system, make changes to the
policies and procedures affected by the
decommissioning
Inputs:
Change Request Modified
systems
Outputs:
Updated policies and
procedures
Affected System
Owners
Program Office
Personnel/users
7.
Conduct system close out review.
Notify the project team and applicable stakeholders
(users, support areas, etc) that a System Closeout Review
has been scheduled.
Review the status of the decommissioned system and
affected systems
- Archived files and artifacts
- Equipment/facilities prepared for disposal
- Affected systems status and test results
Document the meeting
Inputs:
Completed Decommission
Form
Test Results and Evaluation
Report(s)
Outputs:
Meeting minutes
System
Owner/Business
Program Manager
or Business Project
Manager
Project Team
Executive
Sponsor
Others as
needed, IT
Security Team
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 115
APPENDIX E: PROJECT CATEGORIES AND PROJECT DOCUMENTATION LEVEL
Appendix E.1: Project Categories
In order to determine the level of SDLC documentation required for a project, the Business
Program Manager or Business Project Manager must determine the Project Category within the
areas discussed below:
Appendix E.1.1 - Determine type of development
Appendix E.1.2 - Estimated funding for the project
Appendix E.1.3 - Duration of the project
Appendix E.1.4 - Project Risk
Appendix E.1.5 - Project Complexity
Appendix E.1.6 - Special Interests
Appendix E.1.1: Determine type of development
The Business Program Manager or Business Project Manager determines the type of
development needed to support the project.
The type of development is chosen from the following types:
New - A system will be implemented where no system currently exists with the intended
functionality or will replace an existing system.
COTS (base) - A project that will implement a Commercial Off-the-Shelf (COTS)
product requiring no modifications and no integration to other systems.
Cloud (base) A project that will implement a Cloud solution requiring no modifications
and no integration to other systems
COTS (modification) - A project that will implement a Commercial Off-the-Shelf
(COTS) product requiring modifications or integration to other systems.
Cloud (modification) A project that will implement a Cloud solution requiring
modifications or integration to other systems.
Enhancement - A project that will require changes to an existing system’s architecture or
interface.
Maintenance - A project that will make changes to an existing system, but not change the
architecture or interfaces.
Appendix E.1.2: Funding for the project.
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 116
The Business Program Manager or Business Project Manager determines the initial estimated
cost of the project and the authorized funding. At the current time, a project is funded at either
less than $50,000; between $50,000 and $100,000; or it is over $100,000
Appendix E.1.3: Duration of the project
The Business Program Manager or Business Project Manager has reviewed the project needs and
determined the estimated time required to development the system. At the current time, a project
is either less than 6 months or it is over 6 months.
Appendix E.1.4: Project Risk
The Business Program Manager or Business Project Manager will have reviewed all external and
internal factors which can affect the project. These factors will determine the project risk. At
the current time, a project can have risk levels that are low, medium and high.
Appendix E.1.5: Project Complexity
The Business Program Manager or Business Project Manager has reviewed the project needs and
determined that a project has a certain level of interdependencies. Those interdependencies will
affect the project’s complexity and be rated low, medium or high.
Appendix E.1.6: Special Interests
There are potential internal and external factors which can affect the project. Some examples
would be new presidential directives or other Federal Government directives. The Business
Program Manager or Business Project Manager will need to indicative yes or no as to whether
the project is affected by internal and external factors.
Appendix E.2: Project Documentation Level
After the Business Program Manager or Business Project Manager has reviewed and determined
the Project Categories in Appendix E.1, the Project Documentation Level should be determined.
The Project Documentation Level will consist of five levels:
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 117
Project Categories
Project
Documentation
Level
New Development or COTS (modification) or Cloud
(modification)
Cost estimation of less than $50,000 or,
Project duration less than 3 months or,
low Risk or,
low Complexity
and
no special interest
1
New Development or COTS (modification) or Cloud
(modification)
Cost estimation of greater than $50,000 but less
than $100,001 or,
Project duration greater than 3 months and less
than 6 months or,
medium Risk or,
medium Complexity
and
no special interest
2
Maintenance, Enhancement, COTS (base) or Cloud
(base)
Cost estimation of less than $100,001 or,
Project duration less than 6 months or,
low to medium Risk or,
low to medium Project Complexity
and
no special interest
3
New Development or COTS (modification) or Cloud
(modification)
Cost estimation greater than $100,000 or,
Project duration greater than 6 months or,
high Risk or,
high Complexity or,
special interest
4
Maintenance, Enhancement, COTS (base) or Cloud
(base)
Cost estimation of greater than $100,000 or,
Project duration greater than 6 months or,
High Risk or,
High Complexity or,
Special Interest
5
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 118
Appendix E.2.1: Project Documentation Level 1
Project Documentation Level 1 supports projects encompassing new development less than
$50,000, less than 3 months duration, low risk, low complexity and no special interest.
Deliverables
Determine
Need
Define
Requirements
Develop
Design
Build
Components
Evaluate
Readiness
Deploy
System
Needs Statement
Create
User Requirements Document
Create
Project Plan
Create
Update
Update
Update
Update
Quality Assurance
Plan
Create
Update
Update
Update
Update
Software Requirements
Specification
Create
Requirements Traceability
Matrix (RTM)
Create
Update
Update
Update
Update
Test Plan (Unit & Integration)
Create
Update
Training Plan
Create
Update
Software Design Description
Create
Information Systems Security
Plan
Create
Verification, Validation &
Testing Plan
Create
Installation/Conversion Plan
Create
Test Results & Evaluation
Report (Unit & Integration)
Create
Test Results & Evaluation
Report (VV&T)
Create
Operations Manual
Create
Update
User Manual
Create
Training Materials
Create
System Assessment and
Authorization
Create
System Sign-off Package
Create
Phase Exit Package
Create
Create
Create
Create
Create
Create
Legend: Create Create the documentation, Update Update the documentation,
Appendix E.2.2: Project Documentation Level 2
Project Documentation Level 2 supports projects encompassing new development between
$50,000 and $100,000, greater than 3 months but less than 6 months in duration, medium risk,
medium complexity and no special interest.
Deliverables
Determine
Need
Define
Requirements
Develop
Design
Build
Components
Evaluate
Readiness
Deploy
System
Needs Statement
Create
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 119
Deliverables
Determine
Need
Define
Requirements
Develop
Design
Build
Components
Evaluate
Readiness
Deploy
System
User Requirements Document
Create
Project Plan
Create
Update
Update
Update
Update
Configuration
Management Plan
Create
Update
Update
Update
Update
Quality Assurance
Plan
Create
Update
Update
Update
Update
Risk Matrix
Create
Update
Update
Update
Update
Data Specification
Create
Software Requirements
Specification
Create
Requirements Traceability
Matrix (RTM)
Create
Update
Update
Update
Update
Test Plan (Unit & Integration)
Create
Update
Training Plan
Create
Update
Software Design Description
Create
Database Design Description
Create
Information Systems Security
Plan
Create
Version Description Document
Create
Verification, Validation &
Testing Plan
Create
Installation/Conversion Plan
Create
Test Results & Evaluation
Report (Unit & Integration)
Create
Test Results & Evaluation
Report (VV&T)
Create
Operations Manual
Create
Update
User Manual
Create
Training Materials
Create
System Assessment and
Authorization
Create
System Sign-off Package
Create
Phase Exit Package
Create
Create
Create
Create
Create
Create
Legend: Create Create the documentation, Update Update the documentation,
Appendix E.2.3: Project Documentation Level 3
Project Documentation Level 3 supports projects encompassing maintenance or system
enhancements as well as Cloud or COTS requiring no modifications under $100K, less than 6
months in duration, low to medium risk, low to medium complexity and no special interest.
Projects implementing a Cloud or COTS solution with no modification require a Need
Statement document to be developed. The project commences with the creation of a
Project Plan in the Design Phase.
Projects requiring maintenance or system enhancement may require a change to the
system architecture or interfaces. The need is documented on a CR that has been
approved by a CCB. Once the CR has passed through the Needs Phase, the project
commences at Develop System Design Phase. The maintenance and enhancement
changes could be implemented directly in the production environment with system
documentation updated as needed.
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 120
Deliverables
Determine
Need
Define
Requirements
Develop
Design
Build
Components
Evaluate
Readiness
Deploy
System
Needs Statement
Create for
Cloud or
COTS (base)
Change Request
Create for
maintenance
/enhancement
Project Plan
Create
for
COTS
(base)/
Update
Update
Update
Update
Configuration
Management Plan
Create
for
COTS
(base)/
Update
Update
Update
Update
Quality Assurance
Plan
Create
for
COTS
(base)/
Update
Update
Update
Update
Risk Matrix
Create
for
COTS
(base)/
Update
Update
Update
Update
Data Specification
Update
Update
Software Requirements
Specification
Update
Update
Requirements Traceability
Matrix (RTM)
Update
Update
Update
Update
Test Plan (Unit & Integration)
Create
for
COTS
(base)/
Update
Training Plan
Create
for
COTS
(base)/
Update
Software Design Description
Update
Database Design Description
Update
Information Systems Security
Plan
Create
for
COTS
(base)/
Update
Version Description Document
Update
Verification, Validation &
Testing Plan
Create for
COTS (base)/
Update
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 121
Deliverables
Determine
Need
Define
Requirements
Develop
Design
Build
Components
Evaluate
Readiness
Deploy
System
Installation/Conversion Plan
Create for
COTS (base)/
Update
Test Results & Evaluation
Report (Unit & Integration)
Create
Test Results & Evaluation
Report (VV&T)
Create
Operations Manual
Create
Update
User Manual
Create for
COTS (base)
Update
Training Materials
Create for
COTS (base)
Update
System Assessment and
Authorization
Create for
COTS
(base)/
Update
Phase Exit Package
Create
Create
Create
Create
System Sign-off Package
Create
Legend : Create Create the documentation, Update Update the documentation
Appendix E.2.4: Project Documentation Level 4
Project Documentation Level 4 supports projects encompassing new development, Cloud or
COTS product integration over $100,000, project duration over 6 months, high risk projects,
high complexity projects or special interest projects.
Deliverables
Determine Need
Define
Requirements
Develop
Design
Build
Components
Evaluate
Readiness
Deploy
System
Needs Statement
Create
Change Request
IT Investment Analysis
Package
Create
Feasibility Study
Create
Cost Benefit
Analysis
Create
User Requirements
Document
Create
Project Plan
Create
Update
Update
Update
Update
Configuration
Management Plan
Create
Update
Update
Update
Update
Quality Assurance
Plan
Create
Update
Update
Update
Update
Risk Matrix
Create
Update
Update
Update
Update
Data Specification
Create
Software Requirements
Specification
Create
Requirements Traceability
Matrix (RTM)
Create
Update
Update
Update
Update
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 122
Deliverables
Determine Need
Define
Requirements
Develop
Design
Build
Components
Evaluate
Readiness
Deploy
System
Test Plan (Unit &
Integration)
Create
Update
Training Plan
Create
Update
Software Design Description
Create
Database Design Description
Create
Information Systems Security
Plan
Create
Version Description
Document
Create
Verification, Validation &
Testing Plan
Create
Installation/Conversion Plan
Create
Test Results & Evaluation
Report (Unit & Integration)
Create
Test Results & Evaluation
Report (VV&T)
Create
Operations Manual
Create
Update
User Guides
Create
Training Materials
Create
Certification & Accreditation
Package
Create
Phase Exit Review Package
Create
Create
Create
Create
Create
Create
System Sign-off Package
Create
Legend : Create Create the documentation, Update Update the documentation
Appendix E.2.5: Project Documentation Level 5
Project Documentation Level 5 supports projects encompassing maintenance or system
enhancement with cost estimation of greater than $100,000, project duration greater than 6
months, high risk project, high complexity project or special interest.
Projects requiring a system enhancement may require a change to the system architecture
or interfaces. This type of effort begins with an identified need from an existing system.
The need is documented on a Change Request (CR) that has been approved by a CCB.
Once the CR has passed through the Needs Phase, the project commences at Design
System Components Phase.
Projects dealing with maintenance effort also start with an approved CR. Typically, a
maintenance effort will not require a change to the system architecture or interfaces.
Once the CR has passed through the Needs Phase, the project commences at the Build
System Components Phase.
Maintenance and system enhancement projects will require an IRB approval to proceed
in the Determine System Need phase.
Deliverables
Determine
Need
Define
Requirements
Develop
Design
Build
Components
Evaluate
Readiness
Deploy
System
Needs Statement
Change Request
Create
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 123
Deliverables
Determine
Need
Define
Requirements
Develop
Design
Build
Components
Evaluate
Readiness
Deploy
System
IT Investment Analysis
Package
Create
Feasibility Study
Create
Cost Benefit Analysis
Create
User Requirements Document
Project Plan
Update
Update
Update
Update
Configuration
Management Plan
Update
Update
Update
Update
Quality Assurance
Plan
Update
Update
Update
Update
Risk Matrix
Update
Update
Update
Update
Data Specification
Update
Update
Software Requirements
Specification
Update
Update
Requirements Traceability
Matrix (RTM)
Update
Update
Update
Update
Test Plan (Unit & Integration)
Update
Training Plan
Update
Software Design Description
Update
Database Design Description
Update
Information Systems Security
Plan
Update
Version Description Document
Update
Verification, Validation &
Testing Plan
Update
Installation/Conversion Plan
Update
Test Results & Evaluation
Report (Unit & Integration)
Create
Test Results & Evaluation
Report (VV&T)
Create
Operations Manual
Create
Update
User Guides
Update
Update
Training Materials
Update
Update
System Assessment and
Authorization
Update
Phase Exit Review Package
Create
Create
Create
Create
Create
System Sign-off Package
Create
Legend : Create Create the documentation, Update Update the documentation
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 124
APPENDIX F: SCRUM PROCESS DETAILS
The Scrum process is comprised of the following steps:
A. Determine Systems Need / Idea Proposed (Appendix F.1)
B. Developing and Prioritizing a List of Functionality (Appendix F.2)
C. Sprint Planning Meeting (Appendix F.3)
D. Daily Scrum (Appendix F.4)
E. Sprint Functionality Review (Appendix F.5)
F. Monthly Business-related Performance Metric Reviews (Appendix F.6)
A diagram of the Scrum process (Figure 2) is presented below:
Figure 2: Scrum Process
The Technical Project Manager can be a certified Scrum Master or have a certified Scrum
Master assigned to the team reporting to the Technical Project Manager. The Scrum Master
simultaneously functions as coach, advisor, mentor, and compliance monitor for the Scrum
Team. The Scrum Master focuses on providing the best possible circumstances for realizing the
goals fixed for the current Sprint. They do this by removing impediments to the team, elevating
issues they cannot resolve, acting as an intermediary with people outside the team so the
designers and developers can work undisturbed, and facilitating Scrum Meetings. After each
Sprint, the Scrum Master conducts a Sprint Retrospective an Evaluation Meeting with the team
during which experiences and conclusions are reviewed to improve future sprints and overall
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 125
team motivation.
All team members agreed during the Sprint planning meeting to build all of the functionality that
was allocated to the current Sprint. Senior developers are motivated by the challenge to do so.
The Product Owner has to provide the needed input when developers need clarification.
All templates or process documents that are referenced in the OPM SDLC can be utilized in the
Agile process. It is recognized that there will be alternative Agile documentation that Project
Teams will wish to utilize. If alternative Agile documentation methods are used, they must
convey the same information that the current waterfall templates and process documents require.
These Agile documentation methods (i.e., templates, etc.) must be reviewed with the Business
Project Manager or Business Program Manager before implementation. Upon approval of the
Agile documentation methods, the deliverables must be provided to the Business Project
Manager or Business Program Manager as appropriate. Waiver and deviation from the OPM
SDLC is not required when alternative Agile documentation methods are used.
Appendix F.1 Determine Systems Needs / Idea Proposed
The original idea or need for the system might be concrete or vague. It might be expressed in the
form of business terms. A functionlevel description can be developed as part of the Scoping
Phase, but not to the depth of detail that the customer requires. It is not likely to be expressed in
system terms. But just like in the waterfall methodology, the user can document the idea in a
Needs Statement or Change Request. Currently within the Agile community, there is a
preference in using a story board or user story to convey the need. If the need is accepted,
approval must be obtained from the appropriate approvers as outlined in Section 4.2 Section
“SDLC Phases” above.
Appendix F.2 Develop and Prioritize Product Backlog
The Product Owner is responsible for developing a list of all desired features and changes, which
is called the Product Backlog (PB). It helps the team understand more detail about the idea and
helps them form some ideas about how to approach the project. Since the Product Owner (PO)
maintains this list, it allows the PO to add, remove and re-prioritize items in the PB to account
for changing priorities in the work place and mission goals. These changes do not affect the
current Sprint Backlog.
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 126
Appendix F.3 Sprint Planning Meeting Process
This is a meeting with two distinct parts.
In the first part, the Product Owner presents the prioritized Product Backlog to the team. This is
the opportunity for the team to ask questions to clarify each piece of functionality and provides
the initial commitment to how much work can be completed in the Sprint.
In the second part, the team decomposes the stories into tasks and confirms the scope of the
current Sprint. A Sprint is the iterative development cycle of the committed functionality. The
team then develops the highlevel plan as to how it will accomplish the Sprint. The work to be
done is captured in the Sprint Backlog. The Sprint Backlog is the current list of functionality that
is the scope of the current Sprint.
Appendix F.4 Daily Scrum Process
Each day during the sprint, a project status meeting occurs. This is called a daily scrum, or the
daily standup. Daily scrums serve to synchronize the work of team members as they discuss the
work of the sprint. This meeting has specific guidelines:
The meeting starts precisely on time.
All are welcome, but normally only the Scrum Master, Product Owner and Team
members speak.
The meeting is limited to 15 minutes
The meeting should happen at the same location and same time every day
During the meeting, each team member answers three questions:
What have you done since yesterday?
What are you planning to do today?
Do you have any problems that would prevent you from accomplishing your goal?
It is the role of the Scrum Master to facilitate resolution of these impediments with input from
the Product Owner, although the resolution should occur outside the Daily Scrum in order to
keep the daily meeting under 15 minutes if needed.
Appendix F.5 Sprint Functionality Review Process
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 127
At the end of the Sprint, the team demonstrates the solution to the customer. They discuss any
functionality change requests with the customer and add the requests to the Product Backlog. If
the customer accepts the solution, the Product Owner and the Scrum Master along with
appropriate additional approvers (i.e., Chief Architect, IPT members, etc.) must approve the
sprint results using the appropriate SDLC Phase Exit Review procedures and documentation
(defined in Section 4.2 “SDLC Phases” above) before authorizing the initiation or planning of
further sprints. The Product Backlog is updated and reprioritized for the next Sprint. This entire
process continues until the Product Backlog is empty or the customer makes the determination
that the current Sprint version is the final solution and does not wish for the project to continue
any further.
Appendix F.6 Monthly Business-related Performance Metric Reviews
The OPM Baseline Management Policy requires that a project must use a performance
management system, such as an Earned Value Management System for major investments. The
Performance Management System must track both government and contractor efforts, regardless
of contract type. The Performance Management System shall create the data necessary to
populate the IT Dashboard cost and schedule tables on a monthly basis for major investments.
This will require that Scrum milestones be defined and the status of the milestones be reported
on a monthly basis through the implementation of Stage Gate Reviews.
Stage Gate Reviews are conducted by the IT governance organization, investment stakeholders
and the Project Team to ensure that projects are fully complying with IT project management
requirements. The Project Team can bundle several sprints into a single Stage Gate Review
which will be analyzed on a monthly basis especially if using Earned Value Management. The
reviews must analyze the project performance against baselines and may require corrective
action plans or rebaselining as appropriate to the situation. Most importantly, Stage Gate
Reviews determine that the project is ready to advance to the next sprint, bundle of sprints or
phase. The Stage Gate Reviews will provide information to the Business Program Manager or
Business Project Manager so that they can make the decision whether the program or project
should be terminated.
OPM System Development Life Cycle Policy and Standards
Version 1.1
April 2013 Page 128